Non-National Highway System pavement projects
MnDOT Metro District
How the projects scored in 2020
The construction costs shown on this list represent a very rough estimate based on limited information available at the time selection decisions were made. Actual construction and delivery costs will change over time as projects go from a concept through the project development process and are eventually constructed. View more detailed scores (Excel).
Last updated December 2020
Score | Route | Description | High level construction cost estimate for planning purposes | Year Planned (FY) | Comments |
---|---|---|---|---|---|
90 | MN 13 | Medium mill and overlay from I-35W to Yankee Doodle Road | $6,370,000 | Not Selected | Not district priority. Will continue to monitor pavement performance |
83 | MN 5 | Medium mill and overlay from Carver County Road 17 to Hennepin County Road 4 | $3,260,000 | Not Selected | Not district priority. Will continue to monitor pavement performance |
83 | MN 97 | Thin mill and overlay from Roundabout to Hwy 95 | $11,450,000 | 2028 | |
82 | MN 19 | Medium mill and overlay from Red Wing Ave to LeSueur/Scott County Line | $220,000 | Not Selected | Not district priority. Will continue to monitor pavement performance |
81 | MN 5 | Medium mill and overlay from Fuller Rd to Wooddale Ave | $710,000 | Not Selected | Not district priority. Will continue to monitor pavement performance |
81 | MN 5 | Medium mill and overlay from County Road 4 to Fuller Rd | $580,000 | Not Selected | Not district priority. Will continue to monitor pavement performance |
80 | US 10 | Medium mill and overlay from .2 miles north of I-694 to I-694 | $470,000 | Not Selected | Not district priority. Will continue to monitor pavement performance |
79 | MN 62 | Medium mill and overlay from I-35E to Hwy 52 | $3,420,000 | Not Selected | Recent rehabilitation completed |
79 | MN 13 | Medium mill and overlay from Senneca Rd to Yankee Doodle Rd | $620,000 | Not Selected | Not district priority. Will continue to monitor pavement performance |
78 | MN 25 | Medium mill and overlay from White sty to State St | $60,000 | Not Selected | Not district priority. Will continue to monitor pavement performance |
77 | MN 13 | Medium mill and overlay from County Road 42 to Connelly Pkwy | $790,000 | Not Selected | Not district priority. Will continue to monitor pavement performance |
77 | US 61 | Medium mill and overlay from Roselawn Ave to Hwy 36 | $1,090,000 | Not Selected | Not district priority. Will continue to monitor pavement performance |
77 | US 61 | Medium mill and overlay from I-694 to White Bear Ave | $2,480,000 | Not Selected | Not district priority. Will continue to monitor pavement performance |
77 | MN 19 | Thin mill and overlay from LeSueur/Scott County Line to Scott/Rice County Line | $3,330,000 | 2027 | |
77 | MN 282 | Major rehabilitation from Hwy 21 to Hwy 13 | $1,170,000 | 2021 | |
76 | MN 5 | Major rehabilitation from Sibley/Carver County line to 142nd St | $460,000 | 2021 | |
75 | MN 47 | Medium mill and overlay from 27th Ave to 35th Ave | $1,080,000 | Not Selected | Not district priority. Will continue to monitor pavement performance |
75 | MN 120 | Medium mill and overlay from Ridge Dr to 4th St in Oakdale | $1,410,000 | 2026 | |
75 | US 10 | Thin mill and overlay from Hwy 61 to Saint Croix River bridge | $460,000 | 2027 | Poor ride quality requires resurfacing. |
75 | MN 149 | Major rehabilitation from Hwy 55 to I-494 | $320,000 | 2028 | |
74 | MN 3 | Reconstruction from Amana trail to south of Upper 55th Ave | $6,110,000 | 2029 | |
