Non-National Highway System pavement projects
MnDOT District 2
How the projects scored in 2020
The construction costs shown on this list represent a very rough estimate based on limited information available at the time selection decisions were made. Actual construction and delivery costs will change over time as projects go from a concept through the project development process and are eventually constructed. View more detailed scores (Excel).
Last updated December 2020
Score | Route | Description | High-Level Cost Estimate for Planning Purposes | Year Planned (FY) | Comments |
---|---|---|---|---|---|
85 | MN 200 | Resurface Hwy 200 from Hwy 371 to Hwy 84 | $2,800,000 | 2021 | |
80 | MN 222 | Resurface Hwy 222 from Hwy 92 to Oklee | $500,000 | 2026 | |
79 | MN 32 | Resurface Hwy 32 from Red Lake Falls to St. Hilaire | $3,100,000 | 2029 | |
79 | US59 | Resurface Hwy 59 from Thief River Falls to Newfolden | $4,400,000 | Not selected | Distict does not expect pavement segments to deteriorate as fast as model predicts |
79 | MN 6 | Resurface Hwy 6 from 11th Ave in Deer River to 1.6 miles north of Itasca County Road 136 | $2,900,000 | 2025 | |
77 | MN 46 | Resurface Hwy 46 from just Itasca County Road 39 to Itasca County Road 13 | $9,900,000 | Not selected | Coordinating funding with another district |
76 | MN 72 | Resurface Hwy 72 from Blackduck to Hwy 1 | $2,100,000 | 2028 | |
76 | US75 | Resurface Hwy 75 from south Norman County line to Halstad | $4,200,000 | 2030 | |
76 | US75 | Resurface Hwy 75 from Climax to Crookston | $5,200,000 | Not selected | District does not expect pavement segments to deteriorate as fast as model predicts |
76 | MN 89 | Resurface Hwy 89 from Fourtown to Log Church Rd NW | $3,300,000 | 2024 | |
76 | MN 46 | Resurface Hwy 46 from Itasca County Road 13 to Hwy 1 | $3,600,000 | 2028 | |
75 | MN 1 | Resurface Hwy 1 from Northome to Hwy 6 | $6,000,000 | 2030 | |
75 | US75 | Resurface Hwy 75 from Shelly to Climax | $3,300,000 | 2030 | |
74 | MN 1 | Resurface Hwy 1 from Hwy 89 to east Clearwater County line | $4,900,000 | 2027 | |
74 | US59 | Resurface Hwy 59 from Newfolden to Karlstad | $4,500,000 | 2030 | |
74 | MN 72 | Resurface Hwy 72 from Hwy 1 to the Tamarac River | $5,500,000 | 2030 | |
74 | US75 | Resurface Hwy 75 from Stephan to Donaldson | $2,500,000 | Not selected | District does not expect pavement segments to deteriorate as fast as model predicts |
74 | MN 200 | Resurface Hwy 200 from Laporte to Hwy 371 | $2,600,000 | 2025 | |
73 | MN 92 | Resurface Hwy 92 from Hubbard County Road 35 to Hwy 200 | $1,400,000 | 2022 | |
72 | MN 1 | Resurface Hwy 1 from west Beltrami County line to Hwy 89 | $2,500,000 | 2029 | |
72 | MN 1 | Resurface Hwy 1 from busy corner to east Beltrami County line | $1,600,000 | 2029 | |
72 | MN 87 | Reconstruct Hwy 87 from Hwy 71 to Hubbard County Road 6 | $16,100,000 | 2025 | |
72 | MN 89 | Resurface Hwy 89 from Wannaska to Hwy 11 | $3,200,000 | 2027 | |
72 | MN 219 | Resurface Hwy 219 from Hwy 1 to jct with Hwy 89 | $3,700,000 | 2028 | |
72 | MN 220 | Resurface Hwy 220 from East Grand Forks to Alvarado | $4,000,000 | 2027 | |
