Do It Right! Lessons from the field not to be repeated Barriers Some Contractors come up with innovative techniques. Here they are, slip-forming a barrier rail with a field stone finish.
Protect barrier reinforcement and surface of deck where barrier will be installed from being sprayed with AMS cure.
Slip‐formed barriers need a 7-day wet cure: 7 days with the wet side of the burline in contact with the concrete. Dry burline hanging off the barrier is unacceptable—