About this project

In spring 2025, Hwy 95 in North Branch will undergo a safety improvement. The project work will improve safety by constructing a dedicated left turn lane on Hwy 95 at 392nd St.

Summary of work

  • Construct left turn lane
  • Reconstruct existing shoulders
  • Resurface existing pavement