National Highway System pavement projects
MnDOT Metro District
MnDOT scores stretches of highway based on a pavement need when selecting projects to include in the 10-year Capital Highway Investment Plan. Pavement needs on the National Highway System (NHS) are scored and selected separately from pavement needs off the system. MnDOT’s approach to managing pavements follows the guidance and targets in the Transportation Asset Management Plan and the planned outcomes in MnSHIP.
Pavement projects are scored and selected within each district. Potential pavement projects are identified by the Highway Pavement Management Application (HPMA) and by MnDOT District staff.
Once selected, MnDOT then identifies and evaluates alternatives and other needs, legal requirements, issues and opportunities in coordination with local partners, and considers public input. In the process, non-pavement work may be added to a pavement project or a pavement project may be combined with a nearby bridge project. The department follows a context-sensitive complete streets approach, which considers the needs of all users. The final project may address a substantial number of needs beyond the pavement need that precipitated the project. Projects may move years based on local coordination, project delivery, timing of other nearby construction projects, and funding shifts.
What was selected
Related links
- Metro District project selection
- Metro District Non-National Highway System pavement projects
- Metro District Urban pavement projects
How the projects scored
The construction costs shown on this list represent a very rough estimate based on limited information available at the time selection decisions were made. Actual construction and delivery costs will change over time as projects go from a concept through the project development process and are eventually constructed. View more detailed scores (Excel).
Last updated October 2021
Score | Route | Description | High level construction cost estimate for planning purposes | Year Planned (FY) | Comments |
---|---|---|---|---|---|
95 | I94 | Medium mill and overlay from Nicollet Ave Bridge to Western Ave | $53,300,000 | 2031 | Projected poor pavement conditions. |
95 | I494 | Minor rehabilitation from France Ave to US12 | $24,900,000 | 2029 | Preventive maintenance. |
94 | I35E | Unbonded overlay from I35W/E to Lone Oak Rd | $83,500,000 | 2031 | Projected poor pavement conditions. SP1982-207 |
94 | I694 | Minor rehabilitation from Washington County Road 49 to US61 | $12,000,000 | 2031 | Repair early distresses. |
93 | I35E | Medium mill and overlay from Lone Oak Rd to Bridge over Marie Ave | $21,200,000 | 2028 | Projected poor pavement conditions. |
91 | US169 | Medium mill and overlay from MN55 to 77th Ave | $7,800,000 | Not Selected | Program limited by available funding. |
91 | I494 | Major rehabilitation from Minnesota River Bridge to 24th Ave | $12,800,000 | 2023 | Poor pavement conditions. Coordinate with 494 Corridors of Commerce project. SP 2785-433. |
91 | US52 | Medium mill and overlay from I-494 to Lafayette bridge | $5,100,000 | Not Selected | Program limited by available funding. |
90 | I94 | Medium mill and overlay from I-494 to Nicollet Ave bridge | $27,400,000 | Not Selected | RQI does not reflect on the ground conditions |
90 | I494 | Medium mill and overlay from 24th Ave to France Ave | $29,400,000 | 2027 | Poor pavement conditions. Coordinate with 494 Corridors of Commerce project. 1785-424 |
90 | I35E | Minor rehabilitation from Little Canada Road to Ramsey County Road E bridge | $12,000,000 | 2031 | Repair early distresses. |
90 | I35W | Medium mill and overlay from MN13 to 106th St | $4,000,000 | Not Selected | Construction of I-35W River Crossing at time of DIV run, bypass pavement is rough. |
90 | I35W | Medium mill and overlay from 4th St bridge to Ramsey County Road C | $8,000,000 | Not Selected | RQI does not reflect on the ground conditions |
