Non-National Highway System culverts
MnDOT District 2
MnDOT replaces or rehabilitates most culverts (greater than 10 feet) in conjunction with other projects. However, MnDOT will occasionally select a culvert for a standalone rehabilitation or replacement project.
MnDOT scores culvert condition needs when selecting projects to include in the 10-year Capital Highway Investment Plan. Culverts that carry roads on the National Highway System (NHS) are scored and selected separately from culvert needs off the system. MnDOT’s approach to managing culvert condition follows the guidance and targets in the Transportation Asset Management Plan and the planned outcomes in MnSHIP.
Non-NHS culverts are scored statewide, but prioritized within each district. The selection of standalone culvert projects is informed by district staff, experts from MnDOT’s bridge office and the Bridge Replacement and Improvement Management System (BRIM).
Once selected, MnDOT then identifies and evaluates alternatives and other needs, legal requirements, issues and opportunities in coordination with local partners, and considers public input. In the process, non-culvert work may be added to a culvert project or a culvert project may be combined with a nearby pavement project. Projects may move years based on local coordination, project delivery, timing of other nearby construction projects, and funding shifts.
What was selected
Related links
- District 2 project selection
- National Highway System culvert projects
- National Highway System bridge projects
- District 2 Non-National Highway System bridge projects
- Pedestrian bridge rehabilitation/replacement projects
How the projects scored
The construction costs shown on this list represent a very rough estimate based on limited information available at the time selection decisions were made. Actual construction and delivery costs will change over time as projects go from a concept through the project development process and are eventually constructed.
Last updated April 2024
Total Score | Culvert Number | Route | Key Intersection or closest landmark | Work Type | Year Planned | High Level cost estimate for planning purposes | Comments |
---|---|---|---|---|---|---|---|
46 | 6338 | Hwy 200 | East of 340th St | N/A | N/A | $ 250,000 | None |
46 | 6380 | US Hwy 75 | Burnham Creek | N/A | 2026 | $ 460,000 | None |
46 | 8133 | Hwy 200 | West of 350th St | N/A | N/A | $ 230,000 | None |
36 | 8682 | US Hwy 75 | North of Polk County Rd 1 | N/A | N/A | $ 230,000 | None |
36 | 8696 | Hwy 89 | North of Roseau County Rd 20 | N/A | N/A | $ 230,000 | None |
21 | 4102 | US Hwy 75 | North of 130th St | N/A | 2029 | $ 230,000 | None |
20 | 6255 | US Hwy 75 | North of Marshall County Rd 5 | N/A | N/A | $ 450,000 | None |
11 | 2238 | US Hwy 75 | South of 250th St NW | N/A | N/A | $ 340,000 | None |
11 | 4103 | US Hwy 75 | South of Kittson County Rd 23 | N/A | 2029 | $ 230,000 | None |
11 | 4105 | US Hwy 75 | North of Kittson County Rd 10 | N/A | 2029 | $ 250,000 | None |
11 | 4725 | Hwy 102 | South of Polk County Rd 45 | N/A | 2031 | $ 230,000 | None |
11 | 6177 | US Hwy 59 | Marshall County Rd 28 | N/A | N/A | $ 400,000 | None |
11 | 6178 | US Hwy 59 | South of Stassen Ave | N/A | N/A | $ 370,000 | None |
11 | 8245 | US Hwy 59 | Tamarac River | N/A | N/A | $ 230,000 | None |
11 | 8411 | US Hwy 75 | East of 330th Ave SW | N/A | 2026 | $ 230,000 | None |
10 | 8396 | US Hwy 75 | 430th St NW | N/A | N/A | $ 230,000 | None |
2 | 6007 | Hwy 1 | West of 280th Ave NW | N/A | N/A | $ 230,000 | None |
2 | 6008 | Hwy 1 | East of 285th Ave NW | N/A | N/A | $ 230,000 | None |
0 | 6253 | Hwy 9 | Burnham Creek | N/A | N/A | $ 270,000 | None |
0 | 8389 | Hwy 9 | Polk County Rd 41 | N/A | N/A | $ 240,000 | None |
0 | 8390 | Hwy 9 | North of polk County Rd 45 | N/A | N/A | $ 230,000 | None |