74 | MN 97 | Medium mill and overlay from east of Everton Ave to Hwy 61 Roundabout | $30,000 | 2024 | |
74 | MN 41 | Medium mill and overlay from Engler Rd to Pioneer Tr | $520,000 | Not Selected | Not district priority. Will continue to monitor pavement performance |
73 | MN 47 | Reclaim and overlay from 153rd Ave to Cree St | $15,560,000 | 2027 | |
73 | MN 95 | Reclaim and overlay from Chisago County road 14 to Sunrise river | $10,630,000 | 2028 | |
73 | MN 95 | Reconstruction from Oakview Ave to Chisago County Rd 14 | $6,900,000 | 2028 | |
73 | MN 97 | Medium mill and overlay from US61 Roundabout to end of US61 Roundabout | $40,000 | 2024 | |
72 | US 61 | Medium mill and overlay from Hwy 36 to I-694 | $1,690,000 | Not Selected | Not district priority. Will continue to monitor pavement performance |
72 | MN 95 | Medium mill and overlay from Bailey Rd to 70th St | $730,000 | Not Selected | Recent rehabilitation completed |
71 | MN 3 | Medium mill and overlay from 190th to Dakota County Road 58 | $610,000 | Not Selected | Newer roundabout completed |
71 | MN 13 | Medium mill and overlay from .4 miles west of Dakota Ave to .2 miles east of Dakota Ave | $600,000 | Not Selected | Not district priority. Will continue to monitor pavement performance |
71 | MN 13 | Medium mil and overlay from Yankee Doodle Rd to I-494 | $380,000 | Not Selected | Not district priority. Will continue to monitor pavement performance |
71 | US 61 | Medium mill and overlay from Hwy 96 to .8 miles north | $400,000 | Not Selected | Recent rehabilitation completed |
71 | MN 252 | Major rehabilitation from 85th to Hwy 610 | $440,000 | 2025 | Corridors of commerce |
70 | MN 101 | Medium mill and overlay from Carver County Road 61 to Carver County Road 14 | $280,000 | Not Selected | Not district priority. Will continue to monitor pavement performance |
70 | MN 3 | Medium mill and overlay from Upper 55th St to Robert St | $790,000 | 2029 | Selected prior to policy (in 2019-2028 CHIP) |
70 | MN 3 | Medium mill and overlay from Railroad crossing to Chesterfield. | $260,000 | Not Selected | Not district priority. Will continue to monitor pavement performance |
70 | MN 25 | Medium mill and overlay from Scott County line to Sibley County Road 14 | $500,000 | Not Selected | Not district priority. Will continue to monitor pavement performance |
70 | MN 25 | Medium mill and overlay from Sibley County Road 14 to Hwy 5 | $3,020,000 | Not Selected | Not district priority. Will continue to monitor pavement performance |
70 | MN 95 | Medium mill and overlay from Hwy 36 to north of 56th St N | $940,000 | Not Selected | Not district priority. Will continue to monitor pavement performance |
69 | MN 5 | Medium mill and overlay from Birch St to Scandia Rd | $930,000 | Not Selected | Not district priority. Will continue to monitor pavement performance |
69 | MN 47 | Major rehabilitation from Central Ave to Broadway St | $730,000 | 2024 | |
69 | MN 13 | Major reconstruction from I-494 to Hwy 55 | $5,250,000 | 2026 | |
69 | MN 50 | Medium mill and overlay from Hwy 52 to Hwy 60 | $5,630,000 | 2026 | |
69 | US 61 | Medium mill and overlay from Hwy 97 to north of Washington County Road 2 | $7,600,000 | 2030 | RQI is predicted to fall into the poor category before 2030. |
69 | US 61 | Medium mill and overlay from Frenchman Rd to Trailer Park Entrance | $180,000 | Not Selected | |
69 | US 61 | Medium mill and overlay from Forest Lake Circle to south of 250th St N | $310,000 | Not Selected | |
69 | MN 284 | Reclaim and overlay from Hwy 212 to Elm Creek Rd | $5,760,000 | 2026 | Selected prior to policy (in 2019-2028 CHIP) |
