Urban non-freeway/non-expressway pavement projects
MnDOT District 3
How the projects scored in 2019
The construction costs shown on this list represent a very rough estimate based on limited information available at the time selection decisions were made. Actual construction and delivery costs will change over time as projects go from a concept through the project development process and are eventually constructed. View more detailed scores (Excel).
Last updated December 2019
Score | Community | Route | Description | High level construction cost estimate for planning purposes | Year Planned (FY) | Comments |
---|---|---|---|---|---|---|
84 | Wadena | US71 | Reconstruction from Franklin Ave to Elm Ave | $3,500,000 | 2025 | |
79 | Sauk Centre | US71 | Reconstruction from I-94 to 4th St | $16,000,000 | 2025 | |
75 | Buffalo | MN25 | Reconstruction from Bradshaw Ave to 1st St | $6,200,000 | 2023 | |
75 | Elk River | US10 | Medium mill and overlay from Norfolk to Main St | $400,000 | Not selected | Only westbound segment is considered in poor condition, waiting to program with eastbound section |
67 | Mora | MN65 | Reconstruction from 0.8 miles north of Hwy 23 to 0.4 miles north of Hwy 23 | $6,800,000 | 2028 | |
66 | Long Prairie | US71 | Reconstruction from Long Prairie River Bridge to Todd County Road 56 | $5,900,000 | Not selected | Not a current district priority, but will continue to monitor pavement performance |
65 | St. Cloud | MN23 | Medium mill and overlay from Highway 15 to Railroad Bridge near Highway 10 | $5,800,000 | 2028 | |
65 | Brainerd | MN210 | Thin mill and overlay from Baxter to 3rd St NW | $2,500,000 | 2025 | |
65 | Pine River | MN84 | Reconstruction from Highway 371 to Pine River Bridge | $4,600,000 | Not selected | Not a current district priority, but will continue to monitor pavement performance |
60 | Cambridge | MN95 | Reconstruction from Fern St to Davis St | $8,600,000 | 2024 | Selected prior to policy (in 2019-2028 CHIP) |
60 | Monticello | MN25 | Medium mill and overlay from Monticello to I-94 | $800,000 | 2029 | Coordinated with a larger pavement project on Highway 25 |
48 | Eden Valley | MN22 | Reconstruction from Meeker/Stearns County line to Hutchenson Ave | $3,200,000 | Not selected | |
43 | Genola | MN25 | Thin mill and overlay from Highway 27 to 4th Ave N | $400,000 | 2025 | Selected prior to policy (in 2019-2028 CHIP) |
35 | Little Falls | MN27 | Thin mill and overlay from 127th Ave to 9th St | $1,100,000 | Not selected | |
34 | Milaca | MN23 | Reconstruction from South end of Bridge 48030 to 0.1 mile east of 48030 | $5,500,000 | 2025 | Selected prior to policy (in 2019-2028 CHIP) |
30 | Albany | MN238 | Minor concrete pavement rehabilitation from Railroad Ave to Stearns County Road 54 | $200,000 | Not selected | |
27 | Remer | MN6 | Thin mill and overlay from East Junction of Highway 200 to West Junction Highway 200 | $500,000 | Not selected | |
16 | Ironton | MN210 | Thin mill and overlay from 6th Ave to East end of hospital parking lot | $1,100,000 | Not selected | |
15 | Waukon | MN27 | Reconstruction from 85th Ave to Hennepin Ave | $1,200,000 | 2024 | Selected prior to policy (in 2019-2028 CHIP) |