Scoring criteria for national highway system pavement projects. Out of 100 possible points, 60 points are based on the timing of the improvement, 10 points are based on traffic volume, 10 points are based on truck volume, 10 points are based on other infrastructure needs, 5 points are based on network designation, and 5 points are based on the miles covered by the project.

Learn more about how MnDOT evaluates and selects pavement projects

MnDOT scores stretches of highway based on a pavement need when selecting projects to include in the 10-year Capital Highway Investment Plan. Pavement needs on the National Highway System (NHS) are scored and selected separately from pavement needs off the system. MnDOT’s approach to managing pavements follows the guidance and targets in the Transportation Asset Management Plan and the planned outcomes in MnSHIP.

Pavement projects are scored and selected within each district. Potential pavement projects are identified by the Highway Pavement Management Application (HPMA) and by MnDOT District staff.

Once selected, MnDOT then identifies and evaluates alternatives and other needs, legal requirements, issues and opportunities in coordination with local partners, and considers public input. In the process, non-pavement work may be added to a pavement project or a pavement project may be combined with a nearby bridge project. The department follows a context-sensitive complete streets approach, which considers the needs of all users. The final project may address a substantial number of needs beyond the pavement need that precipitated the project. Projects may move years based on local coordination, project delivery, timing of other nearby construction projects, and funding shifts.

What's was selected

Related links

How the projects scored

The construction costs shown on this list represent a very rough estimate based on limited information available at the time selection decisions were made. Actual construction and delivery costs will change over time as projects go from a concept through the project development process and are eventually constructed. View more detailed scores (Excel).

