Along west Mille Lacs Lake, Crow Wing and Mille Lacs counties

About this 2024 project

Begins late May

MnDOT will resurface and improve seven miles of Hwy 169 between Crow Wing Co. Rd. 26 south of Garrison to half-mile north of Ojibwe Dr.; includes new storm sewer, guardrail upgrades and new left-turn lanes at Co. Rd. 26 Timber Trail and Swing-A-Way/S Port.

Hwy 169 south of Garrison project map
Roadwork on Hwy 169 south of Garrison in 2024. Select map to enlarge

Summary of work

  • Resurface road and shoulders
  • Add left-turn lanes at:
    • Timber Trail Rd. (Co. Rd. 25)
    • Swing-A-Way/S Port
  • Replace three culverts
  • Upgrade guardrail

Future impacts

  • Weekdays: Expect short segments of alternate one lane, one-way traffic with flaggers, Mon–noon Fri, during daylight hours
  • Overnights: Sun night–Fri morning for approx. 2 weeks in June
  • Weekends/holidays: All lanes open