72 | MN 6 | Resurface Hwy 6 from Hwy 286 to Hwy 1 | $2,200,000 | 2027 | |
71 | MN 9 | Resurface Hwy 9 from the north Norman County line to Crookston | $3,100,000 | Not selected | District does not expect pavement segments to deteriorate as fast as model predicts |
71 | MN 200 | Resurface Hwy 200 from the junctions of Hwy 32 | $600,000 | Not selected | Waiting to coordinate with another project |
71 | MN 200 | Resurface Hwy 200 from Clearwater County Road 2 to Hwy 71 | $1,500,000 | 2026 | |
70 | MN 1 | Resurface Hwy 1 from Hwy 89 to east Red Lake Nation boundary | $2,300,000 | 2023 | |
70 | MN 72 | Resurface Hwy 72 from Blackduck to 1-mile north | $300,000 | 2026 | Tied to another project |
70 | MN 89 | Resurface Hwy 89 from Hwy 219 to north Marshall County line | $3,600,000 | 2026 | |
70 | MN 89 | Resurface Hwy 89 from south Roseau County line to Wannaska | $1,900,000 | 2026 | |
69 | MN 11 | Resurface Hwy 11 from west Koochiching County line to Frontier | $4,100,000 | Not selected | Coordinating funding with another district |
69 | MN 11 | Resurface Hwy 11 from Frontier to Koochiching County Road 83 | $4,800,000 | Not selected | Coordinating funding with another district |
69 | MN 11 | Resurface Hwy 11 from Loman to Hwy 71 | $3,000,000 | Not selected | Coordinating funding with another district |
69 | MN 64 | Resurface Hwy 64 from south Hubbard County line to Hwy 87 | $1,600,000 | Not selected | District does not expect pavement segments to deteriorate as fast as model predicts |
69 | MN 89 | Resurface Hwy 89 from Hwy 1 to 5-miles to the north | $1,200,000 | 2027 | |
68 | MN 11 | Resurface Hwy 11 from Koochiching County Road 83 to Loman | $2,300,000 | Not selected | District does not expect pavement segments to deteriorate as fast as model predicts |
68 | MN 32 | Resurface Hwy 32 from Fertile to Hwy 2 | $3,500,000 | 2028 | |
68 | US75 | Resurface Hwy 75 from Euclid to Warren | $5,500,000 | Not selected | District does not expect pavement segment to deteriorate as fast as model predicts |
68 | MN 171 | Resurface Hwy 171 from North Dakota state border to Hwy 75 | $400,000 | 2022 | |
67 | MN 1 | Resurface Hwy 1 from east Beltrami County line to Hwy 71 | $1,000,000 | 2029 | |
67 | MN 11 | Resurface Hwy 11 from Baudette to west Koochiching County line | $2,300,000 | 2030 | |
67 | US75 | Resurface Hwy 75 from Hallock to Canadian Border | $3,800,000 | 2022 | |
67 | MN 175 | Resurface Hwy 175 from Hallock to Hwy 59 | $2,800,000 | Not selected | Not a district priority, will continue to monitor pavement performance |
66 | US75 | Resurface Hwy 75 from Donaldson to Hallock | $4,000,000 | 2027 | |
66 | MN 92 | Resurface Hwy 92 from Hwy 32 to Brooks | $4,900,000 | Not selected | District does not expect pavement segment to deteriorate as fast as model predicts |
65 | MN 89 | Resurface Hwy 89 from Grygla to Hwy 219 | $1,300,000 | 2028 | |
65 | MN 200 | Resurface Hwy 200 from west Clearwater County line to Hwy 92 | $2,200,000 | 2021 | |
63 | MN 1 | Resurface Hwy 1 from Hwy 71 to Hwy 46 | $200,000 | Not selected | Tied to a higher scoring pavement project |
63 | MN 92 | Resurface Hwy 92 from Bagley to Clearwater County Road 22 | $700,000 | 2026 | Tied to another paving project |
