Non-National Highway System pavement projects
MnDOT District 1
How the projects scored in 2019
The construction costs shown on this list represent a very rough estimate based on limited information available at the time selection decisions were made. Actual construction and delivery costs will change over time as projects go from a concept through the project development process and are eventually constructed. View more detailed scores (Excel).
Last updated December 2019
Score | Route | Description | High level construction cost estimate for planning purposes | Year Planned (FY) | Comments |
---|---|---|---|---|---|
92 | MN23 | Reclaim and overlay from St Louis Bridge to Highway 39 | $2,200,000 | 2023 | |
91 | US2 | Major concrete rehabilitation from reference point 260 to I-35 | $800,000 | Not Selected | District anticipates the pavement condition will not deteriorate as fast as the model is projecting |
90 | MN73 | Full mill and replace from Moose Horn River to Highway 27 | $400,000 | Not Selected | Not a current district priority, but will continue to monitor pavement performance |
89 | MN37 | Medium mill and overlay from Highway 53 to 135 | $2,800,000 | 2020 | |
87 | US2 /MN6 | Medium mill and overlay in multiple locations in Itasca county | $1,700,000 | 2020 | |
83 | MN1 | Medium mill and overlay from Highway 169 to Cedar St | $2,800,000 | 2023 | |
83 | MN1/US169 | Medium mill and overlay in multiple locations in St. Louis County | $1,100,000 | Not Selected | Not a current district priority, but will continue to monitor pavement performance |
82 | MN48 | Medium mill and overlay from east of I-35 to Pine County Highway 21 | $6,000,000 | 2029 | |
81 | MN27 | Medium mill and overlay from Highway 65 to Kenwood ave | $5,400,000 | 2022 | |
81 | MN73 | Full mill and replace from I-35 to Moose Horn Rver | $1,300,000 | Not Selected | Not a current district priority, but will continue to monitor pavement performance |
80 | MN169 | Medium mill and overlay from Highway 53 to Reference Point 381 | $4,700,000 | 2020 | |
79 | MN135 | Reconstruction from railroad crossing to St. Louis County Road 4 | $10,000,000 | 2020 | |
79 | MN11 | Medium mill and overlay from Highway 53 to Highway 332 | $400,000 | Not Selected | Not a current district priority, but will continue to monitor pavement performance |
78 | MN23 | Medium mill and overlay from Pine/Carlton County Line to St Louis River Br | $10,500,000 | 2023 | |
78 | MN169 | Medium mill and overlay from Pike River to junction with Highway 1 | $2,000,000 | 2024 | |
78 | MN46 | Reclaim and overlay from Itasca County Highway 13 to Koochiching County Highway 40 | $7,800,000 | 2025 | |
78 | MN46 | Reclaim and overlay from Itasca County Highway 39 to Itasca County Highway 13 | $28,000,000 | 2028 | |
78 | MN38 | Medium mill and overlay from 17th St to Itasca County Highway 49 | $3,700,000 | 2029 | |
78 | MN11 | Medium mill and overlay from Highway 332 to Koochiching County Road 20 | $1,500,000 | Not Selected | Not a current district priority, but will continue to monitor pavement performance |
78 | MN65 | Medium mill and overlay from Hawkins ave to Highway 1 | $16,000,000 | Not Selected | Not a current district priority, but will continue to monitor pavement performance |
78 | MN169 | Medium mill and overlay from reference post 381 to 1100 feet south of Highway 1 | $900,000 | Not Selected | |
