- EB I-94 is reduced to three lanes between Century Ave. and Woodbury Dr.
- Traffic going east past the Woodbury Dr./Keats Ave. N. exit should use the left two lanes
- Traffic exiting onto I-494, I-694, Radio Dr./Inwood Ave. N. or Woodbury Dr./Keats Ave. N. should use the right lane
- WB I-94 is reduced to two lanes between Woodbury Dr. and Century Ave.
Ramp closures
5 a.m. Thu, Sept. 26 through Mon, Oct. 14
- The ramps to/from EB I-94 and Woodbury Dr./Keats Ave. N. are closed
- EB I-94 and Woodbury Dr./Keats Ave. N. detour: EB I-94, Manning Ave., WB I-94 and Woodbury Dr./Keats Ave. N.
- Woodbury Dr./Keats Ave. N. to EB I-94 detour: Woodbury Dr./Keats Ave. N., WB I-94, Radio Dr./Inwood Ave. N. and EB I-94
7 p.m. Wed, Sept. 18 through mid-October
- The ramp from NB I-494 to EB I-94 is closed
- The ramp from EB I-94 to SB I-494 is closed
Through October
- The ramp from 10th St. N. to NB I-694 is closed
- The ramp from Century Ave. to EB I-94 is closed
Upcoming
Information about upcoming traffic impacts will be posted as details become available.
About this project
A large pavement project on I-94 between Century Ave. and the St. Croix River will begin in July 2022. This project work is anticipated to take two and a half years to complete.
Summary of work
- Resurface pavement and ramps
- Construct new eastbound lane from I-494 to Woodbury Dr.
- Resurface frontage road (Hudson Rd.) in the project area
- Upgrade pedestrian/bicycle accessibility
- Repair drainage
- Replace signage
- Upgrade lighting
- Install median barrier