69 | MN 21 | Medium mill and overlay from south of Old Hwy 169 to Mill St | $120,000 | 2027 | |
68 | MN 21 | Medium mill and overlay from 230th St to Meadow Wood Court | $570,000 | Not Selected | |
67 | US 61 | Medium mill and overlay from 250th St N | $330,000 | Not Selected | |
67 | US 61 | Medium mill and overlay from Chisago County Road 31/32 to 267th St in Wyoming | $70,000 | Not Selected | |
67 | MN 19 | Medium mill and overlay from Scott County Road 143 to 11th ave SW | $90,000 | Not Selected | |
67 | MN 95 | Medium mill and overlay from north of Commercial Ave to Hwy 36 | $440,000 | Not Selected | |
66 | MN 97 | Medium mill and overlay from I-35W to Hwy 61 | $500,000 | 2024 | |
65 | MN 47 | Medium mill and overlay from Broadway St to 27th Ave NE | $1,270,000 | Not Selected | |
65 | MN 3 | Medium mill and overlay from 145th St to Hwy 149 | $5,760,000 | 2026 | Selected prior to policy (in 2019-2028 CHIP) |
65 | MN 13 | Medium mill and overlay from I-35E to Hwy 13 | $480,000 | Not Selected | |
65 | MN 95 | Medium mill and overlay from .25 miles South of Valley Creek to .25 miles north of Valley Creek | $100,000 | Not Selected | |
65 | MN 149 | Medium mill and overlay from Hwy 3 to Albano Tr | $100,000 | Not Selected | |
64 | MN 13 | Medium mill and overlay from 2nd St to U-35E | $360,000 | Not Selected | |
63 | MN 5 | Medium mill and overlay from .2 miles east of Carver County Road1 0 to .2 miles west of Carver County Road 10 | $90,000 | Not Selected | |
63 | MN 121 | Medium mill and overlay from Pedestrian Bridge to 58th St | $1,230,000 | 2025 | Selected prior to policy (in 2019-2028 CHIP) |
63 | MN 95 | Medium mill and overlay from Vista Road to Chisago County Road 16 | $180,000 | Not Selected | |
63 | MN 96 | Medium mill and overlay from Hwy 61 to Hwy 95 | $15,350,000 | 2030 | RQI currently in the poor to fair range. |
62 | MN 19 | Medium mill and overlay from 11th Ave SW to 5th Ave SW | $90,000 | Not Selected | |
62 | MN 95 | Medium mill and overlay from .7 miles north of I-94 to I-94 | $360,000 | Not Selected | |
62 | MN 95 | Medium mill and overlay from I-94 to Valley Creek | $300,000 | Not Selected | |
62 | MN 41 | Medium mill and overlay from Pioneer Tr to Hwy 5 | $440,000 | 2023 | Selected prior to policy (in 2019-2022 STIP) |
62 | MN 41 | Medium mill and overlay from Hwy 5 to Hwy 7 | $530,000 | Not Selected | |
61 | MN 5 | Medium mill and overlay from Hwy 25 to .1 miles north | $20,000 | Not Selected | |
61 | MN 25 | Medium mill and overlay from Hwy 5 to Hwy 7 | $1,320,000 | 2021 | Selected prior to policy (in 2019-2022 STIP) |
60 | MN 13 | Reclaim and overlay form Eagle Creek to Scott County Road 42 | $5,360,000 | 2030 | RQI currently in the poor to fair range. |
60 | MN 95 | Reclaim and overlay from Hwy 8 to Hwy 97 | $19,580,000 | 2029 | Selected prior to policy (in 2019-2028 CHIP) |
59 | MN 25 | Thin mill and overlay from Hwy 212 to Hwy 5 | $2,820,000 | 2026 | Selected prior to policy (in 2019-2028 CHIP) |
59 | US 61 | Major rehabilitation from 267th St to I35 | $80,000 | 2021 | Selected prior to policy (in 2019-2022 STIP) |
58 | MN 3 | Medium mill and overlay from Ann Marie Tr to Amana Tr | $50,000 | Not Selected | |
57 | MN 25 | Medium mill and overlay from .2 miles south of Hwy 7 to Hwy 7 | $50,000 | Not Selected | |
56 | MN 95 | Medium mill and overlay from Chestnut St to north of Commercial Ave | $210,000 | Not Selected | |
55 | MN 101 | Medium mill and overlay from Hwy 5 to Town Line Rd | $2,180,000 | 2026 | Selected prior to policy (in 2019-2028 CHIP) |
55 | MN 3 | Medium mill and overlay from Ann Marie Trail to Amana Trail | $170,000 | Not Selected | |
