Do It Right! Lessons from the field not to be repeated
Rehab work
Don’t allow the contractor to use
over 60 pound jackhammers
when removing the deck over the
beams — or the beams may get
damaged!
These concrete beams were supposed
to be left in place, and a new deck
poured on top of them.
The contractor
thought they could just repair them
with the deck pour.
We had to make
the contractor provide new beams, so
a large delay was incurred.
Haste makes waste
These beams were supposed to be
reused after the deck was removed.
There is no way to repair this much
damage to prestressed concrete beams.
The DNR would rather we don’t attempt to
neutralize the effects of acid rain with the
liberal application of concrete dust!
We now require the concrete saws to have
a stream of water be directed at the
area being cut, and the milling to be
performed in such a manner as to prevent
visible dust to be liberated.
Try not to remove more concrete than is shown in
the plan.
Quite a bit of sound concrete was
removed and a lot of rebar was damaged because
of the speed at which this joint was removed.
Remove only what was called to be removed
in the Plans.
In this case, the barrier dowels were cut off
to make it easier to replace the Expansion
joint.
What will hold the barrier on the deck now?
Try to remove only what is shown in the plans, as
long as the in-place concrete is sound.
Don’t cut epoxy coated reinforcement with a torch!
All damage to portions of the structure to
remain in place that is due to the contractor's
operations shall be repaired at the contractor’s
expense.
What happens if the barrier
takes a hit at this location now?
Try to prevent damage to sound concrete
when performing repairs!
Sure, maybe they saved some time removing
the expansion joint with a backhoe-mounted
hammer . . . but how much time will they need
to spend repairing the damage?
And how
much damage will not get repaired?
Shotcrete Repairs
Shotcrete is thirsty! Make sure that all repairs
area are cleaned and saturated 24 hours prior
to shotcreting, and re‐wetted prior to shooting.
And . . . make sure that it gets a full three-day wet cure.
Form new top flange monolithically with
new expansion joint.
This repair does not
meet the criteria for beam repair, as only
spalls less than 3 inches deep are permitted to be
poured with the deck. Obtain Bridge Office
approval for exceptions!
Form top flange monolithically with
expansion joint to repair damage to top
flange of beam (removal of entire portion
on left side of web). Excess damage caused!