Urban non-freeway/non-expressway pavement projects
MnDOT District 7
How the projects scored in 2019
The construction costs shown on this list represent a very rough estimate based on limited information available at the time selection decisions were made. Actual construction and delivery costs will change over time as projects go from a concept through the project development process and are eventually constructed. View more detailed scores (Excel).
Last updated December 2019
Score | Community | Route | Description | High-Level Cost Estimate for Planning Purposes | Year Planned (FY) | Comments |
---|---|---|---|---|---|---|
85 | Lakefield | MN86 | Medium mill and overlay from 5th Ave S to Funk Ave | $6,100,000 | Not Selected | Waiting to coordinate with a rural pavement project on Highway 86 |
82 | Jackson | US71 | Medium mill and overlay from the Des Moines River Trail crossing to Springfield Parkway | $4,500,000 | 2028 | Part of larger Highway 71 project |
80 | Worthington | US59 | Reconstruction from 1st Ave to I-90 | $13,000,000 | 2027 | |
80 | Nicollet | MN99 | Medium mill and overlay from Heideman Ave to Birch St | $6,300,000 | Not Selected | Waiting to coordinate with another project. |
79 | Waseca | MN13 | Medium mill and overlay from south of 4th Ave NE to northern Waseca city limits | $900,000 | Not Selected | Waiting to coordinate with another project. |
78 | Gaylord | MN19 | Medium overlay from Spring St to northeast of Spring St | $3,900,000 | Not Selected | Better suited to be included in surrounding Highway 19 project |
76 | Ceylon | MN263 | Reclaim and overlay from Clark St to Railroad St | $5,300,000 | 2021 | Part of larger Highway 263 project. |
76 | Elmore | US169 | Medium overlay from Jay St to Polton St | $3,500,000 | 2023 | |
76 | Kiester | MN22 | Medium mill and overlay from Front St to Center St | $5,100,000 | 2027 | Part of larger Highway 22 project |
75 | Windom | MN60 | Major pavement rehabilitation from 6th St to the east Highway 71 intesection | $8,400,000 | 2020 | |
75 | Henderson | MN93 | Medium mill and overlay from Elm St to Highway 19 | $2,000,000 | Not Selected | Waiting to coordinate with another project. |
75 | Mankato | MN22 | Reconstruction from Bassett Dr to north of Bassett Dr | $17,000,000 | Not Selected | Waiting to coordinate with a larger pavement project on Highway 22 in Mankato |
72 | Minnesota Lake | MN22 | Medium overlay from 4th Ave to Main St | $6,600,000 | 2023 | Part of larger Highway 22 project between Mapleton and Wells. |
71 | Amboy | MN30 | Medium overlay from Stevens St to 4th Ave | $500,000 | Not Selected | |
71 | Round Lake | MN264 | Reclaim and overlay from 2nd Ave to the north end of Main St | $5,600,000 | Not Selected | Potential turnback candidate that will take coordination with local partners |
70 | Waseca | MN13 | Medium mill and overlay from 5th St SE to the railroad crossing | $1,300,000 | Not Selected | |
69 | Luverne | US75 | Medium mill and overlay from I-90 to James St | $1,400,000 | 2025 | Included as part of larger Highway 75 project in Rock County. Selected prior to policy (in 2019-2028 CHIP) |
68 | Darfur | MN30 | Medium overlay from 2nd St through 1st St | $4,900,000 | Not Selected | |
67 | Gaylord | MN5 | Reconstruction from east of 1st St to the Division St intersection | $3,700,000 | Not Selected | |
66 | Sherburn | MN4 | Medium mill and overlay from Front St to 5th St | $6,300,000 | 2022 | Part of larger Highway 4 project. Selected prior to policy (in 2019-2022 STIP) |
66 | Le Center | MN99 | Medium mill and overlay from Maple Ave to Cordova Ave | $8,900,000 | 2027 | Part of larger Highway 99 project. May become a separate urban project if substantial local needs are identified |
66 | Ellsworth | MN91 | Medium mill and overlay from 7th Ave to North Ave | $400,000 | Not Selected | |
65 | Winnebago | MN109 | Medium mill and overlay from Highway 169 to 4th St | $200,000 | Not Selected | |
64 | Springfield | US14 | Medium mill and overlay from Mary Ave to Washington Ave | $2,900,000 | 2022 | Selected prior to policy (in 2019-2022 STIP) |
63 | Wells | MN22 | Medium mill and overlay from 9th St SW to the railroad crossing | $400,000 | 2025 | Included as part of of larger Highway 22 adjacent project to south. Selected prior to policy (in 2019-2028 CHIP) |
63 | New Prague | MN19 | Medium mill and overlay from 7th Ave SE to Alton Ave roundabout | $400,000 | 2029 | Part of larger Highway 19 project east of Highway 169. Selected prior to policy (in 2019-2028 CHIP) |
63 | Arlington | MN5 | Medium mill and overlay from Baker St to Sheila Dr/2nd Ave NW intersection | $4,200,000 | Not Selected | |
61 | Mankato | US169 | Medium mill and overlay from Webster Ave to Highway 14 | $2,800,000 | 2027 | Corridor study to be completed before any long-term improvements made |
60 | Trimont | MN4 | Medium overlay from Chestnut St to Beech St | $6,100,000 | 2022 | Selected prior to policy (in 2019-2022 STIP) |
60 | New Prague | MN19 | Medium mill and overlay from 6th Ave NW to 4th Ave SE | $200,000 | 2029 | Part of larger Highway 19 project east of Highway 169. Selected prior to policy (in 2019-2028 CHIP) |
