The construction costs shown on this list represent a very rough estimate based on limited information available at the time selection decisions were made. Actual construction and delivery costs will change over time as projects go from a concept through the project development process and are eventually constructed. View more detailed scores (Excel).
Last updated December 2020
Score | Route | Description | High Level Cost Estimate for Planning Purposes | Year Planned (FY) | Comments |
---|---|---|---|---|---|
100 | I94 | Mill and overlay from east of Melrose to east of Freeport | $8,400,000 | 2029 | |
94 | I94 | Mill and overlay from Hwy 71/Sauk Centre to East of Melrose | $9,900,000 | 2029 | |
92 | MN15 | Mill and overlay from Stearns County Road 47 to Stearns County Road 33 entrance Ramp | $12,000,000 | 2030 | |
91 | MN23 | Mill and overlay from bypass to Jct Hwy 15 | $10,000,000 | 2026 | |
90 | I94 | Mill and and overlay from east of Freeport to eastern limits of Albany | $6,200,000 | 2027 | |
88 | MN23 | Mill and overlay from Hwy 15 to west of 4th ave South | $5,600,000 | 2027 | |
87 | US 12 | Mill and overlay from Howard Lake to 72nd st in Delano | $2,800,000 | 2022 | |
86 | US 10 | Mill and overlay from west of Hwy 371 to Morrison County Road 35 | $5,800,000 | 2025 | |
86 | US 10 | Mill and overlay from Morrison County Road 35 to Benton County Road 40 | $15,200,000 | 2027 | |
85 | MN25 | Mill and overlay from I-94 bridge to Jct Hwy10 | $4,300,000 | 2028 | |
85 | MN210 | Reconstruction from end of River bridge in Brainerd to east of Hwy 25 | $18,400,000 | 2025 | |
84 | US 169 | Mill and overlay from Ojibwe Dr to Garrison | $4,500,000 | 2024 | |
83 | US 10 | Mill and overlay from County Road 11 to 3 miles west of Hwy 371 | $12,400,000 | 2029 | |
83 | US 10 | Mill and overlay from 4.4 miles west of Clear Lake to 2.2 miles west of Clear Lake | $1,200,000 | Not Selected | Not a district priority. Will continue to monitor pavement performance. |
83 | US 169 | Mill and overlay from north of Mille Lacs County Road 29 to 2.3 miles south of Milaca | $9,400,000 | 2025 | |
80 | MN25 | Mill and overlay from north of 14th St to the southern limits of Monticello | $5,400,000 | 2025 | |
80 | MN210 | Mill and overlay from Hwy 10 to Pillager | $5,000,000 | 2026 | |
79 | US 10 | Mill and overlay from west of Oink Joint Rd to Staples City Limits | $13,000,000 | 2029 | |
78 | MN23 | Mill and overlay from east of Stearns County Road 12 to end of bypass | $15,100,000 | 2027 | |
78 | MN101 | Mill and overlay from Hennepin/Wright County Line to south of Wright County Road 42 | $2,500,000 | 2025 | |
77 | US 10 | Mill and overlay from Main st in Elk River to Hwy 101 in Elk River | $400,000 | Not Selected | Not a district priority. Will continue to monitor pavement performance. |
77 | US 71 | Mill and overlay from 4th St in Sauk Centre to 230th in Long Prairie | $13,700,000 | 2027 | |
77 | US 71 | Mill and overlay from Todd/Wadena County line to Franklin Ave in Wadena | $3,000,000 | 2027 | |
76 | US 10 | Mill and overlay from Long Prairie River to 50th Ave | $17,800,000 | 2028 | |
76 | MN23 | Mill and overlay from District 3/8 border to Hwy 23B | $200,000 | Not Selected | Conditions on the ground are not deteriorating as fast as the model is predicting |
76 | MN55 | Mill and overlay from Hwy 25 to east of Wright County Road 134 | $4,200,000 | 2026 | |
76 | US 71 | Mill and overlay from Elm Ave in Wadena to 5th St in Sebeka | $10,200,000 | 2026 | |
74 | US 169 | Mill and overlay from south of Hwy 23 in Milaca to North of Mile Drew Brook | $8,100,000 | 2028 | |
74 | MN371 | Mill and overlay from Cass County Road 5 in Hackensack to North of Hwy 200 | $4,000,000 | 2025 | |