62 | MN 220 | Resurface Hwy 220 from Climax to Hwy 2 | $6,100,000 | Not selected | District does not expect pavement segment to deteriorate as fast as model predicts |
61 | MN 87 | Resurface Hwy 87 from the southern Hubbard County line to Hwy 64 | $200,000 | Not selected | Waiting to coordinate with another project |
60 | MN 32 | Resurface Hwy 59 from Hwy 2 to Red Lake Falls | $1,900,000 | 2028 | |
60 | MN 113 | Resurface Hwy 113 from west Hubbard County line to Hwy 71 | $200,000 | Not selected | Waiting to coordinate with another project |
59 | MN 87 | Resurface Hwy 87 from Hubbard County Road 13 to Hwy 64 | $1,700,000 | 2025 | |
58 | MN 1 | Resurface Hwy 1 from the North Dakota border to 3-miles east | $700,000 | 2025 | |
57 | MN 200 | Resurface Hwy 200 from Hwy 71 to Laporte | $1,700,000 | 2029 | |
56 | MN 1 | Resurface Hwy 1 from 3-miles east of Oslo to Warren | $4,700,000 | 2028 | |
55 | MN 1 | Resurface Hwy 1 from Hwy 219 to east Pennington County line | $2,400,000 | 2028 | |
53 | MN 89 | Resurface Hwy 89 from Beltrami County Road 26 to Red Lake Nation boundary | $3,600,000 | Not selected | |
50 | US59 | Resurface Hwy 59 from Lake Bronson to Hwy 175 | $1,300,000 | 2026 | Selected prior to policy (In 2019-2028 CHIP) |
48 | MN 32 | Resurface Hwy 32 from the south Norman County line to Hwy 200 | $1,700,000 | Not selected | |
38 | MN 9 | Resurface Hwy 9 from Ada to the north Norman County line | $2,400,000 | Not selected | |
38 | MN 72 | Resurface Hwy 72 from Lake of the Woods County Road 83 to Hwy 11 | $3,300,000 | Not selected | |
37 | MN 92 | Resurface Hwy 92 from Gonvick to Clearwater County Road 22 | $4,200,000 | 2026 | Selected prior to policy (In 2019-2028 CHIP) |
36 | US75 | Resurface Hwy 75 from Warren to Argyle | $1,600,000 | Not selected | |
35 | MN 89 | Resurface Hwy 89 from Hwy 11 to Canadian border | $2,200,000 | Not selected | |
34 | MN 6 | Resurface Hwy 6 from the Bigfork River Bridge to Hwy 6 | $1,700,000 | 2030 | |
33 | MN 92 | Resurface Hwy 92 from Trail to Gonvick | $2,200,000 | Not selected | |
30 | MN 1 | Resurface Hwy 1 from east Pennington County line to Hwy 89 | $1,600,000 | 2029 | |
30 | MN 220 | Resurface Hwy 220 from Hwy 1 to Hwy 11 | $7,300,000 | Not selected | |
29 | MN 223 | Resurface Hwy 223 from Hwy 92 to Clearwater County Road 10 | $1,700,000 | 2025 | Tied to a higher scoring pavement project |
27 | MN 317 | Resurface Hwy 317 from end of Red River Bridge to Jct Hwy 220 | $300,000 | Not selected | |
26 | MN 308 | Resurface Hwy 308 from Hwy 11 to Jct Hwy 89 | $200,000 | Not selected | |
25 | MN 200 | Resurface Hwy 200 from Hwy 92 to Long Lake Park | $1,300,000 | Not selected | |
21 | MN 32 | Resurface Hwy 32 from Hwy 200 to Fertile | $2,500,000 | Not selected | |
15 | MN 1 | Resurface Hwy 1 from north Pennington County line to Hwy 59 | $2,300,000 | Not selected | |
9 | MN 1 | Resurface Hwy 1 from Warren to south Marshall County line | $2,300,000 | Not selected | |
8 | MN 72 | Resurface Hwy 72 from the Tamarac River to 12-miles north of Waskish | $2,000,000 | Not selected | |
6 | MN 226 | Resurface Hwy 226 from Hwy 34 to Hubbard County Road 7 | $300,000 | Not selected |