Scoring criteria for non-national highway system bridge projects. Out of 100 possible points, 50 points are based on the condition of the bridge, 20 points are based on the risk of service interruption, 20 points are based on the remaining service life of the bridge deck, and 10 points are based on the size of the bridge.

Learn more about how MnDOT evaluates and selects bridge and culvert projects

MnDOT scores bridge condition needs when selecting projects to include in the 10-year Capital Highway Investment Plan. Bridges that carry roads on the National Highway System (NHS) are scored and selected separately from bridge needs off the system. MnDOT’s approach to managing bridge condition follows the guidance and targets in the Transportation Asset Management Plan and the planned outcomes in MnSHIP.

Non-NHS bridges are scored statewide, but prioritized within each district. The selection of bridge projects is informed by district staff, experts from MnDOT’s bridge office and the Bridge Replacement and Improvement Management System (BRIM).

Once selected, MnDOT then identifies and evaluates alternatives and other needs, legal requirements, issues and opportunities in coordination with local partners, and considers public input. In the process, non-bridge work may be added to a bridge project or a bridge project may be combined with a nearby pavement project. The department follows a context-sensitive complete streets approach, which considers the needs of all users. The final project may address a substantial number of needs beyond the bridge need that precipitated the project. Projects may move years based on local coordination, project delivery, timing of other nearby construction projects, and funding shifts.

What was selected

Related links

How the projects scored

The construction costs shown on this list represent a very rough estimate based on limited information available at the time selection decisions were made. Actual construction and delivery costs will change over time as projects go from a concept through the project development process and are eventually constructed. View more detailed scores (Excel).

Last updated October 2023

Score Bridge Number Route Key intersection or closest landmark Work type Year Planned (FY) High level construction cost estimate for planning purposesĀ  Comments
90 6347 MN 243 St Croix River Replace 2026 $9,942,000  
80 19857 MN 149 I 494 Reoverlay deck surface Not Selected  $1,900,000  
80 82846 MN 95 I 94 Overlay deck surface Not Selected  $1,900,000 Not a district priority. Will continue to monitor bridge performance & condition
75 62040 MN 51 Ramsey County Road B2 Redeck Not Selected  $1,800,000 Not a district priority. Will continue to monitor bridge performance & condition
75 9012 MN51 MN 36 Replace Not Selected  $3,200,000 Not a district priority. Will continue to monitor bridge performance & condition
75 9013 MN51 MN 36 Replace Not Selected  $3,200,000 Not a district priority. Will continue to monitor bridge performance & condition
70 27730 MN 55  I 394 Reoverlay deck surface Not Selected  $1,400,000  
70 27164 MN 65 BNSF RR Overlay deck surface 2030 $400,000  
65 27840 15th St E MN65 Replace Not Selected  $4,600,000  
65 9122 Mill St MN7 Replace Not Selected  $2,400,000  
65 27161 MN 55 MN 5  Redeck Not Selected  $1,000,000  
65 9492 MN 888A  EB I 35W Replace Not Selected  $3,800,000  
60 19095 MN 3 Chub Creek Reoverlay deck surface Not Selected  $100,000  
60 27015 MN 65 BNSF Railroad Reoverlay deck surface 2029 $600,000  
60 82037 US61 BN/CP Railroad Reoverlay deck surface Not Selected  $1,000,000  
55 62090 MN 149 Mississippi River Preventive maintenance Not Selected  $26,000,000  
45 6859 MN 282 SAND CREEK Replace Not Selected  $2,600,000  
45 9531 MN 5 I 35E Replace Not Selected  $6,100,000  
45 62012 MN 51 BNSF Railroad Replace Not Selected  $6,500,000  
45 62011 MN 51 Pierce Butler Route Replace Not Selected  $3,600,000  
45 9391 MN 95 UP Railroad Replace Not Selected  $4,400,000  
45 9409 Post Road MN 5 Replace Not Selected  $2,400,000  
45 6692 US 61 PED-BIKE TRAIL Replace Not Selected  $3,200,000  
30 10009 MN51 TCW Railroad Replace Not Selected  $2,700,000  
10 9071 Washington County Road 19-ChemoliteRd US 61 Replace Not Selected  $2,100,000  
0 9491 Edgcumbe Road MN5 Replace Not Selected  $3,400,000  