71 | US 2 | Mill and overlay from Cass County Road 206 in Cass Lake to east end of Bridge 5760 | $3,200,000 | 2022 | |
71 | MN23 | Mill and overlay from Hwy 25 to Benton County Road 53 | $1,400,000 | 2030 | |
71 | US 169 | Mill and overlay from South of Rum River bridge to Reference Pt 204 | $700,000 | Not Selected | Not a district priority. Will continue to monitor pavement performance. |
71 | MN210 | Thick overlay from Pillager to Baxter City Limits | $6,500,000 | 2030 | |
70 | US 71 | Mill and overlay from 5th St in Sebeka to Wadena/ Hubbard County line | $7,700,000 | 2027 | |
70 | MN101 | Minor rehabilitation from Wright County Road 42 to bridge over Hwy10 | $2,100,000 | 2030 | |
70 | US 169 | Mill and overlay from Aitkin County Line to Aitkin County Road 76 | $8,500,000 | 2029 | |
70 | US 169 | Milll and overlay from Mill Lacs County Road 103 to Vineland | $4,500,000 | Not Selected | Not a district priority. Will continue to monitor pavement performance. |
59 | US 2 | Thin mill and overlay from Hubbard/Cass County Line to Cass County Road 206 in Cass Lake | $2,900,000 | 2025 | |
69 | MN24 | Reclaim and overlay from I-94 ramps to east of Sherburne County Road 8 | $600,000 | Not Selected | Not a district priority. Will continue to monitor pavement performance. |
69 | MN371 | Reclaim and overlay from Steamboat River Bridge to Reference point 112 | $8,000,000 | 2030 | |
68 | MN210 | Mill and overlay from east end of Hospital Parking lot to Hwy 6 in Deerwood | $4,200,000 | 2027 | |
68 | MN371 | Mill and overlay from Hwy 200 to north of Highland Ave | $7,000,000 | 2027 | |
65 | I94 | Mill and overlay from Hwy 24 in Clearwater to North of Albertville | $7,600,000 | Not Selected | Recently resurfaced in 2019 |
65 | MN210 | Mill and overlay from Wisconsin ave in Hewitt to Hwy10 | $11,200,000 | 2027 | |
63 | I94 | Minor rehabilitation from Douglass/Todd County line to Hwy 71 in Sauk Centre | $11,600,000 | 2030 | |
63 | US 169 | Mill and overlay from North end of Mississippi River Bridge to Aitkin County Road 18 | $4,800,000 | 2024 | Coordinated with D1 project |
63 | US 169 | Mill and overlay from Aitkin County Road 18 to Hwy 200 in Hill City | $5,000,000 | 2025 | Coordinated with D1 project |
61 | MN28 | Reclaim and overlay from Pope/Stearns County Line to Hwy71 | $3,400,000 | Not Selected | |
60 | MN210 | Mill and overlay from Ottertail/Todd County Line to Wisconsin Ave in Hewitt | $1,400,000 | 2025 | |
59 | I94 | Reclaim and overlay from east limits of Albany to Stearns County Road 159 | $14,000,000 | 2030 | |
58 | MN34 | Mill and overlay from Hubbard/Cass County Line to Hwy 371 | $3,400,000 | 2026 | |
53 | MN371 | Thick overlay from Hwy 210 to North of Crow Wing County Road 13 | $12,100,000 | 2029 | |
42 | MN23 | Mill and overlay from County Road 53 to South end of bridge 48030 | $3,200,000 | 2022 | Selected prior to policy (in 2019-2022 STIP) |
40 | MN15 | Mill and overlay from Railroad crossing in Kimball to Hwy 55 | $100,000 | 2021 | Selected prior to policy (in 2019-2022 STIP) |
40 | MN371 | Mill and overlay from Hwy 10 to Morrison County Road 48 | $9,100,000 | 2030 | |
39 | MN65 | Diamond Grinding from Cambridge to Isanti County Road 30 | $800,000 | Not Selected | |
37 | US 10 | Mill and overlay from Becker County Road 40 to Railroad crossing in Saint Cloud | $10,200,000 | 2029 | |
37 | US 71 | Reclaim and overlay from North of Hwy 55 in Belgrade to bridge over I-94 | $5,900,000 | Not Selected | |
32 | US 169 | Unbonded overlay from Hwy 210 to North end of Mississippi River Bridge | $1,900,000 | 2022 | Selected prior to policy (in 2019-2022 STIP) |
20 | MN23 | Medium mill and overlay from Hwy 23B to 1.1 miles east of County Road 12 | $2,000,000 | 2022 | Part of D8 project in 2022 |