88 | I94 | Major rehabilitation from Western Ave to Mounds Blvd | $28,500,000 | 2022 | Very bad pavement condition; extra maintenance required. SP 6283-247. |
88 | I494 | Medium mill and overlay from 5th Ave to Dakota/Hennepin County Line | $13,600,000 | Not Selected | RQI does not reflect on the ground conditions |
88 | I394 | Medium mill and overlay from MN100 to Washington Ave N | $3,200,000 | Not Selected | Recent major rehab. Low RQI attributed largely to high percentage of bridge decks. Also, after a recent lane reconfiguration of WB, part of the outside lane is on rough bituminous shoulder. |
86 | I394 | Thin mill and overlay from I-494 to MN100 | $26,800,000 | 2029 | Projected poor pavement conditions. |
85 | I494 | Medium mill and overlay from Hardman bridge to 5th Ave | $2,200,000 | Not Selected | RQI does not reflect on the ground conditions |
85 | I35E | Major rehabilitation from 10th St Bridge to University ave Bridge | $1,100,000 | 2022 | Poor pavement conditions. SP 6283-247. |
85 | I35W | Medium mill and overlay from 27th St to Washington Ave Bridge | $8,300,000 | 2029 | Projected poor pavement conditions. |
83 | I94 | Unbonded concrete overlay from Ramsey/Washington County Line to west end of St Croix River bridge | $117,800,000 | 2023 | Poor pavement conditions. SP 8282-132. |
83 | US169 | Medium mill and overlay from MN 62 to MN55 | $6,300,000 | Not Selected | Program limited by available funding. |
83 | I35W | Minor rehabilitation from 66th St to 42nd St bridge | $5,700,000 | 2031 | Repair early distresses. |
83 | I694 | Medium mill and overlay from I-494/694 to Lexington Ave | $2,900,000 | Not Selected | This segment consists of older concrete pavement with recent CPR and fairly new UBOLs. 2020 RQI is very good to excellent. Minor CPR is ongoing due to dowel bar issues. |
82 | MN55 | Thick mill and overlay from Fernbrook to General Mills Blvd | $10,200,000 | 2024 | Poor pavement conditions. SP 2723-144. |
81 | MN7 | Medium mill and overlay from Six mile creek to Division St | $5,800,000 | Not Selected | Program limited by available funding. Recent resurfacing project. Construction in progress at time of DIV run. Roughness at intersection contribute to poor ride. |
81 | I494 | Medium mill and overlay from Tamarack bridge to Hardman bridge | $6,100,000 | Not Selected | RQI does not reflect on the ground conditions |
81 | I35W | Medium mill and overlay from Washington Ave bridge to 4th St Bridge | $1,600,000 | Not Selected | This is new pavement but is predominantly comprised of St. Anthony Falls bridge deck. 2020 RQI is excellent. |
79 | I35E | Unbonded overlay from I35W/E to Lone Oak Rd | $76,700,000 | 2030 | Projected poor pavement conditions. SP1982-207 |
79 | US10 | Thin mill and overlay from MN65 to I35W | $9,600,000 | 2027 | Poor pavement conditions; bad longitudinal joints. |
78 | MN7 | Medium mill and overlay from Shady Oak Rd to Texas Ave | $3,000,000 | Not Selected | RQI does not reflect on the ground conditions |
78 | MN65 | Thin mill and overlay from Bunker Lake Rd to 217th Ave | $5,100,000 | 2024 | Poor pavement conditions. SP 0208-165. |
78 | US169 | Medium mill and overlay and CPR from MN 21 to 173rd St W | $12,600,000 | 2024 | Poor pavement conditions. SP 7009-085. |
78 | I35W | Medium mill and overlay from 42nd st bridge to Chicago Ave Bridge | $6,500,000 | Not Selected | Construction of Lake St project at time of DIV run, bypass pavement is rough. |
77 | US61 | Medium mill and overlay from Carver Ave to I-94 | $23,100,000 | 2030 | Poor pavement conditions. |
77 | MN610 | $2,300,000 | Not Selected | Program limited by available funding. | |
77 | I35 | Medium mill and overlay from US 8 to MN95 | $15,700,000 | Not Selected | Program limited by available funding. Proposed thin overlay within next few years. |
76 | US169 | Medium mill and overlay from 77th Ave to 93rd Ave in Osseo | $5,600,000 | 2028 | Poor pavement conditions. |
