Non-National Highway System bridge projects
MnDOT District 7
MnDOT scores bridge condition needs when selecting projects to include in the 10-year Capital Highway Investment Plan. Bridges that carry roads on the National Highway System (NHS) are scored and selected separately from bridge needs off the system. MnDOT’s approach to managing bridge condition follows the guidance and targets in the Transportation Asset Management Plan and the planned outcomes in MnSHIP.
Non-NHS bridges are scored statewide, but prioritized within each district. The selection of bridge projects is informed by district staff, experts from MnDOT’s bridge office and the Bridge Replacement and Improvement Management System (BRIM).
Once selected, MnDOT then identifies and evaluates alternatives and other needs, legal requirements, issues and opportunities in coordination with local partners, and considers public input. In the process, non-bridge work may be added to a bridge project or a bridge project may be combined with a nearby pavement project. The department follows a context-sensitive complete streets approach, which considers the needs of all users. The final project may address a substantial number of needs beyond the bridge need that precipitated the project. Projects may move years based on local coordination, project delivery, timing of other nearby construction projects, and funding shifts.
What was selected
Related links
- District 7 project selection
- National Highway System bridge projects
- District 7 Non-National Highway System culvert projects
- Bridges projects over state highways carrying railroads
- Pedestrian bridge rehabilitation/replacement projects
How the projects scored
The construction costs shown on this list represent a very rough estimate based on limited information available at the time selection decisions were made. Actual construction and delivery costs will change over time as projects go from a concept through the project development process and are eventually constructed.
Last updated April 5, 2024
Total score | Bridge number | Route | Key Intersection or Closest Landmark | Work Type | Year planned | High level cost estimate for planning purposes | Comments |
---|---|---|---|---|---|---|---|
45 | 5076 | Hwy 4 | Watonwan River | Replace | 2023 | $ - | None |
98 | 07042 | US Hwy 169 | Minnesota River; UP Railroad | Redeck | 2025 | $1,610,000 | None |
80 | 40007 | Hwy 19 | US 169 | Reoverlay deck surface | 2029 | $ - | None |
75 | 6497 | Hwy 22 | Le Sueur River | Replace | N/A | $2,570,000 | Cost is greater than total available budget for year |
70 | 22811 | CSAH 17 | I 90 | Overlay deck surface | 2027 | $ - | None |
70 | 67001 | Hwy 270 | BNSF Railroad | Overlay deck surface | 2030 | $ - | None |
65 | 5495 | Hwy 13 | Sakatah Lake | Replace | 2028 | $300,000 | None |
65 | 6757 | Hwy 4 | Big Cottonwood River | Replace | 2023 | $2,250,000 | None |
65 | 07038 | Hwy 30 | Blue Earth River | Redeck | 2030 | $2,680,000 | None |
65 | 53809 | CSAH 15 | I 90 | Replace | N/A | $10,000 | Not a district priority. Will continue to monitor bridge performance. |
65 | 53824 | CR 60 | I 90 | Replace | N/A | $2,320,000 | Not a district priority. Will continue to monitor bridge performance. |
55 | 5965 | Hwy 4 | South Fork Watonwan River | Replace | 2024 | $800,000 | None |
55 | 22810 | CR 109 | I 90 | Redeck | 2027 | $ - | None |
55 | 22812 | CSAH 19 | I 90 | Redeck | 2027 | $650,000 | None |
55 | 22814 | Hwy 22 | I 90 | Redeck | 2029 | $1,290,000 | None |
45 | 9774 | CSAH 6 | I 90 | Replace | N/A | $790,000 | Not a district priority. Will continue to monitor bridge performance. |
35 | 07045 | Hwy 68 | Little Cottonwood River | OPM | 2029 | $1,270,000 | None |
35 | 32805 | CSAH 17 | I 90 | Replace | N/A | $650,000 | Not a district priority. Will continue to monitor bridge performance. |
35 | 32814 | CR 85 | I 90 | Replace | N/A | $1,910,000 | Not a district priority. Will continue to monitor bridge performance. |
10 | 07027 | Hwy 30 | Willow Creek | Overlay deck surface | 2030 | $730,000 | None |
10 | 22805 | CSAH 6 | I 90 | Overlay deck surface | 2027 | $790,000 | None |
10 | 22809 | CSAH 13 | I 90 | Overlay deck surface | 2027 | $3,190,000 | None |
10 | 22813 | CR 221 | I 90 | Overlay deck surface | 2027 | $2,810,000 | None |
10 | 22819 | CSAH 31 | I 90 | Overlay deck surface | 2027 | $100,000 | None |
10 | 22820 | CSAH 23 | I 90 | Reoverlay deck surface | 2027 | $600,000 | None |
10 | 46003 | Hwy 4 | Judicial Ditch #50 | Overlay deck surface | 2024 | $10,000 | None |
0 | 6504 | Hwy 4 | Elm Creek | Replace | 2024 | $ - | None |
0 | 22806 | CSAH 11 | I 90 | OPM | 2027 | $2,300,000 | None |
0 | 40003 | CSAH 45 | MN 22 | Overlay deck surface | 2024 | $2,080,000 | None |
0 | 52009 | US Hwy 169 | Belgrade Avenue | Reoverlay deck surface | 2025 | $540,000 | None |
0 | 72005 | Hwy 93 | Rush River | Replace | 2023 | $ - | None |