Minnesota Department of Transportation

511 Travel Info

Hwy 9 - Barnesville Complete Streets Project

Barnesville to Interstate 94

Construction details

Map of Hwy 9 project in Barnesville.
Barnesville construction official thru-traffic detour

Schedule

Construction began June 1 and lasts through September.

Traffic impacts

  • As of the evening of Friday, Sept. 22, Highway 9/Main Avenue reopens to all traffic!
  • Some work still underway throughout the entire project, so please watch for workers and slow down in the work zone!

Construction phases

Map of Hwy 9 project phasing for the 2023 construction project.
Barnesville construction staging

Construction is being completed in phases.

  • Phase 1: Highway 34 to Main Avenue
  • Phase 2: Main Avenue from Fourth Street to Front Street
  • Phase 3: Hwy 34 to Interstate 94