Hwy 56 reconstruction

LeRoy

Sign up for project email updates

About this project

Summary of work

Hwy 56 Reconstruction Map
Hwy 56 Reconstruction Map (click to enlarge)

A 1.2-mile stretch of Hwy 56 will be reconstructed in LeRoy to address deteriorating pavement conditions, improve drainage, enhance student crosswalk safety and make pedestrian improvements to meet current accessibility standards. At the same time, the City of LeRoy will replace aging city utilities underneath the road.

Construction for this project will take place in three stages in 2024. Learn more in the traffic impacts section below.

Construction started April 29, 2024. It anticipated to be completed late-fall 2024. MnDOT also plans to conduct additional landscaping work (tentatively in 2025), which will include adding new trees to boulevards.

The following is the planned work:

  • Reconfigure Mower Co. Rd. 12, Hwy 56 and Main St. E. intersection to improve safety by reducing vehicle speeds while maintaining efficient traffic flow
  • Construct a cul-de-sac west of Mower Co. Rd. 12
  • Create a buffer zone between traffic and parking from Mather St. to Everett St. for biking
  • Improve school crosswalk safety by constructing a bump out at Mower Co. Rd. 14 and creating a wider school parking zone
  • Replace aging storm water, sanitary sewer and water main utilities underneath Hwy 56
  • Extend water main past Ada St.
  • Replace and install new curb and gutter
  • Replace and install new sidewalks
  • Landscaping, such as adding trees to boulevards (likely in 2025)

Details can be viewed on the project layout map.

Traffic impacts

Hwy 56 construction sections
Hwy 56 construction sections (click to enlarge)

Below are project plans and detour routes. The timeframes are weather dependent. Construction will take place in three stages to better align with the city’s sewer reconstruction efforts.

People will be able to reach their destination within the construction zone. However, which direction they take may depend upon the day’s work.

Residents and business owners with questions about access to properties can contact Trevor Minnich, 507-272-3142.

Stage 1

Crews removed select trees along the corridor in early 2024.

Hwy 56 stage 2a detour map
Hwy 56 stage 2a detour map (click to enlarge)

Stage 2a

Completed: Crews worked between Co. Rd. 56 to S Mather St. (green zone) and Everett St. and east of Ada St. (yellow zone). Traffic was detoured along Co. Rd. 12, 53 and 11, as well as W County Rd. and 105th St.

View the town detour map and the extended detour map.

Hwy 56 stage 2b detour map
Hwy 56 stage 2b detour map (click to enlarge)

Stage 2b

Completed: Crews worked between Co. Rd. 56 to S Mather St. (green zone). Traffic was detoured along Co. Rd. 12, 53 and 11.

View the town detour map and the extended detour map.

Hwy 56 stage 3 detour map
Hwy 56 stage 3 detour map (click to enlarge)

Stage 3

Scheduled September to late-fall 2024
Once stages 2a and 2b are complete, crews will work between S Mather St. and Everett St. (blue zone). Traffic will be detoured south of Co. Rd. 56 and N Mather St.

View the detour map.