Urban non-freeway/non-expressway pavement projects
MnDOT District 4
How the projects scored in 2019
The construction costs shown on this list represent a very rough estimate based on limited information available at the time selection decisions were made. Actual construction and delivery costs will change over time as projects go from a concept through the project development process and are eventually constructed. View more detailed scores (Excel).
Last updated December 2019
Score | Community | Route | Description | High level construction cost estimate for planning purposes | Year Planned (FY) | Comments |
---|---|---|---|---|---|---|
82 | Henning | MN108 | Reconstruction in Henning | $4,600,000 | 2024 | |
79 | Moorhead | US10/US75 | Reconstruction in Moorhead | $25,000,000 | 2025 | |
78 | Alexandria | MN29 | Reconstruction in Alexandria | $34,000,000 | 2029 | |
76 | Osage | MN34 | Reclaim and overlay in Osage | $400,000 | 2024 | |
76 | Fergus Falls | MN210 | Reconstruction in Fergus falls | $5,700,000 | 2029 | |
75 | Frazee | MN87 | Reconstruction in Frazee | $8,500,000 | 2022 | |
75 | Appleton | MN7/MN119 | Reconstruction in Appleton | $18,000,000 | Not selected | District anticipates the pavement condition will not deteriorate as fast as the model is projecting |
73 | Breckenridge | US75 | Reconstruction in Breckenridge | $14,000,000 | Not selected | District anticipates the pavement condition will not deteriorate as fast as the model is projecting |
73 | Alexandria | MN29 | Medium mill and overlay in Alexandria | $1,500,000 | Not selected | District anticipates the pavement condition will not deteriorate as fast as the model is projecting |
72 | Dilworth | US10 | Reconstruction in Dilworth | $30,000,000 | 2027 | |
72 | Fergus Falls | MN210 | Reconstruction in Fergus Falls | $14,000,000 | 2029 | |
71 | Ottertail | MN78 | Reclaim and overlay in Ottertail | $300,000 | Not selected | District anticipates the pavement condition will not deteriorate as fast as the model is projecting |
69 | Pelican Rapids | US59/MN108 | Reconstruction in Pelican Rapids | $10,000,000 | 2024 | Selected prior to policy (in 2020-2028 CHIP) |
68 | Detroit Lakes | MN34 | Reconstruction in Detroit Lakes | $10,500,000 | Not selected | |
66 | Browns Valley | MN28 | Thin mill and overlay in Browns Valley | $400,000 | 2027 | Selected prior to policy (in 2020-2028 CHIP) |
66 | Benson | US12/MN9/MN29 | Overlay in Benson | $31,000,000 | Not selected | |
64 | Wadena | MN29 | Medium mill and overlay in Wadena | $300,000 | 2026 | Selected prior to policy (in 2020-2028 CHIP) |
63 | Wendell | MN55 | Reclaim and overlay in Wendell | $700,000 | Not selected | |
61 | Cyrus | MN28 | Reconstruction in Cyrus | $2,700,000 | 2024 | Selected prior to policy (in 2020-2028 CHIP) |
59 | Alexandria | MN29 | Major concrete repair in Alexandria | $1,800,000 | 2029 | Selected prior to policy (in 2020-2028 CHIP) |
58 | Ottertail | MN108 | Medium mill and overlay in Ottertail | $200,000 | 2024 | Selected prior to policy (in 2020-2028 CHIP) |
58 | Beardsley | MN28 | Thin mill and overlay in Beardsley | $300,000 | 2027 | Selected prior to policy (in 2020-2028 CHIP) |
58 | Battle Lake | MN78 | Reclaim and overlay in Battle lake | $500,000 | Not selected | |
55 | Alexandria | MN29 | Reconstruction in Alexandria | $9,100,000 | 2028 | Selected prior to policy (in 2020-2028 CHIP) |
55 | Glyndon | US10 | Reconstruction in Glyndon | $11,000,000 | Not selected | |
49 | Elizabeth | US59 | Thick mill and overlay in Elizabeth | $700,000 | 2026 | Coordinated with an adjacent NHS pavement project |
46 | Barrett | MN55 | Reconstruction in Barrett | $3,000,000 | Not selected | |
45 | Erhard | US59 | Thick mill and overlay in Erhard | $1,000,000 | 2026 | Coordinated with an adjacent NHS pavement project |
44 | Starbuck | MN28/MN29/MN114 | Reconstruction in multiple locations in Starbuck | $7,000,000 | 2020 | Selected prior to policy (in 2019-2022 STIP) |
42 | Hoffman | MN27 | Thin mill and overlay in Hoffman | $300,000 | Not selected | |
41 | Ortonville | US12/MN7 | Thin mill and overlay in Ortonville | $1,300,000 | Not selected | |
41 | Correll | MN7 | Thin mill and overlay in Correll | $300,000 | Not selected | |
38 | Detroit Lakes | US10 | Reconstruction in Detroit Lakes | $33,000,000 | Not selected |