Urban non-freeway/non-expressway pavement projects
MnDOT District 8
How the projects scored in 2020
The construction costs shown on this list represent a very rough estimate based on limited information available at the time selection decisions were made. Actual construction and delivery costs will change over time as projects go from a concept through the project development process and are eventually constructed. View more detailed scores (Excel).
Last updated December 2020
Score | Community | Route | Description | High-Level Cost Estimate for Planning Purposes | Year Planned (FY) | Comments |
---|---|---|---|---|---|---|
88 | Litchfield | US12 | Medium mill and overlay Highway 22 to Meeker County Road 34 (Litchfield) | $700,000 | 2023 | |
84 | Marshall | MN19 | Concrete reconstruction from 2nd St. to Minnesota St. (Marshall) | $5,700,000 | 2025 | |
84 | Willmar | US12 | Medium mill and overlay from 11th St. W. to 6th St. E. (Willmar) | $2,000,000 | 2027 | |
79 | Marshall | US59 | Reconstruction from Highway 23 to the junction of Highway 68/Highway 19 (Marshall) | $7,800,000 | Not selected | A nearby section of roadway is programmed for reconstruction. Waiting to avoid multiple years of detours. |
76 | Marshall | MN19 | Concrete reconstruction from Minnesota St. to Highway 23 (Marshall) | $13,600,000 | Not selected | A nearby section of roadway is programmed for reconstruction. Waiting to avoid multiple years of detours. |
75 | Marshall | MN19 | Concrete reconstruction from Lyon County Road 7 to 2nd St. (Marshall) | $8,000,000 | Not selected | A nearby section of roadway is programmed for reconstruction. Waiting to avoid multiple years of detours. |
73 | Pipestone | US75 | Reconstruction from Highway 30 to 4th St N (Pipestone) | $4,500,000 | Not selected | This segment was rehabilitated in 2018 |
73 | Glencoe | MN22 | Medium mill and overlay from Highway 212 to Cedar Ave (Glencoe) | $600,000 | 2023 | |
72 | Pipestone | MN30 | Reconstruction from 4th Ave. W. to Highway 75 (Pipestone) | $11,400,000 | Not selected | This segment was rehabilitated in 2017 |
71 | Clara City | MN23 | Medium mill and overlay Highway 7 to Bridge number 12012 (Clara City) | $400,000 | Not selected | This segment was rehabilitated in 2017 |
69 | Morton | MN19 | Reconstruction from Centennial Dr. to Brook Dr. (Morton) | $1,900,000 | Not selected | This segment was rehabilitated in 2016 |
69 | Canby | US75 | Reconstruction from near St Olaf Ave S to Yellow Medicine County Road 3 (Canby) | $8,700,000 | Not selected | This segment was rehabilitated in 2016 |
69 | Olivia | US212 | Reconstruction from the west junction of Highway 71/320th sty to the East junction of Highway 71/13th St (Olivia) | $11,200,000 | Not selected | This segment was rehabilitated in 2014 |
66 | Ivanhoe | MN19 | Medium mill and overlay from Rebecca St. to Lincoln County Road 5 (Ivanhoe) | $300,000 | 2029 | Coordinated with a NHS pavement project |
66 | New London | MN9 | Thick mill and overlay from Highway 23 to 1st Ave SE (New London) | $700,000 | Not selected | |
66 | Hutchinson | MN15 | Reconstruction from 5th Ave to High Drive in Hutchinson | $1,300,000 | Not selected | |
66 | Montevideo | US212 | Medium mill and overlay from Yellow Medicine/Chippewa County Line to Hwy 29 in Montevideo | $200,000 | Not selected | |
65 | Renville | US212 | Reconstruction from Renville County Road 6 to 5th St E (Renville) | $6,500,000 | Not selected | |
