District 4 signs design-build completed project
SP 8824-65, Letting 07/20/07
Status
Project completed in 2008.
Project purpose, benefits
- To relocate, replace and/or add signs along five highways in MnDOT's District 4 Detroit Lakes/Morris region
- Project included an engineering assessment to determine which signs needed to be relocated, replaced, and/or added in order to meet standards
- Construction activities included relocating, replacing and/or adding signs in accordance with the engineering assessment
- Contractors were required to provide a database containing final sign installation information to MnDOT
Approximate timetable
Approximate Timetable |
|
---|---|
Phase I – Request for Qualifications | |
Request for Letters of Interest (LOI) | March 26, 2007 |
Issue Request for Qualifications (RFQ) | April 9, 2007 |
Statement of Qualifications (SOQ) due | April 27, 2007 |
Evaluation of SOQ’s | May 9, 2007 |
Notify Short Listed Submitters | May 9, 2007 |
Phase II – Request for Proposals | |
Issue RFP | May 25, 2007 |
Project Information Meeting with Proposers | June 4, 2007 |
Technical and Price Proposals due | July 10, 2007 |
Evaluation of Technical Proposals | July 11– July 20, 2007 |
Price Proposal Opening | July 20, 2007 |
First Notice to Proceed | August 13, 2007 |
Substantial Completion | June 15 , 2008 |