National Highway System pavement projects
MnDOT District 2
How the projects scored in 2020
The construction costs shown on this list represent a very rough estimate based on limited information available at the time selection decisions were made. Actual construction and delivery costs will change over time as projects go from a concept through the project development process and are eventually constructed. View more detailed scores (Excel).
Last updated December 2020
Score | Route | Description | High Level Cost Estimate for Planning Purposes | Year Planned (FY) | Comments |
---|---|---|---|---|---|
84 | US 2 | Resurface eastbound lanes of Hwy 2 from East Grand Forks Fisher | $5,400,000 | 2028 | |
81 | US 2 | Resurface westbound lanes of Hwy 2 from Fosston to Bagley | $7,400,000 | 2028 | |
81 | US 71 | Resurface Hwy 71 from Beltrami County Road 22 to Hwy 72 | $3,100,000 | 2026 | |
78 | US 59 | Resurface Hwy 59 from Hwy 2 to Brooks | $2,800,000 | 2030 | |
75 | US 2 | Resurface westbound lanes of Hwy 2 from Hwy 59 to Fosston | $5,000,000 | 2027 | |
61 | MN 11 | Resurface Hwy 11 from Roseau to Hwy 313 | $6,100,000 | 2025 | |
74 | US 2 | Resurface westbound lanes of Hwy 2 from East Grand Forks to Fisher | $9,200,000 | 2021 | |
74 | US 59 | Resurface Hwy 59 from Brooks to Thief River Falls | $4,300,000 | 2023 | |
74 | US 71 | Resurface Hwy 71 from Beltrami County Road 15 to Beltrami County Road 22 | $1,900,000 | 2028 | |
73 | US 2 | Resurface westbound lanes of Hwy 2 from Fisher to Hwy 75 | $2,000,000 | 2021 | |
73 | US 2 | Resurface Hwy 2 from the south Beltrami County line to Midge Lake | $5,000,000 | Not selected | District does not expect pavement segments to deteriorate as fast as the model predicts |
73 | US 71 | Resurface Hwy 71 from Hwy 197 to Beltrami County Road 15 | $5,500,000 | 2022 | |
72 | MN 34 | Resurface Hwy 34 from the west Hubbard County line to Park Rapids | $1,100,000 | 2024 | |
72 | US 71 | Resurface Hwy 71 from Menahga to the north Wadena County line | $1,500,000 | Not selected | Coordinating funding with another district |
71 | US 2 | Resurface the eastbound lanes of Hwy 2 from Fosston to Bagley | $6,100,000 | 2028 | |
69 | US 2 | Resurface Hwy 2 from Wilton to Beltrami County Road 11 | $3,000,000 | 2028 | |
69 | US 2 | Resurface Hwy 2 from Cass Lake to Cass County Road 10 | $1,000,000 | 2021 | |
69 | MN 11 | Resurface Hwy 11 from Warroad to east Roseau County line | $2,900,000 | 2027 | |
69 | MN 371 | Resurface Hwy 371 from th Steamboat River Bridge to Cass Lake | $2,100,000 | 2030 | |
66 | US 2 | Resurface eastbound lanes of Hwy 2 from Hwy 9 to Hwy 32 | $5,800,000 | 2022 | |
66 | US 2 | Resurface Hwy 2 from the Mississippi River Bridge to Itasca County Road 18 | $500,000 | 2021 | |
66 | MN 11 | Resurface Hwy 11 from Karlstad to east Kittson County line | $2,200,000 | Not selected | Not a district priority, will continue to monitor pavement performance |
66 | MN 34 | Resurface Hwy 34 from Akeley to the west Cass County line | $1,200,000 | Not selected | Waiting to coordinate with another project |
66 | US 71 | Resurface Hwy 71 from the north Itasca County line to the north junction of Hwy 1 | $1,800,000 | Not selected | Coordinating funding with another district |
65 | MN 11 | Resurface Hwy 11 from the North Dakota border to 1-mile to the east | $300,000 | Not selected | Waiting to coordinate with another project |
67 | US 2 | Resurface Hwy 2 from Cass Lake to Hubbard County Road 25 | $2,400,000 | 2025 | Majority of this project is in District 3 |
58 | MN 11 | Resurface Hwy 11 from Williams to Lake of the Woods County Road 66 | $2,400,000 | Not selected | Not a district priority, will continue to monitor pavement performance |
57 | US 59 | Resurface Hwy 59 from Winger to Hwy 2 | $1,500,000 | 2021 | |
53 | MN 32 | Resurface Hwy 32 from Middle River to Hwy 11 | $5,200,000 | 2024 | |
53 | MN 34 | Resurface Hwy 34 from the west Cass County line to Hwy 371 | $2,700,000 | Not selected | Coordinating funding with another district |
41 | US 2 | Reconstruct eastbound lanes of Hwy 2 from Hwy 32 to Erskine | $48,700,000 | 2021 | |
36 | US 2 | Reconstruct eastbound lanes of Hwy 2 from Hwy 59 to Fosston | $28,300,000 | 2022 | |
28 | US 71 | Resurface Hwy 71 from Lake George to Hwy 71 | $1,700,000 | 2030 | RQI forecast doesn't reflect on the ground conditions |
18 | US 2 | Resurface the eastbound lanes of Hwy 2 from Fisher to Crookston | $6,400,000 | 2030 | RQI forecast doesn't reflect on the ground conditions |
11 | US 71 | Resurface Hwy 71 from the north Wadena County line to Park Rapids | $1,300,000 | Not selected |