Document the basis of acceptance and to adjust the Contract Unit Price of unacceptable Work allowed to remain in place in accordance with 1512.1.
Document substitution of materials per 1605.
Document changes resulting from adoption of new standards, new instructional memoranda, or recommendations from MnDOT Central Office
Document changes in the original (P) quantity due to re-measurement or re-computation in accordance with 1901.1.
Document substitution of methods or equipment at the Contractor’s request in accordance with 1805.
Document 1905 Compensation for Eliminated Items
Document incentive payments/disincentive assessments to the Contractor for pavement ride quality, quality standards, or early completion as provided in the Contract.
Document final pay quantities for landscape items
Document contract predetermined prices.
Approvals required
MnDOT Project Engineer
Local Agency if funding Change, wholly or in part
Contractor (Optional)
Consultant Contract Administrator (can only recommend approval), if applicable