Increasing the transparency of how we select highway construction projects

National Highway System pavement projects

MnDOT Metro District

Scoring criteria for national highway system pavement projects. Out of 100 possible points, 60 points are based on the timing of the improvement, 10 points are based on traffic volume, 10 points are based on truck volume, 10 points are based on other infrastructure needs, 5 points are based on network designation, and 5 points are based on the miles covered by the project.

Learn more about how MnDOT evaluates and selects pavement projects

MnDOT scores stretches of highway based on a pavement need when selecting projects to include in the 10-year Capital Highway Investment Plan. Pavement needs on the National Highway System (NHS) are scored and selected separately from pavement needs off the system. MnDOT’s approach to managing pavements follows the guidance and targets in the Transportation Asset Management Plan and the planned outcomes in MnSHIP.

Pavement projects are scored and selected within each district. Potential pavement projects are identified by the Highway Pavement Management Application (HPMA) and by MnDOT District staff.

Once selected, MnDOT then identifies and evaluates alternatives and other needs, legal requirements, issues and opportunities in coordination with local partners, and considers public input. In the process, non-pavement work may be added to a pavement project or a pavement project may be combined with a nearby bridge project. The department follows a context-sensitive complete streets approach, which considers the needs of all users. The final project may address a substantial number of needs beyond the pavement need that precipitated the project. Projects may move years based on local coordination, project delivery, timing of other nearby construction projects, and funding shifts.

What was selected

Related links

How the projects scored

The construction costs shown on this list represent a very rough estimate based on limited information available at the time selection decisions were made. Actual construction and delivery costs will change over time as projects go from a concept through the project development process and are eventually constructed. View more detailed scores (Excel).

