Non-National Highway System bridge projects
MnDOT District 6
MnDOT scores bridge condition needs when selecting projects to include in the 10-year Capital Highway Investment Plan. Bridges that carry roads on the National Highway System (NHS) are scored and selected separately from bridge needs off the system. MnDOT’s approach to managing bridge condition follows the guidance and targets in the Transportation Asset Management Plan and the planned outcomes in MnSHIP.
Non-NHS bridges are scored statewide, but prioritized within each district. The selection of bridge projects is informed by district staff, experts from MnDOT’s bridge office and the Bridge Replacement and Improvement Management System (BRIM).
Once selected, MnDOT then identifies and evaluates alternatives and other needs, legal requirements, issues and opportunities in coordination with local partners, and considers public input. In the process, non-bridge work may be added to a bridge project or a bridge project may be combined with a nearby pavement project. The department follows a context-sensitive complete streets approach, which considers the needs of all users. The final project may address a substantial number of needs beyond the bridge need that precipitated the project. Projects may move years based on local coordination, project delivery, timing of other nearby construction projects, and funding shifts.
What was selected
Related links
- District 6 project selection
- National Highway System bridge projects
- District 6 Non-National Highway System culvert projects
- Bridges projects over state highways carrying railroads
- Pedestrian bridge rehabilitation/replacement projects
How the projects scored
The construction costs shown on this list represent a very rough estimate based on limited information available at the time selection decisions were made. Actual construction and delivery costs will change over time as projects go from a concept through the project development process and are eventually constructed.
Last updated April 5, 2024
Total score | Bridge number | Route | Key Intersection or Closest Landmark | Work Type | Year Planned | High level cost estimate for planning purposes | Comments |
---|---|---|---|---|---|---|---|
90 | 9507 | CSAH 13 | I 90 | Replace | N/A | $- | Candidate for future replacement project, cost is greater than total available budget. |
80 | 5932 | Hwy 74 | Whitewater River | Replace | 2025 | $- | FY2025 Project |
80 | 9009 | Hwy 30 | Root River | Replace | 2023 | $- | FY2023 Project |
80 | 9105 | Hwy 76 | Money Creek | ReOvly | 2022 | $- | FY2022 Project |
80 | 9183 | Hwy 105 | I 90 | Replace | 2025 | $- | FY2025 Project |
80 | 9201 | US Hwy 218 | I 90 | Replace | 2025 | $- | FY2025 Project |
80 | 9506 | CSAH 20 | I 90 | Replace | N/A | $- | Candidate for future replacement project, cost is greater than total available budget. |
80 | 9668 | CSAH 11 | US Hwy 52 | Replace | N/A | $3,440,000 | Candidate for future replacement project, cost is greater than total available budget. |
80 | 9859 | CSAH 35 | I 90 | Replace | 2026 | $- | FY2026 Project |
80 | 50004 | Hwy 16 | Deer Creek | Overlay | N/A | $760,000 | Candidate for future deck overlay project, cost is greater than total available budget. |
80 | 55017 | CR 111 | US Hwy 52 | Overlay | N/A | $720,000 | Candidate for future deck overlay project, cost is greater than total available budget. |
80 | 85006 | Hwy 74 | Whitewater River | Replace | 2027 | $2,130,000 | FY2027 Project |
70 | 9104 | Hwy 76 | Money Creek | ReOvly | 2022 | $- | FY2022 Project |
70 | 9106 | Hwy 76 | Money Creek | ReOvly | 2022 | $- | FY2022 Project |
70 | 24836 | CSAH 25 | I 35 | Overlay | N/A | $650,000 | Candidate for future deck overlay project, cost is greater than total available budget. |
70 | 28009 | Hwy 16 | Root River | Overlay | N/A | $250,000 | Candidate for future deck overlay project, cost is greater than total available budget. |
70 | 55035 | MSAS 126 | US Hwy 52 | ReOvly | N/A | $730,000 | Candidate for future bridge repair and overlay project, cost is greater than total available budget |
70 | 55053 | CR 125 | US Hwy 52 | ReOvly | N/A | $480,000 | Candidate for future bridge repair and overlay project, cost is greater than total available budget |
70 | 66808 | CON 2 | I 35 | ReOvly | 2023 | $300,000 | FY2023 Project |
65 | 9008 | Hwy 30 | Mill Creek | Replace | 2023 | $- | FY2023 Project |
65 | 9180 | CSAH 45 | I 90 | Replace | 2025 | $- | FY2025 Project |
65 | 9505 | Hwy 56 | I 91 | Replace | N/A | $- | Candidate for future replacement project, cost is greater than total available budget. |
65 | 9706 | CSAH 15 | I 92 | Replace | 2022 | $- | FY2022, Candidate for future replacement project, cost is greater than total available budget. |
65 | 9730 | CSAH 34 | I 93 | Replace | N/A | $2,190,000 | Candidate for future replacement project, cost is greater than total available budget. |
65 | 66001 | Hwy 3 | UP Railroad | Replace | N/A | $6,710,000 | Candidate for future replacement project, cost is greater than total available budget. |
65 | 66821 | CSAH 86 | I 35 | Replace | N/A | $2,910,000 | Candidate for future replacement project, cost is greater than total available budget. |
65 | 74801 | Hwy 30 | I 35 | Replace | 2029 | $2,500,000 | FY2029 Project |
60 | 85023 | US Hwy 14 | DME Railroad | Overlay | N/A | $450,000 | Candidate for future deck overlay project, cost is greater than total available budget. |
55 | 9729 | CSAH 30 | I 90 | Replace | N/A | $2,190,000 | |
55 | 66807 | CSAH 3 | I 35 | Replace | N/A | $2,810,000 | Candidate for future replacement project, cost is greater than total available budget. |
55 | 85012 | Hwy 248 | Rollingstone Creek | Redeck | N/A | $1,400,000 | Candidate for redeck project, cost is greater than total available budget. |
35 | 24813 | CSAH 14 | I 90 | Replace | 2026 | $- | FY2026 Project |
30 | 6640 | Hwy 21 | Cannon River | Replace | N/A | $4,260,000 | Candidate for future replacement project, cost is greater than total available budget. |
20 | 5234 | US Hwy 14 | Stream | Replace | N/A | $1,170,000 | Candidate for future replacement project, cost is greater than total available budget. |
20 | 5848 | Hwy 16 | Crystal Creek | Replace | 2030 | $2,140,000 | FY2030 Project |
20 | 9705 | CSAH 1 | I 90 | N/A | N/A | $- | Candidate for future replacement project |
10 | 6468 | Hwy 56 | Rose Creek | Replace | N/A | $1,190,000 | Removed from CHIP |
10 | 6679 | Hwy 76 | Root River | OPM | 2027 | $310,000 | FY2027 Project |
10 | 6765 | US Hwy 65 | Main St | Replace | N/A | $2,730,000 | Candidate for future replacement project, cost is greater than total available budget. |
10 | 23015 | Hwy 16 | Root River | OPM | 2027 | $20,000 | FY2027 Project |
10 | 24824 | CSAH 19 | I 35 | Overlay | N/A | $1,170,000 | Candidate for future deck overlay project, cost is greater than total available budget. |
10 | 25007 | Hwy 19 | Prairie Creek | Overlay | N/A | $300,000 | Candidate for future deck overlay project, cost is greater than total available budget. |
0 | 74005 | CSAH 45 | US Hwy 14 | Replace | N/A | $2,570,000 | Candidate for future replacement project, cost is greater than total available budget. |