Traffic impacts
Starting on May 12, traffic will be reduced to a single lane controlled by temporary signals at Myhr Creek (milepost 124.83). A temporary bridge bypass will be constructed in advance of the culvert replacement under Hwy 61. Work is expected to last at this location through late July.
Starting on May 19, work will begin at milepost 126.11 at an unnamed creek. Work will start with temporary widening for a bypass and traffic reduced to a single lane controlled by temporary signals.