Last updated October 2022

Score Route Description  High level construction cost estimate for planning purposes  Year Planned (FY) Comments
29 MN610 Medium mill and overlay from Elm Creek Blvd to US 169 $2,700,000 Not Selected  Program limited by available funding.
31 MN41 Repair road from Count Hwy 61 to Hundertmark Rd $12,980,000 2032 Poor pavement conditions.
32 MN280 Unbonded overlay from Como to I-35W $23,400,000 2027 Poor pavement conditions.
33 MN25 Resurface road from US 169 to Minnesota River bridge $2,400,000 2031 Poor pavement conditions. 
35 MN55 Medium mill and overlay from General Mills Blvd to Schaper Rd $2,100,000 Not Selected  Program limited by available funding.
46 MN55 Resurface road from the Wright-Hennepin county line to Fernbrook $22,000,000 2028 Poor pavement conditions.
53 MN62 Resurface road from 28th Ave to MN 55 $10,000,000 2027 Poor pavement conditions. 
55 MN62 Medium mill and overlay from Clearwater Dr to .32 miles east of Clearwater $400,000 Not Selected  Program limited by available funding.
56 MN610 Medium mill and overlay from I-94 to Elm Creek Blvd $2,400,000 Not Selected  Program limited by available funding.
57 MN62 Repair pavement on Hwy 62 between Hwy 13 and 0.2 miles east of I-35E in Mendota Heights $5,172,000 2024 Poor pavement conditions. 
59 MN25 Resurface road from US 212 to MN 5 $2,600,000 2031 Projected poor pavement conditions. 2020 RSL 11 years.
59 MN252 Medium mill and overlay from I-94 WB in Brooklyn Center to .4 miles north of I-94 $500,000 Not Selected  Program limited by available funding.
59 MN36 Medium mill and overlay from Washington Ave to MN95  $1,800,000 Not Selected  Program limited by available funding.
61 MN62 Medium mill and overlay from Portland Ave bridge to .154 miles east of Portland bridge $200,000 Not Selected  Program limited by available funding.
62 MN41 Resurface Hwy 41 from 0.23 miles north of Pioneer Trl in Chaska to Hwy 5 (Arboretum Blvd) in Chanhassen $1,834,000 2023 Poor pavement conditions. 
62 MN41 Medium mill and overlay from MN5 to MN7 $1,100,000 Not selected Program limited by available funding.
62 MN55 Resurface pavement, construct trail and turn lane reconstruction at Dahlberg Drive on Hwy 55 (Olson Memorial Pkwy) from 0.2 miles west of Hwy 100 in Golden Valley to west end of bridge over BNSF tracks in Mpls $3,337,000 2025 Poor pavement conditions. 
62 MN55 Medium mill and overlay from Pine Bend Trail to Hastings CL $3,500,000 Not Selected  Program limited by available funding.
62 MN62 Medium mill and overlay from Clearwater to Tracy Ave $3,300,000 Not Selected  Program limited by available funding.
63 MN55 Repair road from County Rd 63 to US 52 $7,000,000 2028 Poor pavement conditions.
63 MN62 Medium mill and overlay from Portland Ave to 28th ave $1,800,000 Not Selected  Program limited by available funding.
64 MN55 Resurface Road from Highway 52 to US 61 $19,500,000 2030 Poor pavement conditions.
64 MN610 Repair and resurface MN 610 from Mississippi River to Coon Rapids Blvd $15,000,000 2028  
65 MN55 Resurface roadway, sidewalk ADA and signal replacement on MN 55 west of BNSF bridge to I-94 $5,800,000 2026 Poor pavement conditions. Frontage road and ADA needs.
65 MN62 Medium mill and overlay from I-494 to Clearwater Dr $300,000 Not Selected  Program limited by available funding.
66 MN36 Resurface pavement on Hwy 36 from Jct I-35W in Roseville to just east Edgerton in Maplewood/Little Canada and extend auxiliary lane and reconstruct ramp at I-35W SB/Cleveland Ave to Hwy 36 EB $12,352,000 2025 Poor pavement conditions; maintenance liability. 
66 MN610 Repair road from US 169 to Mississippi River $20,000,000 2031 Projected poor pavement conditions.
67 MN41 Medium mill and overlay from US169 to Pioneer Trail $1,200,000 Not Selected  Program limited by available funding.
68 MN252 Resurface road from I-94 to 85th St $8,500,000 2031 Poor pavement conditions. Coordination with 252 CoC project.
69 MN252 Medium mill and overlay from 85th to MN610 $1,100,000 Not Selected  Program limited by available funding.
69 MN316 Resurface pavement on Hwy 316 (Red Wing Blvd) from south jct Hwy 61 to Tuttle in Hastings and widen shoulder at various locations on Hwy 316 (Red Wing Blvd) in Ravenna Township $6,222,000 2025 Poor pavement conditions. 
69 MN62 Medium mill and overlay from I-35E to US52 $3,500,000 Not selected Program limited by available funding.
71 MN25 Medium mill and overlay from Scott County line to MN5 $7,100,000 Not selected RQI does not match on the ground conditions
72 MN280 Repair pavement, guardrail, rehab 13 bridges on Hwy 280 from junction with I-94 in St Paul to junction with I-35W in Roseville and close median on Hwy 280 at Broadway in Lauderdale and install signals at Kosata Ave and ramps with Energy Park Dr in St Paul $25,763,000 2026, Future Poor pavement conditions; coordinate with bridge work. 
73 MN62 Medium mill and overlay from 43rd Ave to Mendota Bridge $1,600,000 Not Selected  Program limited by available funding.
74 MN25 Medium mill and overlay from MN5 to MN7 $3,900,000 Not Selected  Program limited by available funding.
74 MN62 Medium mill and overlay from Tracy ave bridge to Penn Ave Bridge $3,200,000 Not Selected  Program limited by available funding.
75 MN41 Resurface road including pavement marking and guardrail work at Hwy 41 intersection with Peavey Rd in Chaska $82,000 2023  
76 MN100 Medium mill and overlay from I-494 to Cedar Lake Bridge $10,900,000 Not Selected  RQI does not reflect on the ground conditions
76 MN610 Medium mill and overlay from MN252 to Mississippi River Bridge  $1,000,000 Not Selected  Program limited by available funding.
80 MN62 Resurface road from Penn Ave to Portland Ave $11,000,000 2032 Repair early distresses.
82 MN55 Repair pavement and bridge culverts 6732 and 6745 and add turn lane on Hwy 55 (Olson Memorial Hwy) from Old Rockford Rd in Plymouth to just east General Mills Blvd in Golden Valley $18,102,000 2024 Poor pavement conditions. 
96 MN100 Resurface road from the Cedar Lake Rd to I-694 $18,000,000 2027 Poor pavement conditions; preventive maintenance. 