Non-National Highway System pavement projects
MnDOT District 8
How the projects scored in 2023
The construction costs shown on this list represent a very rough estimate based on limited information available at the time selection decisions were made. Actual construction and delivery costs will change over time as projects go from a concept through the project development process and are eventually constructed. View more detailed scores (Excel).
Last updated December 2023
Total Score | Route | Description | High-Level Cost Estimate for Planning Purposes | Year Planned (FY) | Comments |
---|---|---|---|---|---|
87 | MN67 | Construct cul-de-sac on Hwy 67 at entrance to Upper Sioux Agency State Park and remove pavement between cul-de-sac and bridge #87011. | $600,000 | 2025 | |
85 | MN68 | Resurface Hwy 68 from Canby to Minneota; upgrade sidewalks to meet ADA standards in Porter, Taunton and Minneota; replace box culverts and bridges along project area. | $3,300,000 | 2033 | |
85 | MN4 | Resurface Hwy 4 from Fairfax to Hector. | $11,225,000 | 2026/2027 | |
85 | MN68 | Resurface Hwy 68 from Porter to Minneota; upgrade sidewalks to meet ADA standards in Porter, Taunton and Minneota; replace box culverts and bridges along project area. | $10,500,000 | 2032/2033 | |
83 | MN24 | Medium overlay Highway 12 (Litchfield) to Highway 15 | $8,800,000 | Not Selected | This section has not been selected because it is a thin whitetopping test section (4-inch bonded concrete overlay in 2015). District will continue to monitor performance for research purposes. |
81 | MN30 | Resurface Hwy 30 from the Minnesota/South Dakota state line to 8th St in Pipestone. | $1,500,000 | 2029 | |
81 | US75 | Cold in place recycling and medium overlay from Yellow Medicine County Road 3 (Canby) to 0.4 mi. S. of US 212 | $4,000,000 | Not selected | Project was not selected due to fiscal constraints in 2030 (no new non-NHS projects were added in FY 2030) |
81 | US75 | Medium overlay from Murray County Road 3 to US212 | $4,000,000 | Not Selected | Not a district priority will continue to monitor pavement performance. |
80 | US75 | Resurface Hwy 75 from Pipestone Creek to S Valley St in Lake Benton. | $9,300,000 | 2030/2031 | |
78 | MN40 | Resurface Hwy 40 from Milan to the west jct of Hwy 29. | $3,300,000 | 2026 | |
78 | MN30 | Resurface Hwy 30 from Hwy 59 to the Murray/Cottonwood county line; replace bridge over Des Moines River. | $15,400,000 | 2028/2029 | |
78 | MN22 | Medium overlay from Hutchinson to Highway 7 | $3,300,000 | Not Selected | Candidate for reconstruction in 2034 |
75 | MN19 | Resurface Hwy 19 from Ivanhoe to CR 5. | $19,800,000 | 2031/2032 | |
75 | MN22 | Resurface Hwy 22 from Hwy 12 to Eden Valley. | $16,300,000 | 2032/2033 | |
75 | US59 | Reclaim and overlay from 15th Ave. (Clarkfield) to W. JCT. US 212 | $3,800,000 | Not selected | |
74 | MN40 | Reclaim and overlay Old Highway 277 to Kandiyohi County Road 5 (Willmar) | $12,700,000 | 2026 | |
74 | MN40 | Resurface Hwy 40 from CR 4 to Willmar. | $17,400,000 | 2030/2031 | |
74 | MN68 | Reclaim and overlay from N. JCT. US 71 to 0.2 mi. W. of MN 67 (Morgan) | $3,900,000 | Not selected | |
74 | MN55 | Medium overlay from Stearns/Meeker County Line to Eden Valley | $3,000,000 | Not Selected | Candidate for preventive maintenance in 2024 |
73 | MN19 | Resurface (concrete) Hwy 19 from Redwood Falls to Morton; resurface (concrete) Hwy 71 from Hwy 19 to CR 15. | $5,400,000 | 2031 | |
73 | MN30 | Cold in place recycling and medium overlay from US 75 to Ravine St. (Lake Wilson) | $4,300,000 | Not selected | |
71 | US75 | Resurface Hwy 75 from CR 9 to CR 34 in Pipestone. | $15,700,000 | 2026 | |
71 | MN67 | Resurface Hwy 67 from Hwy 23 to the Upper Sioux Agency State Park. | $3,100,000 | 2029 | |
71 | US75 | Resurface Hwy 75 from CR 9 to Hwy 30 in Pipestone. | $5,550,000 | 2026/2027 | |
71 | MN119 | Medium mill and overlay from Highway 212 (Dawson) to Highway 40 | $2,700,000 | Not Selected | |
69 | MN4 | Reclaim and overlay from Hector to Cosmos | $10,100,000 | Not Selected | |
67 | MN68 | Resurface Hwy 68 from Wabasso to Hwy 71. | $1,800,000 | 2030 | |
67 | MN24 | Repair concrete on Hwy 24 from Hwy 12 to Hwy 15. | $1,500,000 | Not Selected | |
66 | MN30 | Surface Hwy 30 from Hwy 75 in Pipestone to 60th Avenue in Lake Wilson. Upgrade sidewalks to meet ADA standards in Lake Wilson. | $7,000,000 | Not Selected | |
