Motorists should expect changes to the Hwy 280 detour from 10 p.m. Fri, May 15 to 5 a.m. Mon, May 18. Sections of I 94 between Minneapolis and St. Paul will close for work on the John Ireland Blvd. bridge, affecting the usual Hwy 280 detour.
All traffic impacts are tentative and weather dependent. Access to businesses will be maintained during construction. In addition to the posted regional detour, please consider using Snelling Ave. for local detours. The Metro Transit Bus Routes 30 and 33 will continue serving existing bus stops during construction, but bus schedules may be affected by construction. Visit Metro Transit for the latest information.
Current
Road closures
Through late August
Hwy 280 is closed in both directions between Hwy 36/I-35W and I-94
Hwy 280 will reopen in both directions before the beginning of the State Fair in late August
Broadway St. is closed in both directions between Industrial Blvd. and Hwy 280
All other cross streets will remain open
Lane closures
Through late August
Energy Park Dr. is reduced to one lane in both directions under Hwy 280
Expect short-term intermittent lane closures on cross streets while bridge work is being done
Ramp closures
Through late August
The following ramps are closed:
Franklin Ave. to I-94
I-94 to University Ave.
Upcoming
Information about upcoming traffic impacts will be provided as details become available. After the State Fair, we will make efforts to limit traffic impacts to lane and ramp closures through fall 2026.
About this project
We are making significant improvements to Hwy 280 from I-94 in St. Paul to Hwy 36/I-35W in Roseville.
In 2026, we will resurface Hwy 280 from I-94 to Hwy 36/I-35W, repair bridges, repair and resurface ramps, repair drainage and make additional improvements. Motorists can expect a full closure of Hwy 280 from I-94 to Hwy 36/I-35W in 2026. A full closure allows crews to finish construction quickly and safely. Resurfacing the aging pavement, improving drainage and repairing bridges will extend the life of the highway and bridges, improve safety and provide a smoother ride for motorists.
In 2028, we will continue to repair bridges and make safety and accessibility improvements for those that travel along and across Hwy 280. These improvements are still being analyzed and considered. We will also permanently close the left turn from Hwy 280 to Broadway St. Northeast to prevent serious crashes from happening in the future. Right turns at the intersection of Hwy 280 and Broadway St. will remain open. There have been a number of serious crashes and close calls at this traffic signal that have been at high speeds. These high-speed crashes are extremely dangerous and can lead to serious or fatal injuries.
We are continuing to plan future safety and accessibility improvements along Hwy 280 for construction in a later year.
Summary of work
2026
Resurface Hwy 280 from I-94 to Hwy 36/I-35W
Repair Hwy 280 bridges over the following locations:
I-94
University of Minnesota Transitway and railroad tracks
Energy Park Dr.
Como Ave.
Hennepin/Larpenteur Ave.
I-35W
Repair and resurface the following ramps:
Energy Park Dr.
Como Ave.
Larpenteur Ave.
St. Croix St.
Replace drainage
Install new traffic signs
Replace guardrails
2028
Repair bridges that carry traffic over Hwy 280 at the following locations:
Wabash Ave.
Franklin Ave.
University Ave.
Territorial Rd.
Permanent closure of the left turn lane from Hwy 280 to Broadway St. Northeast