Increasing the transparency of how we select highway construction projects

Non-National Highway System pavement projects

MnDOT Metro District

Scoring criteria for non-national highway system pavement projects. Out of 100 possible points, 60 points are based on the timing of the improvement, 10 points are based on traffic volume, 10 points are based on truck volume, 10 points are based on other infrastructure needs, 5 points are based on the potential to transfer jurisdiction of the road to a city or county, and 5 points are based on the miles covered by the project.

Learn more about how MnDOT evaluates and selects pavement projects

MnDOT scores stretches of highway based on a pavement need when selecting projects to include in the 10-year Capital Highway Investment Plan. Pavement needs on the National Highway System (NHS) are scored and selected separately from pavement needs off the system. MnDOT’s approach to managing pavements follows the guidance and targets in the Transportation Asset Management Plan and the planned outcomes in MnSHIP.

Pavement projects are scored and selected within each district. Potential pavement projects are identified by the Highway Pavement Management Application (HPMA) and by MnDOT District staff.

Once selected, MnDOT then identifies and evaluates alternatives and other needs, legal requirements, issues and opportunities in coordination with local partners, and considers public input. In the process, non-pavement work may be added to a pavement project or a pavement project may be combined with a nearby bridge project. The department follows a context-sensitive complete streets approach, which considers the needs of all users. The final project may address a substantial number of needs beyond the pavement need that precipitated the project. Projects may move years based on local coordination, project delivery, timing of other nearby construction projects, and funding shifts.

What was selected

Related links

How the projects scored

The construction costs shown on this list represent a very rough estimate based on limited information available at the time selection decisions were made. Actual construction and delivery costs will change over time as projects go from a concept through the project development process and are eventually constructed. View more detailed scores (Excel).