Last updated October 2024

Score Route  Year Planned (FY) Description High Level Cost Estimate for Planning Purposes  Comments
96 I35 2029-2033 Reconstruct I-35 from .5 miles south of Boundary Ave to bridge over Hwy 23 and replace four bridges $32,000,000 6982-359
95 I35 2028 Resurface I-35 under the 5th Ave W bridge and from Hwy 23 to 50th Ave W in Duluth $1,400,000 0906-50
92 MN61 2026-2027 On London Rd in Duluth, from 26 Ave E. to just north of. 60th Ave. E., construct roundabout at 26th and 40th Ave. E., resurface pavement and install trail and on Interstate 35 South Bound at 21st Ave E. install freeway closure gates. $20,200,000 6925-145
92 MN73 2034 In Chisholm reconstruct State Highway 73 from Jct US169 to 4th Ave NW $9,264,000 6930-43
92 US169 2031 Resurface Hwy 169 from 13th St SW to Hwy 2 in Grand Rapids $3,666,000 3115-131
92 US169 2033 Resurface Hwy 169 from east Jct Hwy 2 in Grand Rapids to just west of Elizabeth Ave in Coleraine $11,252,000 3116-155
91 I535 2030 Reconstruct Interstate 535 between Twin Ports Interchange and Garfield Interchange in Duluth $5,300,000 6980-63
88 I35 2025 Northbound and Southbound I-35 in Duluth Repair concrete pavement and interchange ramps from Lake Ave to 0.7 miles South of 21st Ave E. $2,235,226 6929-24
88 MN61 2027-2028 Hwy 61 from 2.6 miles north County Rd  6 to 0.20 mi. North Leveaux Ridge Rd. Resurface Pavement $8,500,000 1601-66
88 US53 Not Selected Resurface Hwy 53 from just north of wayside rest to the Rice River bridge  $7,100,000 Cost is greater than available budget
84 US2 Not Selected Resurface Hwy 2 from just east of Itasca County Road 62 to just west of 10th Ave NW  $3,000,000 Waiting to avoid simultaneous or multiple years of detours in the same area
83 US169 Not Selected Resurface Hwy 169 from just northeast of old Hwy 169 to Hwy 73  $6,740,000 Crack sealed in 2022; Cost is greater than available budget.
82 MN33 Not Selected Resurface Hwy 33 from  just north of Carlton County Road 116 to 1.5 miles south of Hwy 2  $5,270,000 Chip sealed in 2022
82 MN61 2029 Resurface NB Hwy 61 from CR 33 (McQuade Rd) to CR 42 (Homestead Rd) and SB Hwy 61 from CR 33 (McQuade Rd) to Knife River $8,500,000 6926-56
82 US169 2031 Resurface Hwy 169 from CR 64 (Harristown Rd) to 13th St SW in Grand Rapids $4,934,000 3115-129
82 US53 Not Selected Resurface Hwy 53 from St Louis County Road 682/691 to the St Louis River bridge  $4,580,000 Cost is greater than available budget
81 US169 Not Selected Resurface Hwy 169 from 8th Ave E to just south of St. Louis County 92  $1,110,000 District does not expect pavement segment(s) to deteriorate as fast as model predicts.
81 US53 2028 Resurface Hwy 53/Trinity Rd from just north of Piedmont Ave to Hwy 194/Central Entrance in Duluth $4,230,000 0905-56
80 MN33 Not Selected Resurface Hwy 33 from 1.5 miles south of Hwy 2 to railroad bridge  $2,990,000 Chip sealed in 2022
78 I35 2029 Resurface I-35 from .5 miles south of Boundary Ave to bridge over Hwy 23 $2,000,000 6982-366
78 MN61 2030 Resurface Hwy 61 from just south of CR 14 to Reservation Bay Rd and resurface bridges over Flute Reed River and Brule River $16,913,000 1603-54
78 MN61 2029 Resurface Hwy 61 from just north of 60th Ave E to just north of N. Superior St. $1,060,000 6925-147
77 I35 2033 Resurface I-35 from 2.6 miles south of CR 4 to the north end of the Hwy 210 bridge $16,485,000 0980-168
77 I35 Not Selected Resurface I-35 from north of tunnel to Hwy 61/London Rd  $1,590,000
76 US53 Not Selected Resurface Hwy 53 from just south of Cook to south limits of Cook  $170,000
75 MN33 Not Selected Resurface Hwy 33 from I-35 to roundabout  $250,000
75 US71 Not Selected Resurface Hwy 71 from Hwy 11 to Hwy 53/2nd Ave W  $40,000
74 MN210 Not Selected Resurface Hwy 210 from railroad bridge to just east of I-35  $9,770,000
73 MN23 2034 Resurface Hwy 23 from Hwy 107 to I-35 $5,715,000 5801-1039097
73 US2 2031 Resurface Hwy 2 from just west of Pincherry Rd to E Bass Lake Rd in Cohasset $2,974,000 3103-72
73 US53 2034 Resurface NB Hwy 53 from CR 13 to 1.6 miles north of Hwy 33 $24,070,000 6916-116
72 US169 Not Selected Resurface Hwy 169 from just north of Saint Louis County Road 5 to just south of Saint Louis County Road 5  $1,760,000 Crack sealed in 2022
70 MN61 2027 Repair Highway 61 in locations between Two Harbors and just south of CR 5 in Silver Bay $2,150,000 3804-64
70 US53 Not Selected Resurface Hwy 53 from Little Fork River bridge just north of Saint Louis County Road  901  $26,530,000
69 US169 Not Selected Resurface Hwy 169 from just north of Saint Louis County 7 to Hwy 53  $600,000
69 US2 Not Selected Resurface Hwy 2 from 5th St SW to just east of Deer River  $200,000
68 MN11 Not Selected Resurface Hwy 11 from Hwy 71 to just east of Hwy 71  $100,000
68 MN33 2034 Resurface Hwy 33 from just north of Witte Rd to Hwy 53 $15,035,000 6911-1124107
68 MN61 2030 Resurface Hwy 61 from 1.3 miles south of Cutface Creek to just south of UT 89  $2,582,000 1602-54
68 MN61 Not Selected Resurface Hwy 61 from just north of bridge 91367 to just north of Palisade Creek  $1,940,000
68 US169 2032 Resurface Hwy 169 from just south of the Aitkin/Itasca County line to CR 64 (Harristown Rd) $13,300,000 3115-128
67 MN61 2029 Concrete pavement repair on Hwy 61 from just south of the Silver Creek Tunnel to just north of the Silver Creek Tunnel and from just north of Crow Creek to just north of Gooseberry River $2,886,000 3805-111
67 MN61 2032 Resurface Hwy 61 from 1.2 miles north of the Gooseberry River to 0.85 miles south of the Split Rock River and 1.3 miles north of CR 22 to Beaver Bay Bridge $3,957,000 3806-72
65 I35 2028 Repair I-35 concrete in locations between north of Hinckley to Hwy 53 and General Andrews and Kettle River rest area pavement repair. $4,000,000 8821-347
65 US53 Not Selected Resurface Hwy 53 from just south of Hwy 33 to Hwy 33 NB  $100,000
62 US53 Not Selected Resurface Hwy 53 from south limits of Cook to Little Fork River bridge  $770,000
61 MN33 Not Selected Resurface Hwy 33 from railroad bridge to Hwy 53  $10,160,000 Chip sealed in 2022
58 MN61 Not Selected Resurface Hwy 61 from Beaver Bay bridge to just north of bridge 91367  $1,780,000
46 I35 2030-2031 Resurface NB and SB I-35 from the north end of the Hwy 210 bridge to the north end of the St Louis River bridge $11,000,000 0980-166
46 US2 Not Selected Resurface Hwy 2 from north end of grass median to I-35  $90,000
41 MN194 Not Selected Resurface Hwy 194 from just north of Mesaba Ave to Superior St  $1,240,000
41 MN33 Not Selected Repair Hwy 33 concrete pavement from roundabout to just north of Doddridge Ave  $690,000
39 US53 2031 Resurface SB Hwy 53 from just north of Hwy 169 to Rice River bridge $6,332,000 6920-57
30 US53 Not Selected Resurface Hwy 53 from 1.64 miles north of Hwy 33 to 1.1 miles south of St. Louis County Road 52  $2,560,000
27 MN61 Not Selected Resurface Hwy 61 from 1 mile north of Crow Creek to just south of Lake County Road 1  $2,070,000
25 US53 Not Selected Resurface Hwy 53 from 4th St to just north of Piedmont Ave  $580,000