Urban non-freeway/non-expressway pavement projects
MnDOT District 6
How the projects scored in 2019
The construction costs shown on this list represent a very rough estimate based on limited information available at the time selection decisions were made. Actual construction and delivery costs will change over time as projects go from a concept through the project development process and are eventually constructed. View more detailed scores (Excel).
Last updated December 2019
Score | Community | Route | Description | High-Level Cost Estimate for Planning Purposes | Year Planned (FY) | Comments |
---|---|---|---|---|---|---|
87 | Northfield | MN246 | Potential pavement project in Northfield | $5,700,000 | Not selected | Additional coordination needed to better understand local needs and timeline. |
86 | Stewartville | US63 | Future pavement project from south of 6th St SE to the Root River | $500,000 | Not selected | Additional coordination needed to better understand local needs and timeline. |
84 | Winona | MN43 | Resurfacing from Sarnia St to end of Mississippi River bridge | $3,200,000 | 2025 | |
83 | Mantorville | MN57 | reconstruction from Zumbro River bridge to 9th St in Mantorville | $3,100,000 | 2023 | |
83 | Albert Lea | US65/MN13 | Future pavement project from S Shore Drive to Main St to Euclid Ave | $24,000,000 | Not selected | Additional coordination needed to better understand local needs and timeline. |
82 | Spring Valley | MN16 | Reconstruction from Tracy Road to Griswald St | 2026 | ||
82 | Plainview | MN247 | Future pavement project from 10th St to Highway 42 | $400,000 | Not selected | Additional coordination needed to better understand local needs and timeline. |
81 | Lanesboro | MN250 | Future pavement project from Highway 16 to the Root River | $3,600,000 | Not selected | Additional coordination needed to better understand local needs and timeline. |
79 | Northfield - Carleton | MN19 | Future pavement project of Highway 19 from Highway 3 to eastern city limits in Northfield | $1,000,000 | Not selected | Additional coordination needed to better understand local needs and timeline. |
77 | Houston | MN16 | Reconstruction through Houston | $6,000,000 | 2024 | |
77 | Dundas/Northfield | MN3 | Future pavement project from Rice County Road 20 to the Cannon River | $2,600,000 | Not selected | Additional coordination needed to better understand local needs and timeline. |
77 | Austin | MN105 | Future pavement from Turtle Creek to I-90 | $1,000,000 | Not selected | Additional coordination needed to better understand local needs and timeline. |
77 | Red Wing | US61 | Future pavement project from Old Main St to Bench St | $1,000,000 | Not selected | Additional coordination needed to better understand local needs and timeline. |
75 | Cannon Falls | MN19 | Future pavement project from Highway 52 to Highway 20 | $400,000 | Not selected | Additional coordination needed to better understand local needs and timeline. |
75 | Albert Lea | US69 | Future pavement project from 9th St to Highway 13 | $600,000 | Not selected | Additional coordination needed to better understand local needs and timeline. |
73 | Blooming Prairie | US218 | Reconstruction from 3rd St NE to Highway 30 on the north side of town | $6,000,000 | 2023 | |
71 | Altura | MN248 | Future pavement project from 1st Ave SE to 3rd Ave NE | $200,000 | Not selected | |
69 | Faribault | MN298 | Future pavement project in Faribault | $300,000 | Not selected | |
69 | Brownsdale | MN56 | Future pavement project from 260th St to 2 blocks north of Lathan St | $400,000 | Not selected | |
67 | La Crescent | US61/MN16 | Future pavement project from S 14th St to N 4th St | $1,200,000 | Not selected | |
67 | Lake City | US63 | Future pavement project from Orchard Lane to Highway 61 | $6,900,000 | Not selected | |
66 | Harmony | MN139 | Future pavement project from 9th St SW to Highway 52 | $500,000 | Not selected | |
66 | Hokah | MN44 | Future pavement project from 6th St to Highway 16 | $600,000 | Not selected | |
65 | Red Wing | MN58 | Medium mill and overlay from 21st St to US 61 in Red Wing | $1,800,000 | 2021 | Selected in 2021 due to pavement condition. A future reconstruction project is being planned which will include ADA improvements and local utility needs. |
65 | Le Roy | MN56 | Reconstruction from east city line to 0.4 miles north of 770th Ave | $8,700,000 | 2023 | Selected in 2023 to match year of available city funding. |
65 | Northfield | MN3 | Future pavement project from the Cannon River to the railroad bridge north of St Olaf Ave | $400,000 | Not selected | |
64 | Faribault | MN3 | Future pavement project from Highway 21 to north of 2nd Ave NW intersection | $600,000 | Not selected | |
64 | Faribault - Riverside | MN60 | Future pavement project from Central Ave to the Straight River bridge | $400,000 | Not selected | |
62 | Rochester | US14 | Medium mill and overlay from Highway 52 to Olmsted County Road 36 | $3,500,000 | 2023 | Project selected due to pavement wearing down faster than expected, plus there are necessary signal, bicycle, and pedestrian upgrades needed here. |
62 | Nerstrand | MN246 | Future pavement project from Poplar St to Lamb Ave | $300,000 | Not selected | |
60 | Cannon Falls | MN19 | Medium mill and overlay from Highway 20 to Almond St in Cannon Falls | $2,000,000 | 2022 | Selected in 2022 due to pavement condition and needed ADA improvements. |
60 | Elgin | MN42 | Future pavement project from the Whitewater River to Dry Creek | $300,000 | Not selected | |
59 | Wabasha | MN60 | Future pavement project from Highway 61 to the Mississippi River bridge | $700,000 | Not selected | |
56 | Kenyon | MN56 | Future pavement project including Home St to Highway 60 and Highway 60 to Trondheim Road | $300,000 | Not selected | |
54 | West Concord | MN56 | Resurfacing from Southview St to Dodge County Road 24 | $1,000,000 | 2023 | Selected prior to policy (in 2019-2028 CHIP) |
54 | Faribault | MN299 | Future pavement project in Faribault | $400,000 | Not selected | |
52 | Spring Grove | MN44 | Future pavement project from 3rd Ave NW to 4th Ave SE | $400,000 | Not selected | |
45 | Caledonia | MN44 | Medium mill and overlay in Caledonia | $500,000 | 2024 | Coordinated with a larger pavement project |
44 | Adams | MN56 | Future pavement project from 1st St to 5th St | $200,000 | Not selected | |
44 | Albert Lea | MN13 | Future pavement project from Euclid Ave to the Skyline Plaza entrance | $400,000 | Not selected | |
38 | Spring Valley | US63 | Future pavement project from Fillmore County Road 12 to Highway 16 | $300,000 | Not selected | |
36 | Red Wing | US61 | Future pavement project from Potter St to Old Main St | $300,000 | Not selected |