Non-National Highway System culverts
MnDOT District 6
MnDOT replaces or rehabilitates most culverts (greater than 10 feet) in conjunction with other projects. However, MnDOT will occasionally select a culvert for a standalone rehabilitation or replacement project.
MnDOT scores culvert condition needs when selecting projects to include in the 10-year Capital Highway Investment Plan. Culverts that carry roads on the National Highway System (NHS) are scored and selected separately from culvert needs off the system. MnDOT’s approach to managing culvert condition follows the guidance and targets in the Transportation Asset Management Plan and the planned outcomes in MnSHIP.
Non-NHS culverts are scored statewide, but prioritized within each district. The selection of standalone culvert projects is informed by district staff, experts from MnDOT’s bridge office and the Bridge Replacement and Improvement Management System (BRIM).
Once selected, MnDOT then identifies and evaluates alternatives and other needs, legal requirements, issues and opportunities in coordination with local partners, and considers public input. In the process, non-culvert work may be added to a culvert project or a culvert project may be combined with a nearby pavement project. Projects may move years based on local coordination, project delivery, timing of other nearby construction projects, and funding shifts.
What was selected
Related links
- District 6 project selection
- National Highway System culvert projects
- National Highway System bridge projects
- District 6 Non-National Highway System bridge projects
- Pedestrian bridge rehabilitation/replacement projects
How the projects scored
The construction costs shown on this list represent a very rough estimate based on limited information available at the time selection decisions were made. Actual construction and delivery costs will change over time as projects go from a concept through the project development process and are eventually constructed.
Last updated April 5, 2024
Total score | Bridge number | Route | Key Intersection or Closest Landmark | Work Type | Year planned | High Level cost estimate for planning purposes | Comments |
---|---|---|---|---|---|---|---|
80 | 91155 | US Hwy 14 | Bluff Avenue | Replace | 2031 | $230,000 | None |
72 | 20X01 | Hwy 57 | N of Dodge County 16 | Replace | Not Selected | $230,000 | None |
71 | 5836 | Hwy 74 | State Park Road 14 | Replace | Not Selected | $230,000 | None |
64 | 8453 | US Hwy 218 | N of 120th Street | Replace | Not Selected | $260,000 | None |
64 | 8842 | Hwy 26 | S of Spring Hills Dr | Replace | Not Selected | $230,000 | None |
63 | 8648 | Hwy 56 | S of Goodhue County Road 44 | Replace | 2025 | $230,000 | None |
61 | 6108 | Hwy 44 | W of Houston County Road 20 | Replace | Not Selected | $850,000 | None |
61 | 8489 | Hwy 56 | W of 755th Avenue | Replace | 2030 | $270,000 | None |
60 | 689 | Hwy 16 | S of Kistler Drive | Replace | Not Selected | $240,000 | None |
59 | 89344 | Hwy 56 | N of I 90 | Replace | Not Selected | $270,000 | None |
59 | 91122 | Hwy 43 | N of Hartwood Dr | Replace | 2031 | $230,000 | None |
57 | 8885 | Hwy 30 | E of SW 62nd Avenue | Replace | 2029 | $230,000 | None |
56 | 8055 | US Hwy 14 | W of Olmsted County Road 19 | Replace | Not Selected | $230,000 | None |
53 | 6033 | US Hwy 14 | E of Olmsted County Road 102 | Replace | Not Selected | $330,000 | None |
51 | 3225 | US Hwy 14 | S of Winona County Road 120 | Replace | Not Selected | $580,000 | None |
51 | 4988 | US Hwy 14 | Whitewater River | Replace | Not Selected | $500,000 | None |
51 | 4989 | US Hwy 14 | Whitewater River | Replace | Not Selected | $500,000 | None |
51 | 6025 | US Hwy 14 | Hickory Lane | Replace | Not Selected | $390,000 | None |
51 | 6028 | US Hwy 14 | Whitewater River | Replace | Not Selected | $240,000 | None |
51 | 6032 | US Hwy 14 | Whitewater River | Replace | Not Selected | $230,000 | None |
51 | 6170 | Hwy 58 | N of Old Church Road | Replace | Not Selected | $510,000 | None |
51 | 8049 | US Hwy 14 | S of Winona County Road 20 | Replace | Not Selected | $230,000 | None |
51 | 8050 | US Hwy 14 14 | E of Eagle Road | Replace | Not Selected | $230,000 | None |
51 | 8053 | US Hwy 14 | E of 19th Avenue SE | Replace | Not Selected | $230,000 | None |
51 | 8230 | Hwy 58 | S of 325th Street | Replace | Not Selected | $230,000 | None |
51 | 91119 | US Hwy 14 | W of Sportsmans Road | Replace | Not Selected | $540,000 | None |
51 | 91120 | US Hwy 14 | W of Sportsmans Road | Replace | Not Selected | $490,000 | None |
51 | 91148 | US Hwy 14 | E of Rolling Hills Road | Replace | Not Selected | $400,000 | None |
49 | 6934 | Hwy 247 | Silver Spring Creek | Replace | Not Selected | $300,000 | None |
49 | 8669 | Hwy 42 | S of Olmsted County Road 2 | Replace | Not Selected | $230,000 | None |
49 | 91121 | Hwy 43 | S of Winona County Road 4 | Replace | 2031 | $230,000 | None |
47 | 8917 | Hwy 26 | Shellhorn Dr | Replace | Not Selected | $330,000 | None |
47 | 92572 | Hwy 248 | E of Winona County Road 31 | Replace | Not Selected | $310,000 | None |
45 | 6119 | US Hwy 52 | 320th Street | Replace | 2027 | $340,000 | None |
37 | 55 | Hwy 43 | N of Aspen Road | Replace | Not Selected | $340,000 | None |
16 | 6029 | US Hwy 14 | E of 140th Avenue SE | Replace | Not Selected | $230,000 | None |
16 | 6030 | US Hwy 14 | Whitewater River | Replace | Not Selected | $250,000 | None |
16 | 6031 | US Hwy 14 | Whitewater River | Replace | Not Selected | $230,000 | None |
16 | 8051 | US Hwy 14 | E of Cherokee Road | Replace | Not Selected | $230,000 | None |
16 | 8052 | US Hwy 14 | W of West Avenue | Replace | Not Selected | $230,000 | None |
14 | 8675 | Hwy 42 | N of 48th Street NE | Replace | Not Selected | $250,000 | None |
7 | 91201 | I 90 | Badger Run | Replace | 2024 | $- | None |
3 | 91203 | I 90 | Badger Run | Replace | 2024 | $- | None |
2 | 55X10 | Hwy 30 | W of 20th Avenue SE | Replace | 2024 | $- | None |
2 | 95111 | Hwy 16 | E of MN 76 | Replace | Not Selected | $390,000 | None |