Last updated October 2023

Score Route Description High level construction cost estimate for planning purposes Year Planned (FY) Comments
13.5 MN284 Resurface Hwy 284 from 122nd Street to Sparrow Road.   $6,862,524   2031  
15 MN56 Resurface road from the Goodhue/Dakota County line to MN 50/US 52    $7,252,392   2033 Projected poor pavement conditions. 2020 RSL 4 to 11 years. 
18 MN77 Resurface Hwy 77 (Cedar) from 138th St (CR 23) to the Dakota-Hennepin County line in Apple Valley    $45,096,000   2026, 2027   Poor pavement conditions. 
21 MN20 Resurface road from MN 19 to MN 50    $5,000,000   2032 Poor pavement conditions. 2020 RSL 2 to 10 years.
21 MN95 Resurface Hwy 95 from Jct Hwy 8 to Hwy 97.   $15,000,000   2032  
24 MN5 Resurface road from County Rd 11 to MN 41   $5,000,000   2032 Projected poor pavement conditions.
25 MN51 Resurface road from W 7th to Dayton Ave    $10,099,747   2030 Poor pavement conditions.
27 MN13 Medium mill and overlay from Connelly Pkwy to old MN101 $2,000,000 Not selected Program limited by available funding.
27 MN13 Medium mill and overlay from MN13 to MN149 $200,000 Not selected Program limited by available funding.
29 US61 Medium mill and overlay from 267th St to I35 $300,000 Not selected Program limited by available funding.
29 MN65 Medium mill and overlay from south of E Moore Lake Dr to Anoka County Road 10 $3,100,000 Not Selected  Program limited by available funding.
31 MN7 Repair road from W end of 494 bridge. to I-494    $500,000   2032 Poor pavement conditions.
32 US61 Medium mill and overlay from RP155 to 170th ST $200,000 Not selected Program limited by available funding.
33 US61 Resurface road from 3rd St. to US 10    $6,250,000   2032 Poor pavement conditions.
34 US61 Resurface road and repair bridge 19075 on Hwy 61 from N Jct Hwy 316 to 4th St in Hastings   $10,867,000   2027   Poor pavement conditions. 
35 MN97 Reconstruct road, trail on Hwy 97 (Scandia Trail N) from 0.24 miles east of I-35/Hwy 61 (Forest Blvd N) and add turn lanes and lighting on Hwy 97 (Scandia Trail N) from west of Everton Ave N to Hwy 61 (Forest Blvd N) in Forest Lake    $15,884,000   2025   Geometrics. Poor pavement conditions. Ped/bike trail needs. 
39 MN97 Minor rehabilitation within roundabout at US61 100000 Not selected Newer concrete roundabouts.
40 MN13 Medium mill and overlay from Washburn Ave to I-35 $1,400,000 Not Selected  Program limited by available funding.
43 MN13 Reconstruct road from Eagle Creek Ave to County Rd 42 $3,500,000 Not selected Projected poor pavement conditions.
43 MN5 Medium mill and overlay from I-494 to Hennepin/Ramsey County line $3,900,000 Not Selected  Program limited by available funding.
43 MN65 Repair road from 217th Ave to Anoka-Isanti County line $18,000,000 Not Selected  Repair early distresses.
44 MN95 Medium mill and overlay from I-94 to .5 miles S of I-94 $500,000 Not selected Program limited by available funding.
46 MN101 Repair and resurface road, update guardrail and median barrier, signal replacement, ADA curb ramps, drainage, turn lane extension and pork chop island realignment on Hwy 101 from I-94 in Rogers to CR 38 (70th St NE) in Otsego    $12,674,000   2027   Poor pavement conditions. 
47 MN19 Resurface road from the Leseuer/Scott county line to the Scott/Rice county line - Future Project $2,700,000 Not selected  
47 MN95 Thin mill and overlay from I-94 to Mulberry St 18000000 Not selected Projected poor pavement conditions. 2020 RSL is 4 to 6 years.
55 MN5 Medium mill and overlay from Carver County Road 10 to Oak Ave $200,000 Not selected Program limited by available funding.
55 MN121 Medium mill and overlay from I35W to Pedestrian bridge $300,000 Not Selected  Program limited by available funding.
57 MN149 Medium mill and overlay from I-494 to Mendota Heights Rd $600,000 Not selected Program limited by available funding.
57 MN50 Medium mill and overlay from MN3 to US52 $4,300,000 Not selected Program limited by available funding.
57 US61 Medium mill and overlay from RP163 to 250TH St $200,000 Not selected Program limited by available funding.
58 MN149 Medium mill and overlay from Mendota Heights Rd to MN5/7th St 2500000 Not selected Program limited by available funding.
59 MN5 Medium mill and overlay from MN25 to Carver  County Road 10 $1,900,000 Not selected Program limited by available funding.
60 MN77 Medium mill and overlay from Minnesota River bridge to I-494 $3,100,000 Not Selected  Program limited by available funding.
60 MN5 Repair road from MN 41 to Eden Prairie Rd   $16,609,000   2033 Much of this is older PCC with ride impacted by isolated crack slabs, some of which are from subsurface utility issues.
61 MN95 Medium mill and overlay from Valley Creek to Bailey Rd 1200000 Not selected Program limited by available funding.