76 | MN610 | Medium mill and overlay from MN252 to Mississippi River Bridge | $1,000,000 | Not Selected | Program limited by available funding. |
76 | US52 | Medium mill and overlay from Lafayette bridge to I-94 | $200,000 | Not Selected | Program limited by available funding. |
76 | US10 | Medium mill and overlay from Foley Blvd to MN56 | $4,100,000 | Not Selected | RQI does not reflect on the ground conditions |
76 | MN100 | Medium mill and overlay from Cedar Lake Bridge to I-894 | $31,900,000 | 2027 | Poor pavement conditions; preventive maintenance. SP 2735-212 |
76 | MN100 | Medium mill and overlay from I-494 to Cedar Lake Bridge | $10,900,000 | Not Selected | RQI does not reflect on the ground conditions. |
75 | MN65 | Medium mill and overlay from Anoka County Road 10 to Bunker Lake blvd | $5,400,000 | 2024 | Poor pavement conditions. SP 0207-110. |
75 | I35E | Medium mill and overlay from University Ave to Cayuga/Railroad Bridge | $2,100,000 | Not Selected | Program limited by available funding. Section is predominantly bridge decks. |
74 | MN62 | Medium mill and overlay from Tracy ave bridge to Penn Ave Bridge | $3,200,000 | Not Selected | Program limited by available funding. |
74 | US10 | Whitetop overlay from US169/MN47 to Creek Meadows bridge | $21,600,000 | 2030 | Projected poor pavement conditions. |
74 | MN25 | Medium mill and overlay from MN5 to MN7 | $3,900,000 | Not Selected | Program limited by available funding. |
74 | MN13 | Medium mill and overlay from MN13 to Dakota Ave | $700,000 | Not Selected | Program limited by available funding. |
73 | MN7 | Medium mill and overlay from Texas Ave to Railroad Bridge | $700,000 | Not Selected | RQI does not reflect on the ground conditions |
73 | MN62 | Medium mill and overlay from 43rd Ave to Mendota Bridge | $1,600,000 | Not Selected | Program limited by available funding. |
73 | MN65 | Minor rehabilitation from 217th Ave to Anoka/Isanti County line | $4,900,000 | 2029 | Repair early distresses. |
73 | US212 | Minor rehabilitation from Hennepin County Road 4 to I-494 | $13,200,000 | 2027 | Preventive maintenance. |
73 | MN55 | Medium mill and overlay from Mendota Bridge to Argenta Trail | $11,600,000 | 2022 | Poor pavement conditions. SP 1909-099. |
73 | US52 | Medium mill and overlay from Dakota County Road 42 to Clayton Ave | $800,000 | Not Selected | Program limited by available funding. |
73 | US10 | Medium mill and overlay from Cleveland RT/Jarvis LT to Fairoak Ave | $14,800,000 | 2027 | Poor pavement conditions. |
73 | I694 | Medium mill and overlay from County Road 10 to Anoka Isanti County Line | $1,000,000 | Not Selected | Under construction at time of DIV run. New concrete pavement at system interchange (94/494/694). |
72 | US61 | Medium mill and overlay from US 10 to 70th St | $8,500,000 | Not Selected | Program limited by available funding. |
72 | US169 | Medium mill and overlay from Catrerbury rd to Valley View Rd | $8,600,000 | Not Selected | Program limited by available funding. |
72 | US169 | Medium mill and overlay from Anderson Lakes Pkwy to Valley View Rd | $1,500,000 | Not Selected | Program limited by available funding. |
72 | MN610 | $1,500,000 | Not Selected | Program limited by available funding. | |
72 | I35E | Thin mill and overlay from bridge 9532 to 10th St bridge | $5,700,000 | 2028 | Projected poor pavement conditions. |
72 | MN55 | Medium mill and overlay from Wright/Hennepin County Line to Fernbrook | $21,500,000 | 2027 | Poor pavement conditions. |
72 | MN280 | Major rehabilitation from I-94 to Como Ave | $10,800,000 | 2026 | Poor pavement conditions; coordinate with bridge work. 6242-083 |
72 | MN13 | Medium mill and overlay from Dakota to Washburn ave | $1,600,000 | Not Selected | Program limited by available funding. |
71 | MN7 | Medium mill and overlay from MN25 to Six mile Creek | $9,400,000 | 2030 | Projected poor pavement conditions. |
