April 23, 2026

  • Crews install sanitary sewer from Lincoln Street to Luverne Street
  • Pavement removal from Cardinal Drive north to North Fairview

Starting April 27, 2026

  • Storm sewer installation from Lincoln Street to Luverne Street
  • Storm sewer installation from Cardinal Drive to Elm Street
  • Utility Relocations happening throughout the project

Access

  • Local access open from North 75 to James Street, Cashin Dr, and North Fairview
  • Minnesota Veterans Home open from north Hwy 75
  • Dodge Street and Adams Street open to cross Hwy 75

Closed

  • North of Main Street to Dodge Street
  • Cardinal Drive to North Fairview Street - No open crossings from Cardinal to North Fairview