77 | MN73 | Reclaim and overlay from National Forest Route 111 to Highway 1 | $22,000,000 | 2026 | Selected prior to policy (in 2019-2028 CHIP) |
77 | MN23 | Medium mill and overlay from Highway 39 to Becks Rd | $700,000 | Not Selected | |
77 | MN73 | Reclaim and overlay at Highway 169/Dillon Rd | $7,400,000 | Not Selected | |
77 | MN48 | Reconstruction from I-35 overpass to Morris Ave | $2,400,000 | Not Selected | |
77 | MN70 | Medium mill and overlay from Highway 107 to Highway 361 | $4,800,000 | Not Selected | |
76 | MN1 | Medium mill and overlay from Highway 65 to Highway 53 | $7,400,000 | 2020 | Selected prior to policy (in 2019-2022 STIP) |
76 | MN1 | Medium mill and overlay from Highway 53 to Highway 169 | $9,800,000 | 2026 | Selected prior to policy (in 2019-2028 CHIP) |
75 | MN65 | Reclaim and overlay from Highway 1 to Koochiching County Highway 9 | $24,000,000 | 2022 | Selected prior to policy (in 2019-2022 STIP) |
75 | MN1 | Reclaim and overlay from Reference point 198 to Reference point 207 | $4,600,000 | 2023 | Selected prior to policy (in 2019-2022 STIP) |
75 | MN1 | Reclaim and overlay from Reference point 207 to Highway 65 | $4,700,000 | 2023 | Selected prior to policy (in 2019-2022 STIP) |
75 | MN45 | Medium mill and overlay from Highway 210 to I-35 | $1,800,000 | 2026 | Selected prior to policy (in 2019-2028 CHIP) |
75 | MN1 | Medium mill and overlay from 5th St to Highway 6 | $16,000,000 | 2027 | Selected prior to policy (in 2019-2028 CHIP) |
74 | MN169 | Thick mill and overlay from Hidden Valley Rd to Lake County Highway 18/Power Dam Rd | $2,500,000 | 2024 | Selected prior to policy (in 2019-2028 CHIP) |
74 | MN18 | Medium mill and overlay from Finlayson to Pine County Highway 61 | $1,600,000 | 2029 | Selected prior to policy (in 2019-2028 CHIP), also listed as an Urban Pavement Project |
74 | MN70 | Medium mill and overlay from Highway 361 to 0.3 miles east of Highway 361 | $200,000 | Not Selected | |
73 | MN1 | Medium Mill and overlay from Highway 169 to Kawishiwi River | $5,300,000 | Not Selected | |
73 | MN37 | Medium mill and overlay from Highway 169 to Iron Jct Rd | $1,100,000 | Not Selected | |
73 | MN73 | Reclaim and overlay from 3rd Ave to Carlton County Road 129 | $5,900,000 | Not Selected | |
73 | MN217 | Medium mill and overlay from Front St to Highway 53 | $8,600,000 | Not Selected | |
72 | MN47 | Medium mill and overlay from Aitkin County Road 80 to South of 305th Ave | $3,200,000 | 2023 | Selected prior to policy (in 2019-2022 STIP) |
72 | MN6 | Medium mill and overlay from Highway 286 to Highway 1 | $7,000,000 | 2028 | Selected prior to policy (in 2019-2028 CHIP) |
72 | MN73 | Reclaim and overlay from 13th St NW to south of Frider Rd near Chisholm | $5,600,000 | Not Selected | |
70 | MN65 | Medium mill and overlay from Highway 200 to Highway 169 | $6,800,000 | 2020 | Selected prior to policy (in 2019-2022 STIP) |
70 | MN65 | Medium mill and overlay from Koochiching County Highway 8 to Highway 71 | $6,000,000 | 2021 | Selected prior to policy (in 2019-2022 STIP) |
70 | MN1 | Full mill and replace from Salveson Road to Highway 61 | $4,600,000 | Not Selected | |
70 | US2 | Reclaim and overlay from Floodwood to St. Louis County Road 845 | $9,100,000 | Not Selected | |
69 | MN200 | Medium mill and overlay from Highway 169 to Highway 65 | $9,200,000 | 2024 | Selected prior to policy (in 2019-2028 CHIP) |
