2024 work
These roadwork projects on state highways will have traffic impacts, but will be led, constructed and communicated by the city, township or county. Check 511mn.org for current impacts on these projects.
Construct roundabout
Construct roundabout at Hwy 25 and Wright Co. Rd. 83/138 (35th St. NE) in Buffalo to improve access to Wright County facilities and residents in the area. The project includes pedestrian walks and approaches. MnDOT projects in Buffalo
- Construct: 2024
- Impacts: Intersection will close at Hwy 25 and Co. Rd. 83/138 in Buffalo. Hwy 25 detour: uses Co. Rd. 37, Co. Rd. 12 and Hwy 55
- Led by: Wright County
Reconstruct road
Reconstruct and improve Hwy 25 from south of First St. S to north of Settlers Pkwy. in Buffalo, Wright County, includes city utilities and pedestrian sidewalks and approaches. MnDOT projects in Buffalo
- Construct: 2023-2024
- Work schedule:
- Hwy 25 between 1st St. S and Co. Rd. 12 - Complete in 2023
- Hwy 25 Wright Co. Rd. 12 to Settlers Pkwy in 2024
- Work schedule:
- Impacts: Closed between Co. Rd. 12 and Settlers Pkwy.
- Detour: Co. Rd. 12 and Hwy 12 at Montrose. Local traffic to use Settlers Pkwy, Hwy 55 and Second St. S
- Led by: City of Buffalo
Improve access
Improve access at Wright Co. Rd. 75 (Broadway St) - Part of a larger project to resurface and reconstruct Broadway
- Construct: 2023-2024
- Work schedule:
- W Broadway St. at Hwy 25 complete in 2023
- E Broadway St. - spring to mid-summer 2024
- Work schedule:
- Impacts: Lane or shoulder closures; local access detours via city streets
- Led by: Wright County
Improve access
Add left-turn lane on Hwy 65 at the N 9th St. intersection near school in Mora for safer access.
- Construct: Fall 2023-early summer 2024
- Impacts: Lane or shoulder closures
- Led by: City of Mora