About this project
Summary of work
A 1.2-mile stretch of Hwy 56 will be reconstructed in LeRoy to address deteriorating pavement conditions, improve drainage, enhance student crosswalk safety and make pedestrian improvements to meet current accessibility standards. At the same time, the City of LeRoy will replace aging city utilities underneath the road.
Construction for this project will take place in three stages in 2024. Learn more in the traffic impacts section below.
Construction started April 29, 2024. It anticipated to be completed late-fall 2024. MnDOT also plans to conduct additional landscaping work (tentatively in 2025), which will include adding new trees to boulevards.
The following is the planned work:
- Reconfigure Mower Co. Rd. 12, Hwy 56 and Main St. E. intersection to improve safety by reducing vehicle speeds while maintaining efficient traffic flow
- Construct a cul-de-sac west of Mower Co. Rd. 12
- Create a buffer zone between traffic and parking from Mather St. to Everett St. for biking
- Improve school crosswalk safety by constructing a bump out at Mower Co. Rd. 14 and creating a wider school parking zone
- Replace aging storm water, sanitary sewer and water main utilities underneath Hwy 56
- Extend water main past Ada St.
- Replace and install new curb and gutter
- Replace and install new sidewalks
- Landscaping, such as adding trees to boulevards (likely in 2025)
Details can be viewed on the project layout map.