69 | MN1 | Medium mill and overlay from Beltrami/Koochiching County line to Highway 71 | $2,500,000 | 2029 | Selected prior to policy (in 2019-2028 CHIP) |
69 | MN210 | Medium mill and overlay from I-35 to Vermillion St | $4,800,000 | 2029 | Selected prior to policy (in 2019-2028 CHIP), Also listed as urban pavement project |
69 | MN11 | Medium mill and overlay from US/Canada Border to Koochiching County Road 83 | $8,900,000 | Not Selected | |
69 | MN48 | Medium mill and overlay from Pine County Highway 21 to Minnesota/Wisconsin State Line | $7,300,000 | Not Selected | |
68 | MN11 | Medium mill and overlay from Reference post 167 to Koochiching County Rd 82 | $4,400,000 | Not Selected | |
68 | MN11 | Medium mill and overlay from Bigfork River Bridge to Highway 71 | $3,000,000 | Not Selected | |
67 | MN11 | Medium mill and overlay from Island View City limits to Dove Island | $1,600,000 | 2026 | Selected prior to policy (in 2019-2028 CHIP) |
67 | MN1 | Medium mill and overlay from 0.2 miles north of Kawishiwi River to 0.2 miles south of Kawishiwi River | $400,000 | 2028 | Selected prior to policy (in 2019-2028 CHIP) |
66 | MN123 | Reclaim and overlay from Highway 23 to Pine County Highway 30 | $2,300,000 | 2021 | Selected prior to policy (in 2019-2022 STIP) |
66 | MN217 | Reconstruction from Highway 65 to Front St | $1,200,000 | 2025 | Selected prior to policy (in 2019-2028 CHIP), also listed as an Urban Pavement Project |
66 | MN11 | Medium mill and overlay from Koochiching County Road 82 to Bigfork River bridge | $2,400,000 | Not Selected | |
66 | MN210 | Medium mill and overlay from Vermillion St to Highway 23 | $4,000,000 | Not Selected | |
65 | MN73 | Medium mill and overlay from Highway 1 to Highway 53 | $1,900,000 | 2020 | Selected prior to policy (in 2019-2022 STIP) |
65 | MN1 | Reclaim and overlay from Highway 71 to Highway 46 | $300,000 | 2025 | Selected prior to policy (in 2019-2028 CHIP) |
65 | MN1 | Reclaim and overlay from Itasca County Highway 38 to 0.5 miles north of Bass Lake Rd | $7,200,000 | 2029 | Selected prior to policy (in 2019-2028 CHIP) |
65 | MN11 | Medium mill and overlay from just west of McCloud Creek to 1 mile west of Koochiching County Road 4 | $900,000 | 2029 | Selected prior to policy (in 2019-2028 CHIP) |
65 | MN11 | Medium mill and overlay from Koochiching County Road 83 to 1 mile east of Koochiching County Road 83 | $700,000 | 2029 | Selected prior to policy (in 2019-2028 CHIP) |
65 | MN27 | Reconstruction from Kenwood Ave to Carlton County Highway 61 | $6,300,000 | Not Selected | |
64 | MN38 | Medium mill and overlay from 0.9 miles south of Itasca County Road 262 to Newburg Bay Rd | $1,400,000 | 2025 | Selected prior to policy (in 2019-2028 CHIP) |
64 | MN135 | Medium mill and overlay from just north of Embarrass River to Highway 1 | $8,300,000 | 2025 | Selected prior to policy (in 2019-2028 CHIP) |
64 | MN73 | Medium mill and overlay from Highway 210 reference post 25 | $3,100,000 | Not Selected | |
63 | MN73 | Medium mill and overlay from Floodwood to Saint Louis County Road 191 | $3,200,000 | 2025 | Selected prior to policy (in 2019-2028 CHIP) |
63 | MN47 | Medium mill and overlay from 305th Ln to Highway 169 | $9,100,000 | 2029 | Selected prior to policy (in 2019-2028 CHIP) |
63 | MN1 | Medium mill and overlay from Tomahawk Rd to Lake County Highway 2 | $2,600,000 | Not Selected | |
62 | MN65 | Medium mill and overlay from north of Aitkin County Road 27 to Highway 210 | $4,500,000 | 2023 | Selected prior to policy (in 2019-2028 CHIP) |
