The construction costs shown on this list represent a very rough estimate based on limited information available at the time selection decisions were made. Actual construction and delivery costs will change over time as projects go from a concept through the project development process and are eventually constructed. View more detailed scores (Excel).
Last updated December 2023
Total Score | Route | Description | High Level Cost Estimate for Planning Purposes | Year Planned (FY) | Comments |
---|---|---|---|---|---|
83 | US71 | Rural reconstruction from Highway 23 to Willmar Bypass and additional locations on Highway 71 | $25,000,000 | 2028 | |
79 | MN23 | Medium mill and overlay from Highway 75 (Pipestone) to north of Highway 91 (Russel) | $13,400,000 | 2024 | |
79 | US71 | Reclaim and overlay from Redwood County Road 115 (Sanborn) to Highway 68 | $8,800,000 | 2027 | |
78 | MN23 | Major concrete rehabilitation from north of Highway 91 (Russel) to Highway 19 (Marshall) | $20,400,000 | 2029 | |
77 | US212 | Major concrete rehabilitation from Highway 23 (Granite Falls) to east of Highway 23 | $8,600,000 | Not Selected | The district is currently prioritizing other concrete segments that have not yet received a rehabilitation |
75 | MN15 | Thin mill and overlay from Highway 212 (Brownton) to Hutchinson | $3,200,000 | Not Selected | Candidate for Preventative Maintenance work in 2024 |
75 | US14 | Medium overlay and cold in inplace recycling from Lake Benton to Lincoln/Lyon County Line | $5,200,000 | 2027 | |
75 | US12 | Major concrete pavement rehabilitation from Darwin to Cokato | $10,700,000 | 2024 | |
75 | US212 | Medium overlay from Renville County road 16 to Renville County Road 7 | $3,700,000 | 2030 | |
73 | MN7 | Major concrete rehabilitation from Hutchinson to Silver Lake, and from McLeod County road 25 to Highway 7 (Hutchinson Bypass) | $9,200,000 | 2028 | |
72 | US59 | Medium overlay from Highway 14 to Lyon County Road 6 (Marshall) | $5,900,000 | 2028 | |
71 | MN15 | Medium overlay from Hutchinson to Highway 12 (Dassel) | $6,400,000 | Not Selected | District anticipates pavement conditions will not deteriorate as fast as the model predicts |
71 | US71 | Reclaim and overlay from Highway 68 to Redwood Falls | $6,800,000 | 2029 | |
71 | US12 | Medium overlay from Kerkhoven to Pennock | $3,800,000 | Not Selected | Candidate for preventive maintenance work in 2025 |
70 | MN15 | Reclaim and overlay from Highway 12 (Dassel) to Meeker/Stearns County Line | $8,400,000 | 2023 | This section has been prioritized because maintenance patching is losing effectiveness. |
70 | US14 | Medium mill and overlay from Highway 23 to Tracy | $9,400,000 | 2027 | |
70 | MN23 | Thin mill and overlay Highway 19 (Marshall) to Lyon County Road 33 | $1,200,000 | 2027 | This section has been prioritized because a thin mill and overlay will improve performance. |
69 | US59 | Medium overlay Highway 30 (Slayton) to north junction of Highway 30 | $3,000,000 | Not Selected | District anticipates pavement conditions will not deteriorate as fast as the model predicts |
69 | US212 | Minor concrete pavement rehab and diamond grinding from Olivia to Bird Island | $1,000,000 | Not Selected | District anticipates pavement conditions will not deteriorate as fast as the model predicts |
68 | US14 | Thin mill and overlay from Minnesota/South Dakota County line to US75 | $1,400,000 | 2029 | |
67 | MN23 | Medium mill and overlay from Rock/Pipestone County Line (Jasper) to HIghway30 (Pipestone) | $5,700,000 | Not Selected | |
67 | US71 | Medium mill and overlay from Highway 19 (Morton) to Olivia | $7,500,000 | Not Selected | |
65 | US14 | Medium overlay and cold in place recycling from Revere to Redwood/Brown County Line | $6,300,000 | Not Selected | |
64 | MN7 | Reclaim and overlay from Highway 40 (Milan) to Montevideo | $11,100,000 | Not Selected | |
56 | US71 | Concrete reconstruction from Highway 23 to Willmar Bypass | $7,900,000 | Not Selected | |
53 | US59 | Reconstruction from Highway 68 (Marshall) to Lyon County Road 33 | $8,900,000 | Not Selected | |
40 | MN22 | Concrete reconstruction from Glencoe to Hutchinson | $50,600,000 | Not Selected | |
40 | US12 | Thin overlay from Highway 22 to Highway 24 (Litchfield) | $200,000 | Not Selected | |
39 | US12 | Concrete reconstruction from Highway 71 to Kandiyohi/Meeker County Line | $58,300,000 | Not Selected | |
37 | US59 | Thin overlay from Nobles/Murray County Line to Highway 62 (Fulda) | $400,000 | Not Selected | |
36 | US71 | Thin overlay from Quality Drive (Redwood Falls) to Highway 71 and additional locations on Highway 71 | $1,300,000 | Not Selected | |
36 | US12 | Thin mill and overlay from 25th St. SE (Willmar) to Highway 71 | $400,000 | Not Selected | |
20 | US212 | Thin overlay eastbound from west of Highway 5 to Highway 5 | $100,000 | Not Selected | |
8 | MN7 | Thin mill and overlay on Highway 7 & Highway 25 Roundabout | $100,000 | Not Selected | |
8 | US71 | Thin overlay on Highway 71 & Highway 7 Roundabout | $100,000 | Not Selected | |
7 | MN15 | Thin overlay on Highway 19 (Winthrop) to north of Highway 19 | $100,000 | Not Selected | |
6 | MN7 | Minor concrete pavement rehab and diamond grinding at the intersection of Highway 23 & Highway 7 (Clara City) - approx. 1000 feet on each leg | $300,000 | Not Selected | |
MN19 and US71 | Major rehabilitation on MN19 from Qualit Dr to Centennial Dr and on US71 from Hwy 19 to Renville County Road 19 | $3,000,000 | 2030 |