60 | Gaylord | MN22 | Medium mill and overlay from Southview Dr to Commercial Ave | $100,000 | Not Selected | |
59 | New Ulm | MN15 | Thin mill and overlay from 20th S St to Center St | $1,600,000 | Not Selected | |
58 | Blue Earth | US169 | Medium mill and overlay from 10th St to north side of Leland Parkway roundabout | $700,000 | Not Selected | |
57 | Madison Lake | MN60 | Reconstruction from 7th St to 1st St | $2,000,000 | 2021 | Selected prior to policy (in 2019-2022 STIP) |
57 | Montgomery | MN13 | Medium mill and overlay from Milwaukee Ave to north of Welco Dr | $700,000 | Not Selected | |
56 | Gaylord | MN22 | Medium mill and overlay from High Ave to Linden Ave | $400,000 | Not Selected | |
56 | Waseca | MN13 | Medium mill and overlay from the railroad crossing to south of 4th Ave NE | $200,000 | Not Selected | |
55 | New Richland | MN30 | Medium mill and overlay from Elm Ave to Highway 13 | $5,400,000 | Not Selected | |
54 | New Ulm | US14 | Medium mill and overlay from Garden St to 7th St N | $1,500,000 | Not Selected | |
53 | Winthrop | MN19 | Pavement rehabilitation from Brown St to Pleasant Ave | $2,800,000 | 2020 | Short-term fix to be used until funding for a long-term fix can be identified |
52 | Henderson | MN19 | Medium mill and overlay from Fort Road to trail on the west side of the levee | $300,000 | 2025 | Part of larger Highway 19 project. Selected prior to policy (in 2019-2028 CHIP) |
51 | Windom | MN62 | Medium mill and overlay from Plum Ave to Highway 60 | $400,000 | Not Selected | |
49 | St Peter | MN22 | Medium mill and overlay from 3rd St through N Sunrise Dr | $500,000 | 2024 | Part of larger Highway 22 project. Potential turnback. |
49 | New Auburn | MN22 | Medium overlay from 1st St to 5th St | $5,300,000 | Not Selected | |
48 | Worthington | MN60 | Minor concrete rehabilitation from Nobles St to north of the I-90 roundabout | $2,000,000 | Not Selected | |
47 | Truman | MN15 | Medium overlay from 2nd St S to 2nd St N | $11,000,000 | Not Selected | |
47 | Mapleton | MN30 | Medium mill and overlay from 3rd Ave SW to MN 22 | $500,000 | Not Selected | |
47 | Vernon Center | US169 | Major concrete rehabilitation from Kendall St to 1st St | $8,700,000 | Not Selected | |
46 | St Peter | US169 | Medium mill and overlay from Chestnut St to Ramsey St | $5,300,000 | 2022 | Short-term fix to be used until funding for a long-term fix can be identified |
46 | Sleepy Eye | MN4 | Major concrete rehabilitation from Ellsworth St in Sleepy Eye to 65' north of Allison Parkway NW | $1,300,000 | 2027 | Coordinating with another MnDOT project; Selected prior to policy (in 2019-2028 CHIP) |
45 | New Prague | MN13 | Thick overlay from 5th St SW to Highway 19 | $5,500,000 | Not Selected | |
43 | Gibbon | MN19 | Major concrete rehabilitation from Ash Ave to Ely Ave | $6,500,000 | Not Selected | |
42 | Wells | MN109 | Medium mill and overlay from 6th Ave to Highway 22 | $300,000 | 2025 | Coordinating with another MnDOT project. |
40 | Lake Crystal | MN60 | Concrete pavement replacement from Lilly St to Laclaire St | $17,000,000 | 2024 | Coordinating with another MnDOT project; Selected prior to policy (in 2019-2028 CHIP) |
36 | St Peter | US169 | Reconstruction from Minnesota Ave frontage road to Jefferson Ave | $500,000 | 2023 | Coordinating with another MnDOT project; Selected prior to policy (in 2019-2028 CHIP) |
35 | Courtland | US14 | Thin mill and overlay from Red Shoe Dr to Fiemeyer Dr | $3,000,000 | 2021 | Coordinating with another MnDOT project; Selected prior to policy (in 2019-2022 STIP) |
33 | Adrian | MN91 | Major concrete rehabilitation from 4th St to the railroad crossing | $200,000 | 2020 | Coordinating with another MnDOT project; Selected prior to policy (in 2019-2022 STIP) |
33 | Adrian | MN91 | Medium mill and overlay from the railroad crossing to Pearl St | $200,000 | 2020 | Coordinating with another MnDOT project; Selected prior to policy (in 2019-2022 STIP) |
31 | St Peter | US169 | Minor concrete rehabilitation from Jefferson Ave to north of Chestnut St | $400,000 | Not Selected | |
31 | Le Sueur | MN93 | Minor concrete rehabilitation from Main St to west end of the Minnesota River bridge | $100,000 | Not Selected | |
30 | Mankato | MN22 | Reconstruction from Adams St roundabout to the southern intersection of Highway 14 | $4,800,000 | Not Selected | Was in 2019-2028 CHIP, but removed in preparation for a larger Highway 22 project in Mankato |
28 | St James | MN4 | Minor concrete rehabilitation from 9th Ave S to 11th Ave N | $200,000 | Not Selected | |
25 | Mankato | MN22 | Minor concrete rehabilitation from Bassett Dr through the Adams St roundabout | $200,000 | Not Selected | |
21 | Worthington | US59 | Reconstruction from 1st Ave to 440 feet to the east | $100,000 | 2027 | Coordinating with another MnDOT project; Selected prior to policy (in 2019-2028 CHIP) |
20 | Gaylord | MN5/MN22/MN19 | Minor concrete rehabilitation in downtown Gaylord | $200,000 | Not Selected | |
9 | St Peter | MN99 | Minor concrete rehabilitation from Front St to the west end of the Minnesota River Bridge | $100,000 | Not Selected |