71 | US10 | Medium mill and overlay from east of 114th Ave NW to east Foley Blvd | $2,200,000 | Not Selected | RQI does not reflect on the ground conditions |
70 | US12 | Medium mill and overlay from County Road 90 to eastern Independence City limits | $400,000 | Not Selected | Program limited by available funding. |
70 | MN610 | Minor rehabilitation from US169 to Braun bridge | $29,800,000 | 2031 | Projected poor pavement conditions. |
70 | I35W | Medium mill and overlay from 76th St to 66th ST | $1,800,000 | Not Selected | Program limited by available funding. |
70 | MN101 | Minor rehabilitation from Wright County Road 38 to US10 | $5,300,000 | 2031 | Poor pavement conditions. 8608-33 |
69 | US212 | Medium mill and overlay from MN5 to Tacoma Ave | $3,500,000 | Not Selected | Program limited by available funding. |
69 | MN316 | Medium mill and overlay from Southern to northern limits | $7,600,000 | 2025 | Poor pavement conditions. SP 1926-023. |
69 | MN55 | Major rehabilitation from Dakota County Road 63 to US52 | $5,900,000 | 2028 | Poor pavement conditions. |
69 | US52 | Medium mill and overlay from Goodhue/Dakota County Line to County Road 86 | $2,300,000 | Not Selected | Program limited by available funding. |
69 | MN252 | Medium mill and overlay from 85th to MN610 | $1,100,000 | Not Selected | Program limited by available funding. |
68 | MN62 | Minor rehabilitation from Penn ave bridge to Portland Ave bridge | $11,000,000 | 2031 | Repair early distresses. |
68 | MN65 | Medium mill and overlay from 26th St to 10th ST | $1,300,000 | Not Selected | Program limited by available funding. |
68 | US169 | Medium mill and overlay from Elm creek Blvd to Mississippi River Bridge | $500,000 | Not Selected | Program limited by available funding. |
68 | US212 | Medium mill and overlay from 2.2 miles east of MN284 to 4 lane section | $2,200,000 | Not Selected | Program limited by available funding. |
68 | MN101 | Medium mill and overlay from NB split with US169 to SB merge with US169 | $3,400,000 | Not Selected | Program limited by available funding. |
67 | US12 | Medium mill and overlay from Wright/Hennepin County line to Hennepin County Road 90 | $7,600,000 | 2029 | Poor pavement conditions. |
67 | MN7 | Medium mill and overlay from Railroad bridge to MN100 | $900,000 | Not Selected | Program limited by available funding. |
67 | MN41 | Medium mill and overlay from Carver County Road 61 to Pioneer Trail | $12,800,000 | 2027 | Poor pavement conditions. |
67 | MN41 | Medium mill and overlay from US169 to Pioneer Trail | $1,200,000 | Not Selected | Program limited by available funding. |
67 | US212 | Minor rehabilitation from MN 41 to Hennepin County Road 4 | $10,700,000 | 2028 | Preventive maintenance. |
66 | MN7 | Medium mill and overlay from I-494 to Shady Oak Road | $1,000,000 | Not Selected | Program limited by available funding. |
66 | MN36 | Medium mill and overlay from I35W to east of Edgerton St | $9,500,000 | 2025 | Poor pavement conditions; maintenance liability. SP 6212-192. |
66 | MN41 | Reconstruction from Minnesota River to Carver County Road 61 | $800,000 | 2022 | MnDOT contribution to locally led reconstruction in Chaska. SP 1008-087. |
66 | US212 | Meduim mill and overlay from MN5 to .4 miles east of MN5 | $400,000 | Not Selected | Program limited by available funding. |
66 | I35E | Medium mill and overlay from 76th St to 66th ST | $900,000 | Not Selected | Program limited by available funding. |
66 | MN252 | Thin mill and overlay from I-94 to 85th Ave | $11,800,000 | 2029 | Poor pavement conditions. Coordination with 252 CoC project. |
66 | MN13 | Medium mill and overlay from .4 miles west of Dakota Ave to .2 miles east of Dakota ave | $700,000 | Not Selected | Program limited by available funding. |
65 | US8 | Medium mill and overlay from Tern Ave roundabout to Minnesota/Wisconsin State line | $1,900,000 | Not Selected | Program limited by available funding. |