66 | MN40 | Resurface Hwy 40 from Madison to Hwy 119. | $5,700,000 | Not Selected | |
65 | US75 | Resurface Hwy 75 from county line to Hwy 212. | $5,400,000 | 2033 | |
65 | MN40 | Resurface Hwy 40 from Hwy 119 to 5th Street in Milan. | $5,800,000 | 2025/2026 | |
65 | MN7 | Reclaim and overlay Highway 71 to Highway 4 (Cosmos) | $13,000,000 | Not Selected | |
65 | MN4 | Resurface Hwy 4 from US 212 to Cosmos. | $9,300,000 | Not Selected | |
65 | MN7 | Reclaim and overlay from Highway 4 (Cosmos) to Highway 22 | $7,400,000 | Not Selected | Candidate for preventive maintenance in 2025 |
65 | MN68 | Reclaim and overlay from Redwood County Road 3 (Morgan) to Redwood/Brown County Line | $3,100,000 | Not Selected | Candidate for reconstruction in 2030 |
64 | MN7 | Resurface Hwy 7 from Milan to Montevideo. | $12,100,000 | 2031/2032 | |
64 | MN267 | Reclaim and overlay from Iona to Highway 30 | $4,000,000 | Not Selected | |
64 | MN271 | Resurface Hwy 271 from CR 17 to W Ash Street in Hendricks. | $3,200,000 | Not Selected | |
63 | MN68 | Reclaim and overlay from South Dakota/Minnesota State Line to Canby | $6,400,000 | Not Selected | |
62 | MN29, MN40 | Resurface Hwy 29 from west jct of Hwy 40 to east jct of Hwy 40; resurface Hwy 40 from east jct of Hwy 29 to Chippewa CR 4. | $3,500,000 | 2029 | |
62 | MN15 | Resurface Hwy 15 from Hwy 12 in Dassel to Meeker/Stearns county line. |
$9,400,000 | 2024/2025 | |
62 | MN67 | Reclaim and overlay from Redwood Falls to Fergus Ave. (Morgan) | $8,600,000 | Not Selected | |
62 | MN29 | Medium mill and overlay from west junction of Highway 40 to east junction Highway 40 and additional locations on Highway 40 | $5,200,000 | Not Selected | |
62 | MN29 | Reclaim and overlay from Airport Ave (Montevideo) to MN 40 | $3,700,000 | Not selected | |
62 | MN40 | Construct turn lanes on Hwy 40 from Bridge 34032 to 0.3 miles W of 30th Street SW in Willmar. | $900,000 | Not Selected | |
61 | MN274 | Reclaim and overlay from Wood Lake to Highway 23 | $6,500,000 | Not Selected | |
61 | MN9 | Resurface Hwy 9 from Hwy 23 to Hwy 71. | $2,700,000 | Not Selected | |
59 | MN67 | Reclaim and overlay from Travers Ln. to Highway 19 | $12,300,000 | Not Selected | |
58 | MN68 | Reclaim and overlay Highway 71 to Redwood County Road 3 (Morgan) | $7,700,000 | Not Selected | |
58 | MN67 | Reclaim and overlay from US 75 to US59 near Clarkfield | $7,200,000 | Not Selected | |
56 | MN68 | Resurface Hwy 68 from N Grant St in Minneota to Hwy 59 in Marshall, excluding the city of Ghent. | $1,803,000 | 2024 | |
56 | MN68 | Resurface Hwy 68 from N Grant St in Minneota to CR 33 in Marshall, excluding the city of Ghent. | $900,000 | 2024 | |
54 | US59 | Reclaim and overlay from Yellow Medicine County Road 3 to Clarkfield | $4,100,000 | Not Selected | |
43 | MN22 | Resurface Hwy 22 from Glencoe to Hutchinson. | $6,900,000 | 2032 | |
42 | MN22 | Thin overlay from .1 miles east of Hwy 7 to .2 miles west of Hwy 7 | $100,000 | Not Selected | |
40 | MN67 | Thin mill and overlay Highway 23 (Granite Falls) to Travers Ln. | $2,100,000 | Not Selected | |
39 | MN269 | Thin overlay from South Dakota/Minnesota State Line to Highway 23 (Jasper) | $600,000 | Not Selected | |
37 | MN9 | Thin overlay from Kandiyohi County Road 7 (Sunberg) to Kandiyohi / Swift Co. Line | $100,000 | Not selected | |
36 | US75 | Thin overlay from 4th St. N. (Pipestone) to Pipestone County Road 22 | $100,000 | Not Selected | |
32 | MN29 | Thin overlay from Hwy 40 to Chippewa/Swift County Line | $400,000 | Not Selected | |
31 | MN68 | Thin overlay on from Highway 19 to Redwood County Road 32 (Milroy) | $700,000 | Not Selected | |
29 | MN19 | Thin overlay from Reference point 3 to Reference point 4 | $200,000 | Not selected | |
29 | MN19 | Thin overlay from Reference pt 003 to Reference pt 004 | $200,000 | Not Selected | |
18 | US59 | Repair and smooth concrete pavement on Hwy 59 from 211th Street to Lyon CR 14 and from Lyon CR 6 to Hwy 23. | $1,500,000 | 2024 | |
6 | MN330 | Thin overlay from Highway 14 to University of Minnesota SW Research and Outreach Center | $500,000 | Not Selected | |
6 | MN22 | Thin overlay from Sibley/McLeod County line to US212 | $200,000 | Not Selected | |
5 | MN22 | Thin overlay from Sibley/McLeod County Line to Highway 212 | $400,000 | Not Selected | |
3 | MN104 | Thin mill and overlay Highway 9 to Kandiyohi/Pope County Line | $1,400,000 | Not Selected |