61 MN101 Minor concrete pavement repair, from CR 38 to US 10 $3,500,000 Not Selected  Poor pavement conditions. 
62 MN243 Medium mill and overlay from MN95 to St Croix River $700,000 Not selected Program limited by available funding.
62 MN95 Medium mill and overlay from I-94 to Valley Creek 700000 Not selected Program limited by available funding.
63 US61 Medium mill and overlay from 70th St to Carver Ave $4,400,000 Not Selected  Program limited by available funding.
63 US61 Medium mill and overlay from Trailer Pk entrance to 170th St  $1,000,000 Not selected Program limited by available funding.
64 MN149 Medium mill and overlay from Albano Tr to MN55 $2,600,000 Not selected Program limited by available funding.
64 MN95 Medium mill and overlay from Bailey Rd to US61 4100000 Not selected Program limited by available funding.
64 MN95 Medium mill and overlay from Sunrise River to Taylors Falls $6,600,000 Not selected Program limited by available funding.
64 US61 Medium mill and overlay from 170th St to MN97 $1,900,000 Not selected Program limited by available funding.
65 MN13 Medium mill and overlay from Dakota County Line to Washburn Ave $700,000 Not Selected  Program limited by available funding.
65 MN5 Medium mill and overlay from .2 miles W of Carver County Road 10 to .2 miles east of Carver County Road 10 $200,000 Not selected Program limited by available funding.
66 MN7 Medium mill and overlay from I-494 to Shady Oak Road 1000000 Not Selected  Program limited by available funding.
66 MN95 Medium mill and overlay from St Croxi Trail to Point Rd 1000000 Not selected Program limited by available funding.
66 MN13 Medium mill and overlay from .4 miles west of Dakota Ave to .2 miles east of Dakota ave $700,000 Not Selected  Program limited by available funding.
67 MN7 Medium mill and overlay from Railroad bridge to MN100 $900,000 Not Selected  Program limited by available funding.
67 US61 Medium mill and overlay from Chisago County Road 31/22 to 267th St  $200,000 Not selected Program limited by available funding.
67 US61 Medium mill and overlay from I-94/Mounds Blvd to MN5/7th St $700,000 Not selected Program limited by available funding.
68 MN95 Medium mill and overlay from Mulberry to St Saint Croix Trail $500,000 Not selected Program limited by available funding.
68 US61 Medium mill and overlay from 250th St to Chisago County Road 31/32 $700,000 Not selected Program limited by available funding.
68 US61 Medium mill and overlay from White Bear Lake Cr to Frenchman Rd $1,800,000 Not selected Program limited by available funding.
68 MN13 Medium mill and overlay from MN282 to Scott County Road 21 roundabout $2,000,000 Not selected Program limited by available funding.
68 MN65 Medium mill and overlay from 26th St to 10th ST $1,300,000 Not Selected  Program limited by available funding.
68 MN101 Medium mill and overlay from NB split with US169 to SB merge with US169  $3,400,000 Not Selected  Program limited by available funding.
69 MN149 Medium mill and overlay from MN3 to Albano Tr $200,000 Not selected Program limited by available funding.
69 US61 Medium mill and overlay from Frenchman Rd to Trailer Pk entrance $400,000 Not selected Program limited by available funding.
69 MN3 Resurface road from 145th St to MN 149   $4,622,021   2033  
69 MN5 Medium mill and overlay from Birch St to Scandia Rd $1,100,000 Not selected Program limited by available funding.
70 MN51 Resurface road and ADA improvements on Hwy 51 (Snelling Ave) from Grand Ave to St Clair Ave in St Paul    $2,183,000   2024   Poor pavement conditions. 
70 MN65 Resurface road from NE 37th Ave CL to 53rd Ave NE    $5,270,000   2033 Projected poor pavement conditions.
70 MN101 Resurface road from Hwy 5 (W 78th St) to CSAH 62/Townline Rd, resurface road, drainage repairs and ADA improvements on Hwy 101 (W 192nd Ave) from Hwy 5 to Townline Rd in Chanhassen/Eden Prairie    $1,887,000   2024   Poor pavement conditions. 
71 MN13 Medium mill and overlay from Yankee Doodle Rd to I494 $900,000 Not selected RQI does not match on the ground conditions
71 MN3 Medium mill and overlay from MN149 to Bridge 19045 $1,300,000 Not selected Program limited by available funding. 2020 Remaining service life 0 to 7 years. Short PCC section driving down Remaining service life.
72 MN7 Resurface road from TH 25 to Carver County Line    $10,522,000   2033 Projected poor pavement conditions.
72 MN95 Medium mill and overlay from Point Rd to I-94 $2,800,000 Not selected RQI does not match on the ground conditions
72 US61 Medium mill and overlay from US 10 to 70th St $8,500,000 Not Selected  Program limited by available funding.
72 US61 Medium mill and overlay from MN96 to White Bear Lake CL $1,000,000 Not selected RQI does not match on the ground conditions