65 | MN62 | Medium mill and overlay from I-494 to Clearwater Dr | $300,000 | Not Selected | Program limited by available funding. |
65 | US169 | Medium mill and overlay from MN282 to MN21 | $1,400,000 | Not Selected | Program limited by available funding. |
65 | MN55 | Medium mill and overlay from Railroad overpass to Lyndale Ave | $6,700,000 | 2026 | Poor pavement conditions. Frontage road and ADA needs. SP 2751-059 |
65 | MN13 | Medium mill and overlay from Dakota County Line to Washburn Ave | $700,000 | Not Selected | Program limited by available funding. |
64 | US12 | Medium mill and overlay from Hennepin County Road 29 to Wayzata Blvd exit | $3,000,000 | Not Selected | Program limited by available funding. |
63 | MN41 | Medium mill and overlay from Hundermark to Pioneer Trail | $300,000 | Not Selected | Program limited by available funding. |
63 | US61 | Medium mill and overlay from 70th St to Carver Ave | $4,400,000 | Not Selected | Program limited by available funding. |
63 | MN62 | Medium mill and overlay from Portland Ave to 28th ave | $1,800,000 | Not Selected | Program limited by available funding. |
63 | US212 | Medium mill and overlay from Tacoma Ave to Carver County Road 36 | $2,700,000 | Not Selected | Program limited by available funding. |
62 | US8 | Unbonded overlay from Wyoming Ave to Tern Ave roundabout | $32,200,000 | 2030 | Poor pavement conditions. |
62 | MN62 | Medium mill and overlay from Clearwater to Tracy Ave | $3,300,000 | Not Selected | Program limited by available funding. |
62 | MN65 | Medium mill and overlay from 53rd Ave N to Moore Lk Dr | $3,900,000 | 2027 | Poor pavement conditions. |
62 | MN55 | Medium mill and overlay and ADA work from MN100 to Railroad overpass | $3,400,000 | 2025 | Poor pavement conditions. SP 2752-043. |
62 | MN55 | Medium mill and overlay from Pine Bend Trail to Hastings CL | $3,500,000 | Not Selected | Program limited by available funding. |
61 | US12 | Medium mill and overlay from Railroad bridge to 7th St | $300,000 | Not Selected | Program limited by available funding. |
61 | MN7 | Minor CPR from Kings Dr to I-494 | $800,000 | 2030 | Poor pavement conditions. |
61 | MN62 | Medium mill and overlay from Portland Ave bridge to .154 miles east of Portland bridge | $200,000 | Not Selected | Program limited by available funding. |
61 | US212 | Unbonded concrete overlay from I-494 to MN62 | $26,200,000 | 2028 | Poor pavement conditions. |
60 | MN77 | Medium mill and overlay from Minnesota River bridge to I-494 | $3,100,000 | Not Selected | Program limited by available funding. |
60 | US212 | Medium mill and overlay from Chaska Creek to MN41 | $1,700,000 | Not Selected | Program limited by available funding. |
60 | I694 | Medium overlay from Dupont Ave to I-35W | $57,600,000 | 2030 | Projected poor pavement conditions. |
59 | MN36 | Medium mill and overlay from Washington Ave to MN95 | $1,800,000 | Not Selected | Program limited by available funding. |
59 | US61 | Medium mill and overlay from 3rd St Railroad crossing to US10 | $4,200,000 | 2029 | Poor pavement conditions. |
59 | US169 | Medium mill and overlay from .1 miles north of Ash St to 1.2 miles north of Ash St | $1,300,000 | Not Selected | Program limited by available funding. |
59 | I35W | Medium mill and overlay from County Road C to Sunset Ave | $15,100,000 | Not Selected | Program limited by available funding. |
59 | US10 | Medium mill and overlay from Fairoak Ave to US169/MN47 | $900,000 | Not Selected | Program limited by available funding. |
59 | MN252 | Medium mill and overlay from I-94 WB in Brooklyn Center to .4 miles north of I-94 | $500,000 | Not Selected | Program limited by available funding. |
58 | US169 | Medium mill and overlay from 4.5 miles north of MN19 to 5.7 miles north of MN19 | $1,100,000 | Not Selected | Program limited by available funding. |