62 | MN23 | Medium overlay from Highway 18 to Main St in Askov | $4,900,000 | 2024 | Selected prior to policy (in 2019-2028 CHIP) |
62 | MN18 | Medium mill and overlay from Highway 169 to Highway 47 | $7,400,000 | 2024 | Selected prior to policy (in 2019-2028 CHIP) |
62 | MN6 | Medium mill and overlay at Highway 1 to .24 miles north Highway 1 | $1,400,000 | Not Selected | |
61 | MN73 | Medium mill and overlay from Saint Louis County Road 86 to Highway 2 | $6,100,000 | 2025 | Selected prior to policy (in 2019-2028 CHIP) |
61 | MN47 | Medium mill and overlay from Mille Lacs/Aitkin County line to Aitkin County Road 80 | $4,700,000 | 2029 | Selected prior to policy (in 2019-2028 CHIP) |
60 | MN1 | Thick mill and overlay from Highway 38 to Itasca County Highway 38 | $300,000 | Not Selected | |
59 | MN38 | Medium mill and overlay from Itasca County Highway 49 to Itasca County Highway 19 | $3,800,000 | 2025 | Smaller repair selected while longer term funding is secured for reconstruction |
58 | MN6 | Medium mill and overlay from Bigfork River Bridge to Highway 1 | $4,800,000 | 2028 | Smaller repair selected while longer term funding is secured for reconstruction |
57 | MN6 | Reclaim and overlay from Cass/Itasca County line to Highway 2 | $5,700,000 | 2021 | Selected prior to policy (in 2019-2022 STIP) |
57 | MN107 | Medium mill and overlay from Kanabec/Pine Co line to Highway 23 | $6,700,000 | 2027 | Smaller repair selected while longer term funding is secured for reconstruction |
57 | MN1 | Reclaim and overlay from Kawishiwi River to National Forest Road 553 | $3,400,000 | Not Selected | |
55 | MN38 | Medium mill and overlay from Itasca County Highway 14 to Highway 1 | $4,300,000 | 2027 | Smaller repair selected while longer term funding is secured for reconstruction |
54 | MN38 | Full mill and replace from Big Fork to Highway 38 | $600,000 | 2023 | Selected prior to policy (in 2019-2022 STIP), also listed as Urban Pavement project |
51 | MN289 | Full mill and replace from Highway 73 to Highway 289 | $400,000 | Not Selected | |
44 | MN194 | Medium mill and overlay from Highway 2 to Highway 53 | $3,000,000 | 2022 | Selected prior to policy (in 2019-2022 STIP) |
42 | MN65 | Medium mill and overlay from Highway 210 to Sandy River | $6,100,000 | Not Selected | |
37 | MN200 | Thin mill and overlay from Highway 65 to Highway 2 | $3,200,000 | Not Selected | |
36 | MN6 | Medium mill and overlay from reference post 93 to Itasca County Road 136 | $5,000,000 | 2028 | District 2 construction district funded project |
36 | MN200 | Medium mill and overlay from Cass/Aitkin County line to Highway 169 | $4,100,000 | Not Selected | |
32 | MN6 | Medium mill and overlay from Itasca County Road 136 to Highway 286 | $2,900,000 | 2020 | Selected prior to policy (in 2019-2022 STIP) |
29 | MN11 | Medium mill and overlay from Koochiching County line to reference post 146 | $7,100,000 | Not Selected | |
27 | MN123 | Thin mill and overlay from Pine County Highway 30 to Highway 23 | $1,400,000 | Not Selected | |
25 | MN11 | Medium mill and overlay from reference Town Road 129 to US/Canada Border | $1,000,000 | 2029 | Ongong maintenance concerns |
25 | MN73 | Medium mill and overlay from Highway 27 to 3rd Ave | $1,900,000 | 2029 | District anticipates the pavement condition will deteriorate faster than the model is projecting. Also listed as an urban pavement project |