65 | Clarkfield | MN67 | Reconstruction Highway 59 to 6th St. (Clarkfield) | $2,700,000 | 2024 | Selected prior to policy (In 2019-2028 CHIP) |
64 | Litchfield | US12 | Resurfacing from Hwy 24 to 4th St in Litchfield | $500,000 | Not selected | |
63 | Litchfield | MN22 | Concrete reconstruction from Pleasure Dr. to Highway 12 (Litchfield) | $5,200,000 | Not selected | |
63 | Madison | US75 | Medium mill and overlay from Highway 40 to 8th St and Highway 40 from Highway 75 to Western Ave (Madison) | $2,000,000 | 2023 | This section has been prioritized because the pavement will be 17 years old |
63 | Lake Benton | US14 | Reconstruction from South Valley St to Highway 14 and from near the Railroad tracks to Jesse St | $5,500,000 | 2027 | The District has been coordinating with the City to replace their utilities. |
62 | Tracy | US14 | Medium mill and overlay from Lyon County Road 28 to 4th St. E. (Tracy) | $700,000 | 2028 | Coordinated with a Non-NHS pavement project |
62 | Grove City | US 12 | Reconstruction from west junction Hwy 4 to east junction Hwy 4 Grove City | $1,400,000 | Not selected | |
62 | Danube | US212 | Reconstruction from Freedom St to 2nd St in Danube | $2,600,000 | Not selected | |
61 | Redwood Falls | US71 | Reconstruction from 11th St to Quality Dr | $11,000,000 | Not selected | |
61 | Granite Falls | US212 | Reconstruction from 17th St to Hwy 23 in Granite Falls | $3,700,000 | Not selected | |
60 | Montevideo | MN7 | Thin mill and overlay from Highway 29 to 28th St | $1,000,000 | 2026 | Due to a rapid drop in pavement quality, the district is planning a thin mill and overlay in 2026 to extend the current lifespan of this segment. |
59 | Fairfax | MN19 | Reconstruction from 1st St to Highway 4 (Fairfax) | $4,000,000 | Not selected | |
57 | Dawson | US212 | Reconstruction from Highway 119 to Lac qui Parle County 39 (Dawson) | $7,700,000 | Not selected | |
55 | Redwood Falls | MN67 | Reconstruction on Highway 71 to Veda Dr. (Redwood Falls) | $7,700,000 | Not selected | |
53 | Hutchinson | MN15 | Thin mill and overlay from 5th Ave. to McLeod County Road 15 (Hutchinson) | $200,000 | Not selected | |
46 | Hutchinson | MN7 | Major concrete pavement rehab and diamond grinding Buff St. to Technology Dr. (Hutchinson) | $1,300,000 | Not selected | |
38 | Hendricks | MN271 | Thin mill and overlay from Railroad St. to Henderson St. (Hendricks) | $200,000 | Not selected | |
37 | Walnut Grove | US14 | Reconstruction from 8th St to 6th St in Walnut Grove | $3,700,000 | Not selected | |
35 | Olivia | US212 | Resurfacing from Hwy [@Description]71 to Renville County Road 14 in Olivia | $200,000 | Not selected | |
28 | Redwood Falls | MN19 | Resurfacing from Minnesota St to Sunrise Blvd in Redwood falls | $400,000 | Not selected | |
28 | Bird Island | US212 | Resurfacing from 10th St to 1st St in Bird Island | $200,000 | Not selected | |
25 | Eden Valley | MN22 | Thin mill and overlay Highway 55 to Meeker/Stearns County Line (Eden Valley) | $100,000 | Not selected | |
21 | Marshall | MN68 | Resurfacing from Hwy 59 to Hwy 19 in Marshall | $200,000 | Not selected | |
20 | Iona | MN267 | Thin mill and overlay from Murray County Road 4 to Ireland Ave. (Iona) | $100,000 | Not selected | |
16 | Cosmos | MN4 | Thin mill and overlay from Southern Cross Ave. to Northern Cross Ave. (Cosmos) | $400,000 | Not selected | |
16 | Eden Valley | MN22 | Thin mill and overlay from Hwy 55 to Meeker/Stearns County Line in Eden Valley | $100,000 | Not selected |