54 | MN 13 | Medium mill and overlay from Hwy 55 to 2nd St | $460,000 | Not Selected | |
50 | MN 5 | Thin mill and overlay from Carver County Road 11 to Hwy 41 | $4,900,000 | 2029 | Selected prior to policy (in 2019-2028 CHIP) |
48 | MN 51 | Thin mill and overlay from Hwy 36 to Grey Fox Rd | $5,760,000 | 2026 | Longitudinal joint distresses need fixing; not necessarily associated with poor ride. Other area needs included. |
46 | MN 20 | Thin mill and overlay from Hwy 19 to Hwy 50 | $6,620,000 | 2028 | Selected prior to policy (in 2019-2028 CHIP) |
44 | MN 62 | Thin mill and overlay from Mendota to I35E | $1,250,000 | 2025 | Predicted RQI does not match on the ground conditions. Poor condition requires resurfacing. |
43 | MN 25 | Medium mill and overlay from Hwy 7 to White St | $1,120,000 | Not Selected | |
42 | MN 3 | Thin mill and overlay from Rice/Dakota County line to Hwy 50 | $8,740,000 | 2028 | Thin mill and overlay selected for preventive maintenance. |
41 | US 10 | Medium mill and overlay from I35W to north of I494/694 | $970,000 | Not Selected | |
41 | MN 95 | Thin mill and overlay from Isanti trail to west of Falcon Ave | $1,520,000 | 2028 | Poor ride requires resurfacing. Coordinating with locals. |
40 | MN 56 | Thin mill and overlay from Goodhue/Dakota County line to Hwy 50 | $4,390,000 | 2027 | Thin mill and overlay selected for preventive maintenance. |
38 | MN 95 | Medium mill and overlay from old County Road 15 to south of Hudson Rd D | $440,000 | Not Selected | |
37 | MN 95 | Medium mill and overlay from .7 miles north of I-94 to I-94 | $350,000 | Not Selected | |
34 | MN 5 | Major rehabilitation from 142nd St to Hwy 212 | $140,000 | 2021 | Selected prior to policy (in 2019-2022 STIP) |
34 | MN 47 | Thin mill and overlay from 40th Ave to Hwy 10 | $15,790,000 | 2030 | RQI predictions do not match conditions on the ground. Requires resurfacing. Other area and local needs included. |
34 | MN 13 | Medium mill and overlay from Hwy 19 to 1.5 miles north of Hwy 19 | $1,530,000 | Not Selected | |
32 | US 61 | Medium mill and overlay from south of 170th st to .1 miles north of 170th | $60,000 | Not Selected | Recent roundabout completed |
30 | MN 101 | Medium mill and overlay from Carver County Road 14 to Kiowa Tr | $1,070,000 | Not Selected | |
29 | MN 101 | Medium mill and overlay from Kiowa Tr to Lyman Blvd | $170,000 | Not Selected | |
28 | MN 95 | Reclaim and overlay from Isanti/Chisago County line to north of 392nd st | $1,380,000 | 2028 | Poor ride quality requires resurfacing. Coordinating with locals. |
26 | MN 95 | Medium mill and overlay from Valley Crk to Jct Bailey | $480,000 | Not Selected | |
26 | MN 95 | Medium mill and overlay from 70th St to Hwy 61 | $1,250,000 | Not Selected | |
19 | MN 55 | Thin mill and overlay from Hwy 100 to Lyndale Ave | $2,020,000 | Not Selected | RQI predictions do not match conditions on the ground. Requires resurfacing. Other functional and local needs included. |
19 | MN 47 | Thin mill and overlay from Cree St to Anoka/Isanti County line | $3,320,000 | 2025 | Pavement is rough but surface work is secondary. Project driven by safety. |
13 | MN 95 | Thin mill and overlay from Hwy 97 to north of Commercial Ave | $17,710,000 | 2029 | RQI prediction does not match conditions on the ground. Poor ride requires resurfacing. |
9 | MN 47 | Thin mill and overlay from Industry ave to 153rd | $2,130,000 | 2027 | Thin mill and overlay selected for preventive maintenance. |
4 | MN 244 | Thin mill and overlay from Ash St to Hwy 96 | $1,050,000 | 2025 | Notoriously poor riding urban section. Requires resurfacing. Other functional area and local needs included. |