72 MN13 Medium mill and overlay from Dakota to Washburn ave $1,600,000 Not Selected  Program limited by available funding.
72 MN3 Reconstruct the road from Amana Trail to MN 62   $10,400,000   2033  
73 MN7 Medium mill and overlay from Texas Ave to Railroad Bridge  700000 Not Selected  RQI does not reflect on the ground conditions
73 MN13 Medium mill and overlay legs to and from Scott County Road 21 roundabout $300,000 Not selected Very new pavement either side of new roundabout.
73 MN21 Medium mill and overlay from 7th St to Sawmill Rd $4,300,000 Not selected RQI does not match on the ground conditions
73 MN3 Medium mill and overlay from Bridge 19045 to Mendota Rd $500,000 Not selected RQI does not match on the ground conditions
74 MN284 Reconstruct road from US 212 to 122nd St   $4,480,000   2031 Many issues with this pavement including geometric and ADA needs. RQI data not reflective of the poor pavement conditions.
74 MN51 Medium mill and overlay from Grey Fox Rd to I694 $300,000 Not selected Recently repaired in 2021
74 MN13 Medium mill and overlay from MN13 to Dakota Ave $700,000 Not Selected  Program limited by available funding.
76 MN50 Resurface Hwy 50 (240th St) from Hwy 52 (Emery Ave/Rochester Blvd) in Hampton to Hwy 61 in Douglas Township   $7,196,000   2026   Poor pavement conditions. 
76 MN21 Medium mill and overlay from Sawmill Rd to Mill St $300,000 Not selected RQI does not match on the ground conditions
77 MN120 Resurface Hwy 120 from BrookView Dr to 4th St.   $2,112,476   2032 Projected poor pavement conditions.
77 MN21 Medium mill and overlay from MN19 to Scott County Road 37 $300,000 Not selected Program limited by available funding. Short urban section.
77 MN3 Resurface road from Rice County line to MN 50    $10,207,680   2029 Poor pavement conditions. 
78 MN7 Medium mill and overlay from Shady Oak Rd to Texas Ave $3,000,000 Not Selected  RQI does not reflect on the ground conditions
78 MN13 Medium mill and overlay from  Scott County Road 42 to Connelly Pkwy $700,000 Not selected RQI does not match on the ground conditions
78 MN3 Medium mill and overlay from MN50 to Dakota County Road 58 $3,300,000 Not selected Program limited by available funding. 2020 Remaining service life is predicted 9 to 15 years.
78 MN65 Repair pavement and replace bridges 6817 ( new bridge # 02X06) and 9417 (02X07) over Coon Creek, replace box culvert bridge 9465 and ADA, signal replacement on Hwy 65 (Central Ave) from CR 10 (Mounds View Blvd) in Spring Lake Park to 217th Ave in East Bethel, cable median barrier from Bunker Lake Blvd to 237th    $40,546,000   2024   Poor pavement conditions. 
78 MN65 Resurface road form 53rd Ave NE to South Moore Lake Dr $3,000,000 Not Selected  Poor pavement conditions.
79 MN51 Resurface, guardrail and ADA on Hwy 51 (Snelling Ave N) from north end of bridge over MN 36 in Roseville to 0.1 mile north of Grey Fox Rd in Arden Hills   $6,678,000   2026   Poor pavement conditions. ADA, bike/ped, and drainage needs. 
79 MN96 Resurface road from US 61 to MN 95 $10,280,000 Not selected Projected poor pavement conditions.
81 MN7 Resurface road from the Hennepin/Carver County line to Division St and replace bridge over County Road 82.   $31,280,000   2029 Recent resurfacing project. Construction in progress at time of DIV run. Roughness at intersection contribute to poor ride.
81 MN97 Resurface road from US61 to MN95   $8,957,692   2032 Poor pavement conditions. Project has been deferred several times. 
81 US61 Thin mill and overlay from Goodhue/Dakota County Line to MN316 $9,000,000 Not Selected Projected poor pavement conditions.
81 MN5 Medium mill and overlay from Hennepin/Ramsey County Line to Munster Ave $600,000 Not selected Not selected. Program limited by available funding. Short section of PCC before and after river bridge. Bridge surface is pulling average RQI down.
82 US61 Resurface road, traffic signals, pedestrian improvements, drainage, curb and gutter and replace bridge #96093 on Hwy 61 from 0.2 miles north of Carver Ave to east junction of I-94 in St Paul.   $10,000,000   2028 Poor pavement conditions.
87 MN95 Resurface Hwy 95 from Hemingway Ave to Manning Bridge over Sunrise River.   $7,009,720   2031 Poor pavement conditions. 2020 RSL 0 to 5 years.
90 MN95 Resurface Hwy 95 from the Isanti county line to Hemingway Ave    $9,002,400   2028  
90 MN95 Resurface road from MN 97 to MN 36   $13,000,000   2030 Projected poor pavement conditions.
90 MN13 Medium mill and overlay from I-35W to Yankee Doodle Rd $6,900,000 Not selected RQI does not match on the ground conditions
61 MN101 Minor concrete pavement repair, from CR 38 to US 10 $3,500,000 Not Selected  Poor pavement conditions. 