58 | US169 | Medium mill and overlay from Elm Creek Blvd to US10 | $1,400,000 | Not Selected | Program limited by available funding. |
58 | US212 | Medium mill and overlay from 4 lane section to Chaska Creek | $2,700,000 | Not Selected | Program limited by available funding. |
57 | MN62 | Medium mill and overlay from Mendota bridge to I-35E | $6,700,000 | 2024 | Poor pavement conditions. SP 1918-119. |
57 | US169 | Medium mill and overlay from LeSueur/Scott County line to MN19 | $400,000 | Not Selected | Program limited by available funding. |
57 | MN55 | Medium mill and overlay from US52 to US61 | $26,000,000 | 2028 | Poor pavement conditions. |
56 | MN610 | Medium mill and overlay from I-94 to Elm Creek Blvd | $2,400,000 | Not Selected | Program limited by available funding. |
55 | MN62 | Medium mill and overlay from Clearwater Dr to .32 miles east of Clearwater | $400,000 | Not Selected | Program limited by available funding. |
55 | I694 | Medium mill and overlay from Lexington Ave to MN49 | $4,600,000 | Not Selected | Program limited by available funding. |
55 | MN121 | Medium mill and overlay from I35W to Pedestrian bridge | $300,000 | Not Selected | Program limited by available funding. |
54 | US212 | Medium mill and overlay from .1 miles south of MN62 to MN62 | $1,000,000 | Not Selected | Program limited by available funding. |
54 | I494 | Medium mill and overlay from US12 to I-94 | $12,800,000 | Not Selected | Program limited by available funding. |
53 | MN62 | Reconstruction from 28th Ave S to 43rd Ave | $12,300,000 | 2027 | Poor pavement conditions. |
51 | US52 | Unbonded concrete overlay from Clayton to I-494 | $43,300,000 | 2028 | Poor pavement conditions. |
50 | I35W | Unbonded concrete overlay from I35W/I35E to Cliff Rd exit | $72,300,000 | 2025 | Mobility needs; bridge replacement coordination. SP 1981-140. |
50 | I35 | Medium mill and overlay from Scott County road 2 to MN50 | $6,400,000 | Not Selected | Program limited by available funding. |
49 | I35W | Medium mill and overlay from 90th St to 76th St | $1,000,000 | 2024 | Poor pavement conditions. Coordinate with 494 CoC project. SP 2785-424. |
46 | MN36 | Medium mill and overlay from east of Edgerton St to Washington Ave | $8,900,000 | 2022 | Poor pavement conditions; maintenance liability. SP 8204-077. |
46 | MN101 | Reclaim NB lanes & medium mill and overlay SB lanes from I-94 to Wright County Road 38 | $10,900,000 | 2026 | Poor pavement conditions. 2738-031 |
45 | US169 | Thin mill and overlay from Minnesota River Bridge to Anderson Lake Blvd | $10,300,000 | 2028 | Poor pavement conditions. 2776-112 |
45 | I35 | Medium mill and overlay from MN95 to Chisago County Road 9 | $6,700,000 | Not Selected | Program limited by available funding. |
44 | US52 | Unbonded overlay from Dakota County Road 86 to Dakota County Road 42 | $66,100,000 | 2023 | Poor pavement conditions. SP 1906-071. |
43 | I94 | Medium mill and overlay from Mounds Blvd to Ramsey/Washington County line | $6,800,000 | Not Selected | Program limited by available funding. |
43 | MN5 | Medium mill and overlay from I-494 to Hennepin/Ramsey County line | $3,900,000 | Not Selected | Program limited by available funding. |
40 | US8 | Medium mill and overlay from I-35 to Wyoming Ave | $12,100,000 | 2025 | Coordination with County safety improvements. Poor pavement conditions. SP 1308-027. |
40 | MN13 | Medium mill and overlay from Washburn Ave to I-35 | $1,400,000 | Not Selected | Program limited by available funding. |
39 | US12 | Reconstruction and mill and overlay from Wayzata Blvd to I-494 | $60,600,000 | 2026 | Concrete segment is in poor condition; maintenance liability 2716-129 |
39 | I35E | Replace short segment of pavement either side of bridge 9532 | $3,000,000 | 2026 | Poor pavement conditions. Coordinate with Shepard Rd bridge replacement. |
39 | I694 | Major rehabilitation from MN49 to Washington County Road 10 | $18,400,000 | 2029 | Repair early distresses. |
