The construction costs shown on this list represent a very rough estimate based on limited information available at the time selection decisions were made. Actual construction and delivery costs will change over time as projects go from a concept through the project development process and are eventually constructed. View more detailed scores (Excel).
Last updated December 2019
Score | Community | Route | Description | High-Level Cost Estimate for Planning Purposes | Year Planned (FY) | Comments |
---|---|---|---|---|---|---|
90 | Saint Paul | US952A | Medium mill and overlay from Wyoming St to I-35E | $18,000,000 | 2022 | |
87 | Oakdale / Maplewood | MN120 | Reclaim and overlay from 4th St in Oakdale to Highway 244 | $4,400,000 | 2024 | |
75 | Saint Paul | MN51 | Medium mill and overlay from Dayton Ave to Como Ave | $2,100,000 | Not Selected | Waiting to coordinate with transit |
73 | Minneapolis | US952A | Medium mill and overlay from I-35W to University Ave | $600,000 | 2027 | |
70 | Saint Paul | MN51 | Medium mill and overlay from St. Clair to Grand Ave | $300,000 | 2024 | |
70 | Columbia Heights | MN65 | Medium mill and overlay from 37th Ave to 53rd Ave NE | $1,900,000 | 2027 | |
67 | Saint Paul | US61 | Medium mill and overlay from Highway 5 to Roselawn Ave | $2,400,000 | 2023 | |
67 | Saint Paul | MN5 | Thin mill and overlay from Munster Ave to Highway 61 | $3,500,000 | 2024 | |
66 | Anoka | MN47 | Thin mill and overlay from Highway 10 to Industry Ave NW | $800,000 | 2021 | |
66 | Minneapolis | MN65 | Medium mill and overlay from 3rd Ave S to NE 27th Ave | $2,700,000 | 2027 | |
65 | Saint Paul | MN5 | Medium mill and overlay from Highway 61 to Highway 129 | $3,400,000 | 2022 | |
65 | Saint Paul | MN51 | Thin mill and overlay from Highway 5/West 7th St to Dayton Ave | $1,900,000 | 2029 | |
65 | Waconia | MN5 | Thin mill and overlay from Oak Ave to Birch St | $1,000,000 | Not Selected | |
65 | West Saint Paul | US952A | Medium mill and overlay from Old Highway 110 to Wyoming St | $3,000,000 | Not Selected | |
60 | Mahtomedi | MN244 | Nova Chip from Washington County Road 12 to Highway 96 | $1,100,000 | 2025 | Selected prior to policy (in 2019-2028 CHIP) |
60 | Saint Paul | MN5 | Medium mill and overlay from Ramsey/Hennepin County Line to Highway 52 | $700,000 | Not Selected | |
58 | Saint Paul | US61 | Thin mill and overlay from Mounds Blvd to Highway 5 | $600,000 | 2021 | Selected prior to policy (in 2019-2022 STIP) |
58 | Saint Paul | MN156 | Thin mill and overlay from Dakota/Ramsey County Line | $200,000 | 2021 | Selected prior to policy (in 2019-2022 STIP) |
56 | South Saint Paul | MN156 | Major Concrete Rehabilitation from I-494 to Dakota/Ramsey County Line | $4,300,000 | 2021 | Selected prior to policy (in 2019-2022 STIP) |
50 | Rosemount | MN3 | Thin mill and overlay from Dakota County Road 58 to 145th St | $800,000 | Not Selected | |
47 | Taylors Falls | MN95 | Thin mill and overlay from Chisago County Road 16 to Highway 8 | $200,000 | Not Selected | |
44 | Jordan | MN282 | Thin mill and overlay from Jordan to Highway 21 | $400,000 | Not Selected | |
39 | Jordan | MN21 | Thin mill and overlay from Mill St to Highway 169 | $300,000 | 2027 | Coordinated with larger pavement project |
33 | Belle Plaine | MN25 | Thin mill and overlay from Highway 169 to Scott County Line | $700,000 | 2027 | Coordinated with larger pavement project |
26 | Waconia | MN284 | Thin mill and overlay from Elm Creek Rd to Highway 5 | $400,000 | Not Selected | |
25 | White Bear Lake | US61 | Medium mill and overlay from White Bear Ave to Highway 96 | $700,000 | Not Selected | Preventive maintenance scheduled in 2020 to extend surface life |
22 | Minneapolis | MN65 | Thin mill and overlay from 27th Ave to 37th Ave | $900,000 | Not Selected | |
12 | New Prague | MN21 | Minor concrete repair from Scott/Le Sueur County line to 7th St | $100,000 | Not Selected |