Project Score | District | Route | Year Planned | Description | Federal Total | Local match | Total Project Cost | Comments |
---|---|---|---|---|---|---|---|---|
50 | 6 | TH-65 | 2027 | TH-65/PROSPECT AVE ROUNDABOUT | $2,469,593 | $274,399 | $2,743,992 | Prior approval: insufficient funds at this time |
90 | 6 | TH-57 | 2027 | TH-57/CSAH-16 ROUNDABOUT | $2,278,800 | $717,195 | $2,995,995 | Prior approval |
54 | 6 | TH-44 | 2027 | TH-44/TH-76 ROUNDABOUT | $3,412,515 | $666,000 | $4,078,515 | Prior approval: insufficient funds at this time |
64 | 1 | US-53 | 2026 | TH-53/CSAH-146 (HAT TRICK AVE) OFFSET INTERSECTION | $1,170,000 | $130,000 | $1,300,000 | |
57 | 1 | US-53 | 2025 | TH-53/CSAH-142 ROUNDABOUT | $1,200,000 | $1,133,333 | $2,333,333 | |
95 | 2 | Districtwide | 2025 | DISTRICTWIDE ENHANCED EDGELINE PAVEMENT MARKINGS | $540,000 | $60,000 | $600,000 | Additional funds requested from Nov21_D2-03 ($360K HSIP of $400K total) |
94 | 2 | MN-200 | 2026 | TH-200 FROM LAPORTE TO TH-371 SHOULDER PAVING, RUMBLE STRIPS, CLEAR ZONE MAINTENANCE | $800,000 | $80,000 | $880,000 | |
54 | 3 | US-169 | 2026 | TH-27/TH-169 ROUNDABOUT | $2,250,000 | $250,000 | $2,500,000 | |
63 | 3 | US-71 | 2027 | TH-71/TH-210 ROUNDABOUT | $1,800,000 | $200,000 | $2,000,000 | |
53 | 3 | US-10 | 2027 | (RESUBMIT) | $900,000 | $100,000 | $1,000,000 | Prior approval: insufficient funds at this time |
80 | 3 | MN-4 | 2026 | TH-4/CSAH-32 REALIGNMENT AND LIGHTING | $225,000 | $25,000 | $250,000 | |
56 | 3 | MN-23 | 2027 | TH-23/CSAH-8 J-TURN | $1,080,000 | $120,000 | $1,200,000 | Prior approval |
62 | 3 | US-10 | 2027 | TH-10/CSAH-16 AND TH-10/CSAH-11 J-TURNS | $1,350,000 | $150,000 | $1,500,000 | Prior approval |
55 | 3 | MN-23 | CHIP | TH-23/BEL CLARE DR J-TURN | $1,080,000 | $120,000 | $1,200,000 | Recommend funding in future year once funding targets are available |
50 | 3 | MN-47 | CHIP | TH-47/CSAH-5 ROUNDABOUT | $2,250,000 | $250,000 | $2,500,000 | Recommend funding in future year once funding targets are available |
50 | 3 | MN-371 | CHIP | TH-371/CSAH-29 J-TURN | $1,800,000 | $200,000 | $2,000,000 | Recommend funding in future year once funding targets are available |
51 | 3 | MN-47 | CHIP | TH-47/CSAH-8 ROUNDABOUT | $2,250,000 | $250,000 | $2,500,000 | Recommend funding in future year once funding targets are available |
56 | 3 | US-10 | 2027 | TH-71 FROM SAUK CENTRE TO LONG PRAIRIE CENTERLINE RUMBLE STRIPS AND 6-INCH MARKINGS | $900,000 | $100,000 | $1,000,000 | Nov22_D3-03 resubmission |
99 | 3 | US-71 | 2025 | TH-10 AND CR-40/155TH ST RCI | $67,500 | $7,500 | $75,000 | |
94 | 4 | TH-108 | 2024 | TH-108 FROM PELICAN RAPIDS TO TH-78 N-JCT SIGN PANEL AND STRUCTURE UPGRADES | $600,000 | $60,000 | $660,000 | |
93 | 4 | Districtwide | 2025 | DISTRICTWIDE ENHANCED EDGELINE PAVEMENT MARKINGS | $760,000 | $76,000 | $836,000 | |
58 | 4 | TH-29 | 2025 | TH-29 FROM BROADWAY ST TO NOKOMIS ST (ALEXANDRIA) PEDESTRIAN SAFETY IMPROVEMENTS | $750,000 | $75,000 | $825,000 | |
94 | 4 | TH-113 | 2025 | TH-113 FROM MAHOMEN COUNTY LINE TO TH-71 SIGN PANEL AND STRUCTURE UPGRADES | $1,200,000 | $120,000 | $1,320,000 | |
72 | 6 | TH-63 | 2027 | TH-63/TH-247/CSAH-12 ROUNDABOUT | $2,883,600 | $320,400 | $3,204,000 | |
50 | 7 | TH-13 | 2026 | TH-13/TH-99 ROUNDABOUT | $2,400,000 | $370,000 | $2,770,000 | |
79 | 8 | TH-23 | 2027 | TH-23/TH-9 AT GRADE SAFETY IMPROVEMENT, ACCESS MANAGEMENT, PEDESTRIAN CROSSING | $2,250,000 | $250,000 | $2,500,000 | |
100 | 8 | Districtwide | 2025 | DISTRICTWIDE CENTERLINE RUMBLE STRIPS ON CONCRETE ROADWAYS | $1,710,000 | $190,000 | $1,900,000 |