38 | I94 | Medium mill and overlay from Exit 207 to I494 | $14,500,000 | Not Selected | Program limited by available funding. |
36 | US12 | Thin mill and overlay from the eastern Independence City limits to Hennepin County Road 29 | $3,800,000 | 2029 | Poor pavement conditions. |
36 | US169 | Medium mill and overlay from Valley View Rd to US 212/MN62 | $1,900,000 | Not Selected | Program limited by available funding. |
35 | MN77 | Medium mill and overlay from I-494 to MN62 | $13,200,000 | 2022 | Poor pavement conditions. SP 2758-077. |
35 | MN55 | Medium mill and overlay from General Mills Blvd to Schaper Rd | $2,100,000 | Not Selected | Program limited by available funding. |
34 | US61 | Thin mill and overlay from MN316 to 3rd st | $3,700,000 | 2026 | Poor pavement conditions. 1913-107 |
33 | I94 | Medium mill and overlay from Wright/Hennepin County line | $3,400,000 | Not Selected | Program limited by available funding. |
32 | MN280 | Unbonded overlay from Como to I-35W | $23,400,000 | 2027 | Poor pavement conditions. |
32 | I35 | Medium overlay from Dakota County Road 70 to I35E/I35W | $18,500,000 | 2029 | Poor pavement conditions. |
31 | I35W | Medium mill and overlay from 106th to 76th | $7,300,000 | 2023 | Poor pavement conditions. Coordinate with 494 CoC project. SP 2782-352. |
29 | MN65 | Medium mill and overlay from south of E Moore Lake Dr to Anoka County Road 10 | $3,100,000 | Not Selected | Program limited by available funding. |
29 | I494 | Medium mill and overlay from I-94/694 to Lake Dr | $2,300,000 | Not Selected | Program limited by available funding. |
29 | MN610 | Medium mill and overlay from Elm Creek Blvd to US 169 | $2,700,000 | Not Selected | Program limited by available funding. |
29 | I35E | Medium mill and overlay from Cayuga to Little Canada Rd | $7,700,000 | Not Selected | Program limited by available funding. |
29 | US10 | Medium mill and overlay from MN101 to Cleveland Ave | $3,400,000 | Not Selected | Program limited by available funding. |
28 | I35E | Medium mill and overlay from Ramsey County Road 96 to 80th St | $10,600,000 | Not Selected | Program limited by available funding. |
27 | I35W | Medium mill and overlay from Sunset Ave to I35W/I35E | $7,100,000 | Not Selected | Program limited by available funding. |
25 | I35 | Medium mill and overlay from I35W/E to US8 | $6,400,000 | Not Selected | Program limited by available funding. |
25 | I35 | Medium mill and overlay from Chisago County Road 9 to Chisago/Pine County line | $8,600,000 | Not Selected | Program limited by available funding. |
23 | I494 | Medium mill and overlay from I94/694 to Tamarack Rd | $800,000 | Not Selected | Program limited by available funding. |
21 | US169 | Medium mill and overlay from MN19 to MN25 | $4,500,000 | Not Selected | Program limited by available funding. |
19 | US212 | Major rehabilitation from Carver County Road 36 to 2.2 miles east of MN284 | $8,400,000 | 2023 | Poor pavement conditions. SP 1013-101. |
18 | MN77 | Unbonded overlay from 138th St to Dakota/Hennepin County line | $51,600,000 | 2026 | Poor pavement conditions. 1929-050 |
18 | US169 | Major rehabilitation from Scott County Road 16 to Canterbury Rd | $13,100,000 | 2026 | Poor pavement conditions. 7009-129 |
18 | US169 | Medium mill and overlay from 1.2 miles north of MN282 to .27 miles north of MN282 | $5,900,000 | Not Selected | Program limited by available funding. |
18 | US169 | Medium mill and overlay from 93rd Ave to Elm Creek Blvd | $4,000,000 | Not Selected | Program limited by available funding. |
17 | I35E | Medium mill and overlay from County Road E to County Road 96 | $2,300,000 | Not Selected | Program limited by available funding. |
15 | US169 | Medium mill and overlay from MN25 to Ash St | $1,800,000 | Not Selected | Program limited by available funding. |
11 | I35E | Medium mill and overlay from south of I-35W to I35E/W | $1,300,000 | Not Selected | Program limited by available funding. |